Fru-Con Construction Corporation; Austin Maintenance & Construction, Inc., a Delaware Corporation, doing business as Fru-Con/Austin, JV, Appellants, v. Controlled Air, Inc., a Kansas Corporation, Appellee.
No. 08-1712
United States Court of Appeals FOR THE EIGHTH CIRCUIT
Submitted: September 26, 2008 Filed: July 24, 2009
Before BYE, BEAM, and SHEPHERD, Circuit Judges.
Fru-Con Construction Corporation and Austin Maintenance and Construction, Inc. (the Joint Venture) appeal the district court‘s application of Colorado River1 abstention to dismiss the Joint Venture‘s breach of contract action against Controlled Air, Inc. We reverse.
I. BACKGROUND
Nordic Biofuels of Ravenna, L.L.C., hired the Joint Venture through a real estate improvement contract as defined by
A dispute between Controlled Air and the Joint Venture arose and work ceased on the project. Controlled Air supplied labor and materials through January 14, 2007, and the Joint Venture assumed responsibility for the work on January 17, 2007. Pursuant to the Nebraska Construction Lien Act (NCLA), Controlled Air recorded a construction lien on March 1, 2007, for purportedly unpaid labor and materials. The recording alleged that the Joint Venture owed Controlled Air $1,496,636 for labor and materials provided through January 14. Controlled Air filed suit to foreclose the construction lien in the District Court of Buffalo County, Nebraska, on May 18, 2007. The Joint Venture, however, had previously filed a breach of contract action against Controlled Air in the United States District Court for the Eastern District of Missouri. The complaint alleged that the Joint Venture incurred damages of $1,500,000 after January 17, 2007, as a result of Controlled Air‘s breach of the agreement.
Believing that its Nebraska lien foreclosure action could serve to litigate the entire dispute between the parties, Controlled Air filed a motion asking the federal court to abstain from or dismiss the Joint Venture‘s breach of contract claim in the Eastern District of Missouri. Believing that the federal court forum could serve the
A. Nebraska Proceedings
The Joint Venture‘s motion to dismiss the lien foreclosure proceeding alleged that by filing a surety bond issued by a company authorized to do business in Nebraska, the action was no longer in rem and the forum selection clause applied, mandating jurisdiction in Missouri. During the first hearing on this matter, the Nebraska court held that the bond was ineffective because only a person having an interest in the real estate may file a bond under
The Nebraska court first noted that the bond discharged the real estate lien,3 but then concluded that the foreclosure action was still in existence “in so much as the lien is transferred to the submitted surety bond.” On this basis, the court held that the
Although the contract action had not been asserted in Nebraska, the state court, in making its ruling, applied
B. Federal Proceedings
The District Court for the Eastern District of Missouri recognized its subject matter jurisdiction but granted Controlled Air‘s motion to abstain from and dismiss the Joint Venture‘s breach of contract action, but only after the Nebraska court retained jurisdiction over the lien foreclosure proceeding.4 The Joint Venture disputed Controlled Air‘s motion to abstain in the federal case on grounds that the construction lien property was no longer under the exclusive control of the Nebraska court and
Clearly believing that the federal contract action and the state lien foreclosure proceeding were parallel matters5–unaware of the fact that the Joint Venture, under protest and out of an abundance of caution, had later asserted its contract action against Controlled Air in the Nebraska court, Controlled Air, Inc. v. Abengoa Bioenergy of Neb., LLC, No. CI07319 (D. Ct. Buffalo County, Neb. Oct. 22, 2007) (answer and counterclaim)–the federal district court first referenced the six abstention factors created by Colorado River and then proceeded to discuss each in turn. The court found that the following factors favored abstention: (1) while the Nebraska action is not in rem and the state court does not have exclusive jurisdiction, the state court has an interest in adjudicating the contract dispute; (2) allowing the federal action to continue would result in piecemeal litigation; (3) the Nebraska court is a more convenient forum; (4) state law controls; and (5) the state court can adequately protect the Joint Venture‘s rights. The sixth and final factor regarding priority of filing (of the federal contract action and the state lien foreclosure action) was held neutral. Then, the district court abstained from and dismissed the federal case.
Turning to the forum selection clause, which it separately considered, the district court concluded that “any questions of forum were validly decided by the Nebraska court.” The district court concluded that abstention was a question for it to decide while enforcement of the forum selection clause was a question best left “to the
II. DISCUSSION
Because the availability of a federal forum for the lien foreclosure claim has been an issue in both the Colorado River abstention ruling and the enforceability of the forum selection clause, we discuss that matter at the outset.
