G. H. LINDEKUGEL & SONS, INC., Appellant v. S. D. STATE HIGHWAY COMMISSION, et al. Respondents
File No. 10969
Supreme Court of South Dakota
November 21, 1972
202 N.W.2d 125 | 87 S.D. 32
All the Judges concur.
John B. Wehde, Huron, for defendant, third party plaintiff and respondent.
Stephens, Riter, Mayer & Hofer, Pierre, for third party defendant and respondent soil consultants.
ANDERST, Circuit Judge.
The plaintiff contracted with the defendant on or about May 3, 1965, to construct a state highway department office and laboratory building. The building consists of two connected sections, referred to as the “A” section and “B” section. The contract provided the “B” section was to be completed by September 1, 1966, and the “A” section was to be completed by December 1, 1966. The plaintiff was subsequently given an extension of the completion date on each section. The “B” section was actually completed on January 8, 1967, or 85 days later than the extended dateline, and the “A” section was completed on March 19, 1967, or 63 days later than the extended dateline on that section. The defendant retained $280 per day on each section as liquidated damages under the terms of the contract, or a total retained of $41,440.
This action was initiated by the plaintiff, G. H. Lindekugel & Sons, Inc., against the defendant, South Dakota State Highway Commission, pursuant to the provisions of Ch. 110, S.L.1964, now
The defendant joined the architects, Wendell G. Fritzel, Jean R. Kroeger, Edward L. Griffin, Milton L. Berg, d/b/a
The plaintiff appealed from the judgment which dismissed its action against defendant State, and assigned as error the entry of the above mentioned order which dismissed two of plaintiff‘s claims and the judgment for defendant on the merits as to its third claim.
The judgments between defendant, as third party plaintiff, and third party defendants, architects and soil consultants, have not been appealed to this Court, thus we have no jurisdiction to grant the motion to dismiss that appeal or take other action except to note the record shows no appeal as to them.
The South Dakota Constitution,
“The Legislature shall direct by law in what manner and in what courts suits may be brought against the state.”
Of further importance is
“* * * No indebtedness shall be incurred or money expended by the state, and no warrant shall be drawn upon the state treasurer except in pursuance of an appropriation for the specific purpose first made. * * *”
This suit is brought under the provisions of
“The state of South Dakota may be sued and made defendant in any court in which an action is brought against the South Dakota state highway commission respecting any claim, right, or controversy arising out of the work performed, or by virtue of the provisions of any construction contract entered into by the South Dakota state highway commission. * * *”
Further,
“out of the state highway fund from all the moneys levied and collected by the state by general state taxation for state highway purposes, or appropriated for state highway purposes“.
See also
This court has held on numerous occasions, Griffis v. State, 69 S.D. 439, 11 N.W.2d 138; Griffis v. State, 68 S.D. 360, 2 N.W.2d 666; Kansas City Bridge Co. v. State, 61 S.D. 580, 250 N.W. 343; and Sigwald v. State, 50 S.D. 37, 208 N.W. 162, that
The expenditure of moneys levied and collected for state highway purposes, or appropriated for state highway purposes, is
“In view of Section 9, Article XI, State Constitution, * * * this court in Sigwald v. State, supra, held that moneys [levied and collected or appropriated for state highway purposes] * * * were not available for the payment of damages for breach of contract caused by the Highway Commission; that the word ‘specific’ in this Constitutional provision impelled such conclusion. True, the claim in the Sigwald case was for damages for prevention of performance and the claim in the instant case is for labor performed in excess of the requirements of the contract. The question in either instance is whether there is an appropriation for payment of damages accruing from the breach of contract.” (emphasis supplied)
Sigwald posed the question as follows:
“In the language of the constitutional provision [§ 9, Art. XI, supra], is the above [now
SDCL 31-5-8 , supra] ‘an appropriation for the specific purpose’ of paying damages arising from the breach of a contract caused by the highway commission? The word ‘specific’ compels a negative answer to the question whatever the answer might be were it not for that word.“This claim therefore [is] adjustable only by the Legislature * * *”
Sigwald further reached the conclusion “that the Legislature, in granting permission to sue the state, had in mind only such actions as might result in a judgment which could lawfully be paid“.
