Fullerton Lumber Co. v. Calhoun

89 Mo. App. 209 | Mo. Ct. App. | 1901

BROADDUS, J.

This is a suit by the plaintiffs, composing the Eullerton Lumber Company, to enforce a mechanic’s lien for material furnished to the contractor, defendant Calhoun, for the construction of certain buildings for the defendant Epstein in the city of St. Joseph, Missouri. The defendant Epstein and defendant Gernandt, who claimed some interest in the property, answered at length and substantially as follows: They admit that the defendant on the twenty-eighth day of June, 1899, contracted with defendant *213Calhoun for tbe erection of tbe building and improvements in question for the sum of $3,150, wbicb tbe said Calboun was to receive as full compensation for tbe buildings and improvements, said Calhoun to furnish tbe materials. Defendant Epstein further answering alleges, that bis co-defendant Calboun “is principal of tbe plaintiffs acting in tbe name of Eullerton Lumber Company under wbicb name they were then and now doing business, and as sureties entered into a bond on tbe fifth day of July, 1899, wbicb said bond was executed and entered into before any work was performed or any labor done upon said residence or barn and was agreed to be entered into at tbe time said contract was entered into, and was agreed to be and was a part of said contract, wbicb bond is attached to said contract and is a part thereof * * *, by tbe terms of wbicb bond tbe said Calboun and these plaintiffs have bound themselves to tbe defendant in tbe sum of $2,500, 'for tbe payment of wbicb,” etc. Tbe conditions of tbe bond are substantially: Eor a faithful performance on tbe part of Calboun of tbe contract for tbe building and improvements in question and to indemnify defendant Epstein against all claims, demands, judgments, liens, and mechanics’ liens, and all costs incurred by him in suits in reference to tbe buildings. In fact, it amounts to a complete indemnity to Epstein for any damages be may sustain for non-performance of tbe contract for tbe buildings. It is further averred that tbe plaintiffs and defendant Calboun, by reason of tbe execution of said bond, waived all claim and right to have a lien enforced against defendant’s property.

There were two additional defenses set up in tbe answer, but as they were not sustained by evidence they are omitted.

Tbe plaintiffs introduced their lien and other evidence to support their cause. Tbe defendants introduced no evidence upon tbe issue now before this court, and it, therefore, follows that tbe bond set out in tbe defendants’ answer was not read *214to the jury. It is proper, however, to state that upon cross-examination of plaintiffs’ witnesses, the defendant elicited evidence tending to show the state of the accounts between contractor Calhoun and Epstein, the owner of the building. It is sufficient to say that the trial court, in the instructions given to the jury, limited plaintiffs’ right of recovery as-a lien against the lots to the amount found due by Epstein to Calhoun, the contractor, which action of the court raises the only materia1 question in the case which involves not only the legal effect of the bond set out in defendant’s answer, but also the propriety of the action of the court in considering the effect of said bond, it not having been introduced as evidence.

The plaintiffs’ reply admits the execution of the bond, but states that there was no consideration for the same, as it was not executed at the time the contract in question was entered into and attached as a part thereof, and that plaintiffs had no knowledge of the contract for building at the time it signed the same as security. The defendant Epstein in his answer alleges that the contract for building was entered into on the twenty-eighth day of June, 1899, and the bond was executed on the fifth day of July, 1899, before any work was done on the building, and that it was attached to and became a part of the contract. The verdict of the jury was for the plaintiffs against Calhoun for $815.33, and for plaintiffs against premises for the sum of $138.52 as a lien.

The plaintiffs contend that the court was not authorized to predicáte its instruction to the jury on behalf of the defendant and refuse instruction offered on behalf of the plaintiffs, for reasons based upon said bond, as the same had not been read as evidence and was not shown to have been attached and made a part of the contract of the builder Calhoun with said Epstein. It is true, the plaintiffs admit the execution of the bond as sureties of Calhoun, but they say that there was *215no consideration for the same, as the contract was dated the twenty-eighth of June, 1899, and the bond was not executed until July 5, 1899, and that it was not attached to or made a part of the contract. If this be an admission that the bond was a part of the contract, then the action of the court was not error. There was no dispute at any time that plaintiffs had executed the bond as sureties. The bond does not describe the contract in suit, but only refers to it as “a certain contract for the erection of certain buildings in said contract described, which contract is hereto annexed.” As the plaintiffs admitted by their reply the execution of the bond, but denied their liability because it'was not attached to and made a part of the original contract, and because the bond was dated several days after the contract, could make no difference as the plaintiffs, as securities, admitted in said bond that their undertaking was attached to the contract.

The terms of the contract and bond were set out in defendants’ answer. The plaintiff read the contract to the jury. The bond was not read as evidence, as before stated. The plaintiffs by their reply not only admitted the bond, but its terms as set out by defendants’ answer, and only denied its force and effect. And besides, the plaintiffs waived the formal introduction of the bond and treated the same as in evidence by their instruction number two, which they asked the court to give and which instruction is as follows:

“The court instructs that, under the law, pleadings and evidence in the case, you will find that the plaintiffs are not liable as sureties on the bond set forth in defendants’ answer.” And again in their instruction number four they ask the court to say to the jury that, “if they believe from the evidence that the bond set forth in defendants’ answer was executed after Calhoun and Epstein made their contract, and after Calhoun had entered upon the performance of said contract, then there *216was no consideration for said bond and plaintiffs are not liable as sureties thereon.” The plaintiffs tried their case upon the theory that the bond in question was in evidence and before the court, and they will not be permitted to have their ease retried here upon a different theory. Hackett v. Phil. Underwriter, 79 Mo. App. 16; Hilz v. Railway, 101 Mo. 36; Hill v. Drug Co., 140 Mo. 433; Pope v. Ramsey, 78 Mo. App. 157.

The undisputed evidence in the case was, that it was the understanding at the time the contract was entered into that the bond was to be given; and there was no evidence that the work had been commenced on the building before the bond was made. It would, under these circumstances, be immaterial whether the bond was attached to the contract or not. The facts showed a sufficient consideration to bind the plaintiffs as sureties on the bond. Overbeck v. Mayer, 59 Mo. App. 290; Sevell v. Porter, 52 Mo. App. 632. And whether work upon the buildings had commenced before the execution of the bond or not was immaterial, for the reason that the agreement of Calhoun, the contractor, at the time the contract was entered into, to give the bond, was a sufficient consideration for the execution thereof by the plaintiffs as sureties. Robertson v. Finley, 31 Mo. 384; Peck v. Harris, 57 Mo. App. 467; Ring v. Kelly, 10 Mo. App. 413.

We find no error on the trial of the cause. Affirmed.

All concur.