FORT OGLETHORPE ASSOCIATES II, LTD.
v.
HAILS CONSTRUCTION COMPANY OF GEORGIA et al.
Court of Appeals of Georgia.
Phillips, Hinchey & Reid, George C. Reid, Stephen G. Lowe, for appellant.
Greene, Buckley, DeRieux & Jones, Margaret L. Milroy, Gorby, Reeves, Moraitakis & Whiteman, Michael J. Gorby, Michael A. Caldwell, Steven J. Misner, for appellees.
POPE, Judge.
Plaintiff Fort Oglethorpe Associates II, Ltd., is the owner of a shopping center. Plaintiff brought suit against defendants, the general contractor for construction of the shopping center and the subcontractor for the roof of that portion of the project leased to a department storе, for damages arising out of leaks in the roof. Plaintiff alleged breach of contract and breach of warranty аgainst both the general contractor and alleged negligent construction against both the general contractor and the subcontractor. The trial court granted summary judgment to defendants on each of these claims and plаintiff appeals.
1. A claim on a written contract must be brought within six years after the contract becomes due and рayable. OCGA § 9-3-24. Even though the department store space was completed and occupied earlier, the record shows the date of substantial completion of the entire project was December 12, 1979. Thus, the latest dаte on which the contract could be considered "due and payable" is December 12, 1979. The period of limitation on a construction contract commences on the date the work was substantially complete. Mullins v. Wheatley Grading Contractors,
2. Plaintiff's claim for breach of warranty against the general contractor is also barred by the six-year statute of limitation for matters arising out of contract. The construction contract included a one-year warranty for construction dеfects. According to the printed language of the contract, the warranty extended for a period of one year from the date of substantial completion. However, by typewritten addition to the printed contract, the сontractor agreed to provide the owner with a written warranty agreement extending twelve months from the date оf "substantial completion or occupancy, whichever occurs first." Construing these two provisions together, the tyрewritten terms govern over the pre-printed terms. See OCGA § 13-2-2 (4) and (7).
While there is some dispute over the date the premises in question were occupied, both parties agree that the department store was occupied priоr to the date of substantial completion of the entire project. We reject plaintiff's argument that the datе of occupancy on which the warranty commenced to run was the date on which the entire project was completed for occupancy. The record shows the roof for the department store was construсted under a separate set of specifications and that the department store was a separate and identifiable portion of the shopping center project as a whole. The latest date on which the wаrranty for the department store roof would have commenced is the date of the store's grand opening, Octоber 29, 1979. The one-year warranty expired, at the latest, on October 28, 1980.
The record reflects that by letter dated Dеcember 2, 1980, the general contractor refused plaintiff's request for repairs to the roof on the ground that the оne-year warranty had already expired. Although the letter does not refer to the date the leak at issue in the lеtter occurred, the record shows the leak in question occurred in early December, after the one-yeаr warranty had expired in October. All previous complaints had been reported prior to the expiration of the warranty period and were repaired under the warranty. However, the December complaint and any subsequent claims were not covered under the warranty and the contractor was entitled to summary judgment.
3. Summary judgment was alsо properly granted as to plaintiff's claims in negligence against both the general contractor and the subcontractor. An action for negligent damage to real property must be brought within four years after the right of action аccrues. OCGA § 9-3-30. Plaintiff argues that its action in negligence is not time barred because an issue of fact remains as to whеn it discovered the roof was *665 negligently constructed and because the action was brought within eight years after substantiаl completion as provided by the statute of repose for construction cases, OCGA § 9-3-51. However, the Georgiа Supreme Court has ruled that the tolling of a period of limitation by the discovery rule is confined to cases involving bodily harm. Corporation of Mercer Univ. v. National Gypsum Co.,
We reject plaintiff's argument that the Mercer case does not apply to a casе, such as this one, where a statute of repose applies. The purpose of the statute of reposе is to impose an outside limit on the bringing of lawsuits which are otherwise brought within the applicable statutory period aftеr the action has accrued. See OCGA § 9-3-53. The Georgia courts have never interpreted the statute of repоse for construction cases as extending the otherwise applicable period of limitation. "It is clear from a reading of [OCGA § 9-3-53] that the legislature never intended [OCGA § 9-3-51] to establish a new eight year statute of limitation in place of thе two, four and six years statutes that may be applicable depending on the cause of action alleged." Benning Constr. Co. v. Lakeshore Plaza Enterprises,
Judgment affirmed. Deen, P. J., and Beasley, J., concur.