The first Griffis v. State opinion, 68 S.D. 360, 2 N.W.2d 666, discussed damages and extra work in the following language:
“This court has held that where funds are only available for highway construction and maintenance an action cannot be maintained by a contractor for damages for breach of contract. (citations omitted)
“Plaintiffs contend that the purpose of this action is to secure compensation for extra work and not for damages for breach of contract, and that their claim may be paid from funds appropriated for the construction and maintenance of highways under the supervision of the State Highway Commission. It is conceded that funds have not been specifically appropriated for payment of damages for breach of contract.”
Cuka v. State, 80 S.D. 232, 122 N.W.2d 83, was an action where, pursuant to an offer of the Highway Commission and a contract of purchase and sale, Cuka delivered a deed to the right-of-way involved. His claim was approved by the commission, and the state auditor issued a warrant which was delivered to the commission. Sometime later the commission decided not to proceed and returned that deed to Cuka. After citing our earlier opinions, the court wrote:
“In effect, plaintiff is asking for damages for breach of contract. As such his claim must be denied as there are no appropriated highway funds available to pay the same.”
The pertinent limitation on the expenditure of moneys levied, collected or appropriated for state highway purposes in
We believe that
The second major contention of the plaintiff‘s appeal is the trial court erred in finding the state properly withheld liquidated damages. Plaintiff properly invoked the jurisdiction of the circuit court on the merits of this claim as it was within the terms and amount of the contract. While denying recovery for four of plaintiff‘s claims, the court in the first Griffis v. State decision, supra, held a determination of the propriety of deductions made by the state for overtime days and failure to pay for riprap at the price stipulated in the contract was a proper subject of an action against the state. A voluminous record was made on this issue in the present action. It was agreed that much of the evidence was conflicting, each party arguing his version was correct. Proposed findings of fact presented by both parties to the court were rejected, the court thereafter making its own independent findings.
“‘It is well settled that the credibility of witnesses and weight of evidence is for the trial court and that a reviewing court accepts that version of the evidence, including the inferences that can be fairly drawn therefrom, which is favorable to the trial court‘s action. Consequently, an appellate court is not free to disturb findings unless they are contrary to the clear preponderance of the evidence.‘” Kent v. Association Life Insurance Co., 84 S.D. 8, 166 N.W.2d 429.
HANSON, P. J., and BIEGELMEIER, J., concur.
WOLLMAN and DOYLE, JJ., concur in part and dissent in part.
ANDERST, Circuit Judge, sitting for WINANS, J., disqualified.
BIEGELMEIER, Judge (concurring).
It is clear the court‘s opinion, in which I join, does not deny recovery to a plaintiff for any money due under, by virtue of, or within the provisions of the contract; it does deny recovery for any damages (as cited opinions stress) outside of, separate from, and in addition to those provided for in the contract. Plaintiff recognizes the latter situation exists here by stating in its brief its claim is for “additional compensation” for labor and material incurred for “additional work it had to do to complete the project“.
The result reached is consistent and in conformity with the requirement that the claim, etc. arise “out of the work performed, or by virtue of the provisions of any construction contract” (emphasis supplied) of the state highway commission clauses in
The court has not hesitated to approve recovery of sums found due contractors in contracts with the state or its agencies. Mention is made of only two. In one action where this court had
WOLLMAN, Judge (concurring in part and dissenting in part).
I concur in that portion of the majority opinion which affirms the trial court‘s ruling on the question of liquidated damages. I cannot agree, however, with the holding that
Sigwald v. State, 1926, 50 S.D. 37, 208 N.W.162, held that
To hold that
I am authorized to say that Judge DOYLE joins in this concurrence and dissent.
