421 F.2d 710 | Ct. Cl. | 1970
Lead Opinion
delivered tbe opinion of tbe court:
Tbe Government called for bids, in June 1968, for tbe installation and repair of sewers and incidental roads at Ft. Lewis in tbe State of Washington. Several bids were received, including one from plaintiff, an established general contractor. After tbe opening (late in June), tbe contracting officer told plaintiff orally that it would be awarded tbe contract. Tbe next day defendant placed a written notice of award to plaintiff in the mail, but shortly retrieved it before delivery, and ultimately informed plaintiff that it would not have tbe contract. Tbe reason for this apparent change of mind was this: Plaintiff was tbe second low bidder in terms of dollar amount, tbe lowest being Hanson Excavating Co.; determining, on the opening, that Hanson’s bid was non-responsive, tbe contracting officer decided to reject it and to make tbe award to plaintiff; tbe oral notification and tbe putting of tbe written notice in tbe mails then followed; however, Hanson protested almost immediately and tbe written notification was taken from tbe post office in order to give the procuring officials time to consider this protect; after some deliberation,
Insisting that it bad a valid contract — either through tbe oral notification or tbe deposit of tbe written notice of award with tbe post — -plaintiff demanded that it be allowed to perform and to receive a formal contract. Upon tbe defendant’s refusal, this action was commenced, seeking tbe profits plaintiff says it would have made. There is no controversy over tbe pertinent facts and both parties have moved for summary judgment.
As in Nesbitt v. United States, 170 Ct. Cl. 666, 668-69, 345 F. 2d 583, 584-85 (1965), cert. denied, 383 U.S. 926 (1966), we are saved from having to consider or decide most of tbe issues which have been proffered. We can assume with plaintiff, for tbe purposes of the case and without agreeing or disagreeing, that a contract was made either when tbe contracting officer told plaintiff on tbe telephone that it would be given tbe award or shortly thereafter when the written notice of award was dropped in tbe mails. We can also assume, on tbe same neutral basis, that an award to plaintiff would have been valid.
The contract tbe Government made, if it made one, necessarily included tbe standard termination-for-convenience clause. Tbe written contract-form which would have to follow an award contained such an article, and plaintiff expressly agreed in its bid that, if it obtained tbe award, it would
The rule we have followed is that, where the contract embodies a convenience-termination provision as this one would, a Government directive to end performance of the work will not be considered a breach but rather a convenience termination — if it could lawfully come under that clause — even though the contracting officer wrongly calls it a cancellation, mistakenly deems the contract illegal, or erroneously thinks that he can terminate the work on some other ground.
There can be no doubt that the Government, in the circumstances here, could have immediately terminated plaintiff’s contract for convenience if a valid agreement had been entered into via the oral notification or the deposit of the written award-notice in the mails. The documents filed by the defendant in support of its motion
In addition, it is quite probable that the Government would actually have used the termination clause, rather than com-
Plaintiff, which never started performance, incurred no costs of performance and therefore asks only for its anticipated (but unearned) profits. It is, of course, firmly settled that these are not allowable under a convenience-termination. See, e.g., Nesbitt v. United States, supra, 170 Ct. Cl. at 671, 345 F. 2d at 586; Nolan Bros., Inc. v. United States, supra, 186 Ct. Cl. at 607-08, 405 F. 2d at 1253-54; General Builders Supply Co. v. United States, supra, 187 Ct. Cl. at 485-86, 409 F. 2d at 251-52. Our holding in Nesbitt is precisely applicable : The profit the claimant would have made under the contract, but did not in fact earn, “is a type of recovery to which he would clearly not be entitled on a convenience termination and, accordingly, to which he now has no right. Since he seeks nothing else, he cannot have any judgment.” 170 Ct. Cl. at 671, 345 F. 2d at 586.
The plaintiff’s motion for summary judgment is therefore denied and the defendant’s is granted. The petition is dismissed.
There could be two possible illegalities in the contract: (i) if Hanson was correct in its protest, there would be the question whether the grant of the contract to plaintiff, not then the lowest responsive bidder, was lawful; and (ii) there would also be the further issue of whether the invitation for bids was so ambiguous and unspecific that no valid award could be made to anyone.
The Instructions to Bidders stated: “The bidder whose bid is accepted will, within the time established in the bid, enter into a written contract with the Government and, if required, furnish performance and payment bonds on Government standard forms in the amount indicated in the invitation for bids or the specifications.”
