Funk v. HouseFunk v. House
- Reporters:
- ,
- Before:
- Dunklin
A written contract was entered into by J. W. Gregg, contractor, and Dr. P. C. Funk, owner, by the terms of which the contractor agreed to build a house for the owner for a consideration of $3,379.65, and to furnish the labor and material therefor. The contract provided that the work was to be done under the supervision and to the satisfaction of the architects, Waller & Fields, or their superintendent, who prepared the plans and specifications for the building. It was further stipulated in the contract that 80 per cent, of the contract price should be payable for labor and material used in the building upon certificates of the superintendent, itemized statements to be furnished by the contractor to the superintendent as a basis for such certificates, and the remaining 20 per cent, of the contract price was payable 15 days after the completion and acceptance of the entire work.
The owner paid 80 per cent, of the contract price under the stipulations above mentioned. House & Son furnished to Gregg, the contractor, labor and material which were employed in the construction of the building and for which Gregg paid nothing. In a suit instituted by them, they recovered a judgment against Gregg for such labor and material in the sum of $209.38 and costs of suit aggregating $5.
The present suit was a garnishment proceeding instituted by House & Son against Funk, as garnishee, to subject any balance due by the garnishee to Gregg, under the contract, to the payment of that judgment, and, from a judgment in favor of the plaintiffs against the garnishee for $214.68, the garnishee has appealed.
In his answer, after denying any indebtedness to Gregg, the garnishee alleged specially the contract between himself and Gregg for the construction of the house, the . payment by the garnishee of 80 per cent, of the contract price, further alleging that Gregg had failed to complete the house in accordance; with the terms of the contract and had abandoned the same; that the garnishee had been forced to the necessity of taking charge of the work for the purpose of completing the same according to the terms of the contract, and had done so; that, according to the terms of the contract, the garnishee had a right to retain 20 per cent, of the contract price as security for the faithful completion of .the house and to be applied under the direction of the architect; that the garnishee had been damaged in a sum in excess of the balance of the contract price, which had been estimated by the architect as the amount due the garnishee for such breach of the contract by Gregg. He further alleged that Gregg had no interest in the building contract; that, in executing the same, he had done so merely as the agent of the J; J. B. McCullar Lumber Company; and that, if the garnishee owed any sum under the contract, the same was due to such company and not to Gregg.
The answer of the garnishee was controverted by plaintiffs, who alleged that they had good reason to believe, and did believe, that Funk was indebted to Gregg in the sum of at least $700 for labor and material furnished and done in the construction of the building, about $309 of which was furnished by the plaintiffs to Gregg with full knowledge and notice to Funk at the time.
Gregg also filed a controverting affidavit in which he claimed Funk was indebted to him under the contract in a sum in excess of $700; that he (Gregg) had completed the contract according to its terms; that he did not abandon the building before the work was completed; and that, if any certificate had been given by the architect that the building was not completed according to the contract and the full contract price not earned, the same was given as the result of a fraudulent conspiracy betwéen the architect and Funk for the purpose of defeating the collection of such balance of the contract price.
The garnishee addressed a special exception to the allegation in plaintiffs’ petition that they had furnished to Gregg $309 worth of work and material, which were used in the erection of the building, with full knowledge of the garnishee; the ground of exception being that by such allegations plaintiffs were attempting to set up an original cause of action in themselves against the garnishee. The court overruled this special exception, and also overruled the garnishee’s objection upon the same ground to the testimony of the plaintiff J. T. House that he did furnish Gregg material and labor for completing the house, amounting to $309, with garnishee’s knowledge, and that such work and material so furnished were satisfactory to the garnishee and accepted by him. *484 Those rulings are made the bases of appellant’s first and second assignments of error. The pleading to which the exception was addressed was a reply to the issue tendered by the garnishee that Gregg had no interest in the contract, but that, in making the same, he acted merely as the agent of the McCullar Lumber Company, in whom alone the right to recover any balance due on the contract was vested.
“It is also agreed that if the contractor shall at any time refuse or neglect to furnish the, proper material or workman or otherwise fail or refuse to comply with the plans and specifications, such failure being certified to by the architect,, the owner shall be at liberty (after three days’ written notice to the contractor) to provide the proper material and workman and deduct the cost from the money then due, or to become due, the contractor, or for sufficient reasons to terminate the employment of the contractor and take charge of the premises and all material thereon-, and complete the building according to plans and specifications, charging the expense to the contractor.”
And it was expressly pleaded by the garnishee that it bad become necessary for him to take charge of the work for the purpose of completing the house according to the terms of the contract, and that he had done so. This clearly shows that the garnishee elected to avail himself of the remedy given by the stipulation last quoted. It also appears from the evidence that the appellant did take charge of the house for the purpose of completing the same under the direction of the architect, who further directed him to apply the balance withheld from the contract price to payment for labor and material necessary tó so complete the work and pay over any excess remaining of such balance to the contractor. When appellant elected to take charge of the house upon Gregg’s breach of the contract, the contract was thereupon terminated. If the amount necessary to complete the house was less than the amount withheld by appellant, then appellant owed Gregg the difference.
“It is agreed by the parties that 20 per cent of the contract price should be held by the owner as security for the faithful completion of the work and may be applied under the direction of the architect in liquidation of any damages under this contract”
In support .of this contention appellant cites Kilgore v. Baptist Educational Society, 89 Tex. 468, 35 S. W. 145. The contract involved in that case was a building contract, in which the owner and the contractor had expressly agreed that the owner should pay the contractor as the work on the building progressed according to the estimates of the architect, whose estimates were by the terms of the contract made binding upon the owner. The court held that the jury should have been instructed that the estimates given Were presumed to be correct, in the absence of any showing that the architect, in giving them, acted fraudulently. We are of the opinion that the stipulation now under, discussion cannot properly be construed as an agreement that any estimates by the architect- of the amount of damages sustained by the plaintiff by reason of Gregg’s breach of his contract should be binding upon the parties, and hence the decision cited is not applicable.
We are of the opinion further that the judgment is supported by the testimony, and, as we have found no error in the record, it is affirmed.