143 P. 1025 | Cal. | 1914
G. Ganahl Lumber Company, Frick-Fleming Hardware Company, O.F. Pealer, and five others instituted actions to foreclose mechanics' liens upon a lot and building owned by the defendant Weinsveig. The building had been partially constructed under a contract between Weinsveig, as owner, and one Reeve, as contractor. Reeve abandoned his contract and the building was completed by Weinsveig. The actions were consolidated. The judgment of the court was that three of the lien claimants, to wit, G. Ganahl Lumber Company, Frick-Fleming Hardware Company, and Pealer were not, and that the other five claimants were, entitled to liens; that the liens of said five be transferred from the real property to a fund of $1,847.05, theretofore deposited in court by the owner, and that said fund be distributed, in proportions fixed by the decree, among the successful claimants. The three who were denied liens were given judgments against the contractor, and the owner, Weinsveig, was given judgment against them for his costs. These three plaintiffs thereupon appealed "from that portion of the judgment . . . in behalf of defendant Weinsveig and against plaintiffs G. Ganahl Lumber Company, Frick-Fleming Hardware Company, and O.F. Pealer." The appeal was transferred to the district court of appeal for the second appellate district, and that court reversed the judgment on the ground that a finding relative to the completion of the building was not sustained by the evidence. (G. GanahlLumber Co. v. Weinsveig,
The cause came on for trial again upon amended pleadings. The owner, Weinsveig, set up, in addition to other matters, the former judgment and the notice of appeal therefrom, limited as above set forth. He alleged that, pending the appeal, the money deposited in court had been distributed among the five successful plaintiffs pursuant to the judgment, and that the judgment had been satisfied by said plaintiffs. *666
The court, upon the second trial, found in favor of these allegations. From them it reached the conclusion that, inasmuch as no appeal had been taken by G. Ganahl Lumber Company, Frick-Fleming Hardware Company, or Pealer, from the judgment in favor of other lien claimants, the part of the judgment distributing the fund of $1,847.05 among such other claimants had become final, and the parties appealing from the original decree could litigate (in addition to their liability for costs), only their right to hold the owner for the difference between said $1,847.05 and the amount for which he might, on a second trial, be found to be liable. Since the case was one in which the contractor had abandoned his contract, the amount applicable to liens was a portion of the contract price, to be computed according to the method defined in section 1200 of the Code of Civil Procedure. At the second trial that amount was determined to be $2,836.89, or $989.84 more than the sum which, by the first judgment, had been ordered distributed among the five successful claimants. This excess, the court concluded, was all that the three plaintiffs who had appealed from the original judgment were entitled to look to. Finding that they had established their right to liens, it apportioned this amount of $989.84 among them in the ratio of their respective claims, and entered a decree of foreclosure in their favor for the sums thus found due to them on account of their liens. From this judgment the plaintiffs G. Ganahl Lumber Company and Frick-Fleming Hardware Company appeal. The defendant Weinsveig also appeals from the judgment. All of said parties appeal, further, from an order denying their respective motions for a new trial.
The only question raised on the appeal of the plaintiffs is whether the court below was right in limiting their claims against the owner to the difference between the total amount found applicable to liens, and the amount awarded by the first judgment to other lien claimants. The appellants contend that, by the reversal on the first appeal, the first judgment was set aside in its entirety, and the cause set free for a new trial of all the issues. This position requires an examination of the scope and effect of the former notice of appeal. That notice, as has been stated, was not directed to the whole judgment, but only to "that portion" thereof "in behalf of defendant Weinsveig and against" the three plaintiffs there appealing. *667
It is now well settled in this state that a party may appeal from a specific part of a judgment. (Code Civ. Proc., sec. 940;Early v. Mannix,
These considerations dispose of the appeals by plaintiffs. They likewise meet the defendant owner's contention that the only matter left open for adjudication after the first appeal and the order of reversal thereon was the judgment in favor of the owner for costs.
Some further points are raised by the defendant Weinsveig in support of his appeal.
It is urged that the rule of section 1200 is an invasion of the constitutional rights of the owner, at least in a case where the application of the section results in the payment by the owner of a total sum in excess of the contract price. We have heretofore held that the section does not deprive lien claimants of any protection guaranteed them by the constitution. *669 (Hoffman-Marks Co. v. Spires,
The sufficiency of the evidence to sustain various findings is questioned by the owner. Thus, it is claimed that the finding that the building was completed on March 1, 1908, is contrary to the evidence. The actual date of completion, as the owner argues, was March 7th. The importance of this point lies in the fact that the two appealing plaintiffs filed their claims of lien on the 2d day of March, or before the completion of the building, if the appellant owner be correct in his view of the evidence. While there is much to support his contention in this regard, we think the record does contain enough testimony the other way to have justified the trial court in its finding that the building was substantially completed on March 1st, leaving undone at that date only "trivial imperfections." The testimony of the architect, while not very definite, was open to this construction, and the trial court so accepted it, as it had the right to do.
The attack on the finding of the amount applicable to liens, upon abandonment by the contractor, cannot be upheld. The court found the value of the work and materials already done and furnished, estimated "as near as may be by the standard of the whole contract price," to be $6,591.15. The whole contract price was $10,249. Two expert witnesses called by plaintiffs, testified that in their opinion the work done and materials furnished up to the abandonment amounted to sixty-seven or sixty-eight per cent of the total labor and materials required for the complete building. A witness for the owner fixed the proportion at sixty per cent. The value of the work and materials, as fixed by the court, was a trifle over sixty per cent of the total contract price. This was fully authorized by the testimony to which we have referred. The amount paid by the owner to the contractor ($3,754.26) was not in dispute, and the difference between $6,591.15 and $3,754.26, *671 or $2,836.89, was properly determined to be the amount which, under the terms of section 1200, was applicable to the payment of liens.
From the sum payable to lien claimants the owner sought to deduct three hundred dollars, claimed as damages for loss of rents occasioned through the failure of the contractor to finish the building within the time agreed. This item cannot be deducted from the fund available to lienors where the contractor has abandoned his contract. (Marshall v. Vallejo Commercial Bank,
There are no other points of sufficient consequence to merit attention.
The judgment and the order appealed from are affirmed.
Shaw, J., and Angellotti, J., concurred.
Hearing in Bank denied.