Perhaps it is now unnecessary to spell out three caveats to this rule: (A) We are not, of course, referring to mere temporary suspensions of work but to permanent directions to stop. (B) Under the old form contracts, the rule was different for default-terminations in those instances where there was in fact no default. See Schlesinger v. United States, 182 Ct. Cl. 571, 584-85, 390 F. 2d 702, 710 (1968) ; J. D. Hedin Constr. Co. v. United States, 187 Ct. Cl. 45, 57-59, 408 F.2d 424, 431-32 (1969) ; General Builders Supply Co. v. United States, 187 Ct. Cl. 477, 485-86, 409 F. 2d 246, 251 (1969) ; Vann v. Unites States, ante, at 579-80, 420 F. 2d at 986-87. (C) The Government has in some circumstances, such as a true default or illegality of the contract, the right to terminate or cancel without any payment under the termination-convenience clause. See, e.g., Schoenbrod v. United States, 187 Ct. Cl. 627, 635, 410 F. 2d 400, 404 (1969) ; Prestex Inc. v. Unites States, 162 Ct. Cl. 620, 320 F. 2d 367 (1963).
See, also, Litchfield Mfg. Corp. v. United States, 167 Ct. Cl. 604, 609 n. 9, 338 F. 2d 94, 96 n. 9 (1964) ; Acme Process Equip. Co. v. United States, 171 Ct. Cl. 324, 355, 360 n. 29, 347 F. 2d 509, 527-28, 530 n. 29 (1965), rev’d on other grounds, 385 U.S. 138 (1966) ; Nolan Bros., Inc. v. United States, 186 Ct. Cl. 602, 606-10, 405 F. 2d 1250, 1253-55 (1969) ; J. D. Hedin Constr. Co. v. United States, 187 Ct. Cl. 45, 57-59, 408 F. 2d 424, 431-32 (1969) ; General Builders Supply Co. v. United States, 187 Ct. Cl. 477, 485-86, 409 F. 2d 246, 251 (1969).
Plaintiff does not controvert, or attempt to contest, the facts reflected in the defendant’s documents (and aflidavits) which are relevant to this point and are properly to be considered under our rules.
Concurrence Opinion
concurring:
I concur in both the reasoning and the result of Judge Davis’ opinion. However, I feel that the court should go one step further and direct itself to the question of whether a
Without going into great detail, I would simply hold that no contract — either oral or written — ever came into existence in the present case. The fact that the written contract award notice was retrieved from the mails by defendant before receipt by plaintiff is enough to prevent the formation of a valid written contract. This court has consistently held that where a bid offer is accepted by the transmittal of an acceptance through the mail, a valid contract is not formed until the acceptance is received by the offeror. Pacific Alaska Contractors, Inc. v. United States, 141 Ct. Cl. 303, 157 F. Supp. 844 (1958); Rhode Island Tool Co. v. United States, 130 Ct. Cl. 698, 128 F. Supp. 417 (1955); Dick v. United States, 113 Ct. Cl. 94, 82 F. Supp. 326 (1949).
The question of whether an oral contract was formed should likewise be answered in the negative. Both the provisions of the contract
For tbe reasons just stated, I feel tbat tbe petition should also bave been dismissed on tbe grounds tbat no contract was ever formed, and not just on tbe assumption tbat, bad a contract been in existence, it would have been terminated by tbe Government under tbe convenience-termination provision.
Standard Form 21, which was the bid form used in this case, provides as follows:
“The undersigned agrees that, upon written aeeeptcmee of this hid, mailed or otherwise furnished within.calendar days * * * after the date of opening of bids, he will within 10 calendar days * * * execute Standard Form 23 * * (Emphasis added.)
10 U.S.C. §2305(c) (1964), which deals with general military procurement, states:
“Bids shall be opened publicly at the time and place stated In the advertisement. Awards shall be made with reasonable promptness hy giving written notice to the responsible bidder »**.*«»” (Emphasis added.)
The exact same language is used in 41 U.S.C. § 253 (1964) which deals with procurement procedures for public contracts.
In addition, the Armed Services Procurement Regulations, 32 C.F.R. § 2.407-1 (1969), likewise require that any notice of award pursuant to an invitation for bids be in writing. The provision reads in part:
“* * * Awards shall he made hy mailing or otherwise furnishing to the bidder a properly executed awtvrd document * * * or notice of award on such form as may be prescribed by the procuring activity. When a notice of award is issued, it shall be followed as soon as possible by the formal award. * * * All provisions of the invitation for bids * * * shall be clearly and accurately set forth * * * in the award document, since the award is an acceptance of the hid, and the hid and the award constitute the contract." (Emphasis added.)