144 Ga. 691 | Ga. | 1916
Fulton County, through its commissioners, entered into a . written contract with a contractor, whereby the contractor bound himself, in consideration of the sum of $122,000 to construct the concrete framework required in a court-house building. It is provided in the contract that the work shall begin within a certain time and be completed in 175 working days, “time being of the essence hereof,” and in default of timely completion the contractor is to pay the county thereafter until completion $50 per day as liquidated damages. “The sums which may become due to the owner on account thereof may be retained by the owner out of any sums which may be or become owing to the contractor hereunder, or may be recoverable by suit therefor.” If the contractor should at any time refuse or neglect to supply a sufficiency of workmen or materials of the proper quality, or to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements of the contract, or become bankrupt or insolvent, the owner shall be at liberty, after three days written notice, to provide any such labor or material, “and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; . . or if the contractor shall become bankrupt or insolvent, the owner shall also be at liberty to terminate the employment of the contractor, to annul and' cancel this contract for the
1. The assignment to the bank by the contractor of amounts alleged to be due under the contract was subject to the terms of the contract between the county and the contractor, with notice of which the assignee was chargeable.
2. Under the contract the county might have completed the work itself; and had it done so, the contractor would not have been entitled to receive any further payments until the work was wholly finished, and then only if the balance to be paid under the contract should exceed the expense incurred by the county for finishing the work. If the expense should be more than such unpaid balance, the contractor would be liable to the county for the difference.
(а) Where instead of itself completing the work the county permitted the surety on the contractor’s bond to do so, which was done at a necessary expense exceeding the balance of the contract -price after deducting payments made to the contractor before default, and including' the sums sought to be recovered in this suit, such surety became subrogated as to the right which the county would have had to the balance of the contract price had it completed the work itself; and where such balance was paid by the county to'the surety, its right thereto was superior to the claim of the assignee of the contractor before his failure. Title Guaranty Co. v. Dutcher, 203 Fed. 169; First National Bank v. City Trust etc. Co., 114 Fed. 529 (52 C. C. A. 313); Henningsen v. United States Fidelity etc. Co., 143 Fed. 812, s. c. 208 U. S. 404 (28 Sup. Ct. 389, 52 L. ed. 547); Prairie State Bank v. U. S., 164 U. S. 227 (17 Sup. Ct. 142, 41 L. ed. 412).
(б) Under the facts above stated, where a suit was brought by the assignee of the contractor against the county to recover the amount sought to be assigned, the petition was demurrable.
Judgment affirmed.