G. De Vincentis & Son Construction, Inc. v. City of OneontaG. De Vincentis & Son Construction, Inc. v. City of Oneonta
Appeal from an order of the Supreme Court (O’Brien, III, J.), entered November 21, 2001 in Otsego County, which, inter alia, partially granted defendant’s motion for summary judgment dismissing the complaint.
As a result of plaintiffs successful bid on the Center Street Reconstruction Project in the City of Oneonta, Otsego County, plaintiff and defendant entered into a contract dated June 24, 1998 which specified that the project would be completed by August 21,1998 and plaintiff would receive $282,016.75. Thereafter, by letters dated August 7 and 11, 1998, plaintiff informed defendant that it had encountered certain conditions requiring work not included in the contract. The conditions resulted in changes to the water service, extra milling and installation of several new driveway aprons. Plaintiff requested additional moneys and an extension of time to complete the project. A meeting was held on August 17, 1998 attended by, among others, defendant’s engineer, James Suozzo, and its engineering
Plaintiff filed a complaint on December 12, 2000 seeking damages for breach of contract, unjust enrichment, quantum meruit and estoppel based upon, among other things, the extra work on the Center Street project contract. In its answer, defendant cited as a defense plaintiffs failure to meet conditions precedent for payment of the extra work under the contract. Plaintiff subsequently moved for partial summary judgment and defendant cross-moved for summary judgment dismissing the complaint. Defendant submitted an affidavit from Suozzo wherein he stated that the December 16, 1999 letter was not a partial approval of plaintiffs claim, but an offer to settle that was rejected. Supreme Court, among other things, granted defendant’s cross motion with respect to all causes of action seeking compensation for the extra work on the Center Street project citing plaintiffs failure to comply with the notice and documentation requirements listed in the contract as conditions precedent. Plaintiff appeals.
Initially, plaintiff maintains that its contract claims should not have been dismissed because defendant, by its conduct, waived its right to insist upon strict compliance with the notice and documentation requirements.
Notably, while defendant produced proof that plaintiff did not comply with all of the provisions of the notice and documentation requirements, the contract did not explicitly require plaintiff to strictly comply with its terms, nor did it include a provision prohibiting estoppel or waiver on the part of the City (see e.g. A.H.A. Gen. Constr. v New York City Hous. Auth.,
Here, we find that plaintiff has raised questions of fact as to whether defendant had actual knowledge of plaintiff’s extra work claims and whether defendant, through the conduct of its agents, waived its right to insist upon strict compliance (see Amadeus v State of New York, supra). The record contains proof of plaintiffs submissions, including letters and invoices outlining costs incurred by plaintiff for extra work and the participation of defendant’s engineer and engineering administrator in discussions concerning these matters. While defendant attempts to distance itself from the actions of Suozzo, the contract specifically notes that the engineer’s approval is a condition precedent to determination of claims. With respect to the December 16, 1999 letter, the City Attorney for defendant, in a reply affidavit, acknowledges that Suozzo, “after a thorough review of the claims made by [plaintiff], pursuant to
Given the unresolved factual issues concerning the extent of the authority held by defendant’s agents, we deem summary judgment with respect to plaintiff’s sixth cause of action seeking to bind defendant to the amounts “approved” by its engineer to be premature.
Spain, Carpinello, Lahtinen and Kane, JJ., concur. Ordered that the order is modified, on the law, without costs, by reversing so much thereof as granted defendant’s cross motion for summary judgment dismissing the first, second, third and sixth causes of action; cross motion denied to that extent; and, as so modified, affirmed.
Notes
. Plaintiff abandoned any objections to the dismissal of the fourth and fifth causes of action sounding in quantum meruit and unjust enrichment by not raising them in its brief.
. Although defendant maintains that the waiver issue was not raised before Supreme Court, an examination of plaintiff’s bill of particulars reveals the existence of a waiver argument.