A. Lien Foreclosure Jurisdiction
Nebraska jurisdiction over the lien dispute is “unique” only in the sense that the Nebraska statute, here the NCLA, governs the nature and amount of damages the lien claimant may recover in its construction lien dispute, nothing more. Of course, federal courts routinely interpret and apply state law. Frequently, as in this appeal, statutes from more than one state are in play in a single piece of litigation.
The NCLA does not specify the forum or procedure that must be used to determine rights and remedies under the legislation.
In the event that such a judgment is rendered by the federal district court for the Eastern District of Missouri, it may be transferred, if necessary, to the District Court of Buffalo County, Nebraska, through the Uniform Enforcement of Foreign Judgments Act long ago enacted in Nebraska. See
B. Federal Court Jurisdiction
1. Abstention
We review a district court‘s decision to abstain from exercising jurisdiction over the federal court contract action under Colorado River for an abuse of discretion. Mountain Pure, LLC v. Turner Holdings, LLC, 439 F.3d 920, 926 (8th Cir. 2006). Federal courts, however, have a “virtually unflagging obligation . . . to exercise the jurisdiction given them, even when there is a pending state court action involving the same subject matter.” Id. (internal citations omitted). Thus, a federal court may divest itself of jurisdiction by abstaining only when parallel state and federal actions exist and exceptional circumstances warrant abstention. Colorado River Water Conservation Dist. v. United States, 424 U.S. 800, 817-18 (1976).7
(1) whether there is a res over which one court has established jurisdiction, (2) the inconvenience of the federal forum, (3) whether maintaining separate actions may result in piecemeal litigation, unless the relevant law would require piecemeal litigation and the federal court issue is easily severed, (4) which case has priority–not necessarily which case was filed first but a greater emphasis on the relative progress made in the cases, (5) whether state or federal law controls, especially favoring the exercise of jurisdiction where federal law controls, and (6) the adequacy of the state forum to protect the federal plaintiff‘s rights.
Mountain Pure, 439 F.3d at 926. In this case, the district court abstained based on five of the six factors and dismissed the case without further comment. On appeal, the parties’ focus on the district court‘s analysis of these six factors and, separately, the viability of the forum selection clause. Because the federal district court compared only the federal contract action and the state lien foreclosure action, clearly non-parallel proceedings, the Colorado River doctrine did not provide a basis for its judgment. Thus, we actually need not consider whether the district court properly weighed the above factors. Nonetheless, for a reason we later note, we carefully analyze the application of these components by the federal district court in Section IIB2.
a. Parallel Proceedings
As a threshold matter, as above indicated, there must be pending parallel state and federal court proceedings before Colorado River is implicated. In re Burns & Wilcox, Ltd., 54 F.3d 475, 477 (8th Cir. 1995) (citing Baskin v. Bath Twp. Bd. of Zoning Appeals, 15 F.3d 569, 571-72 (6th Cir. 1994)), limited on other grounds by Quackenbush v. Allstate Ins. Co., 517 U.S. 706, 710-11 (1996). Precedent
The pendency of a state claim based on the same general facts or subject matter as a federal claim and involving the same parties is not alone sufficient. Federated Rural Elec. Ins. Corp. v. Ark. Elec. Coop., Inc., 48 F.3d 294, 297 (8th Cir. 1995). Rather, a substantial similarity must exist between the state and federal proceedings, which similarity occurs when there is a substantial likelihood that the state proceeding will fully dispose of the claims presented in the federal court. TruServ Corp. v. Flegles, Inc., 419 F.3d 584, 592 (7th Cir. 2005). This analysis focuses on matters as they currently exist, not as they could be modified. Baskin, 15 F.3d at 572. Moreover, in keeping with the Supreme Court‘s charge to abstain in limited instances only, jurisdiction must be exercised if there is any doubt as to the parallel nature of the state and federal proceedings. AAR Int‘l, Inc. v. Nimelias Enter. S.A., 250 F.3d 510, 520 (7th Cir. 2001).
With these principles in mind, we start with a specific finding that Controlled Air‘s lien foreclosure proceeding is not parallel to the Joint Venture‘s breach of contract action for purposes of Colorado River abstention. Controlled Air is seeking to foreclose a Nebraska statutory lien for labor and materials furnished on and before January 14, 2007. The Joint Venture, however, seeks common law contract damages
The sources of law, required evidentiary showings, measures of damages, and treatment on appeal are also distinct for each claim. The lien amount is, at least in part, based on Nebraska statute and is limited by the NCLA. The breach of contract claim, on the other hand, is based on Missouri common law and entails the satisfaction of five different elements. Berra v. Papin Builders, Inc., 706 S.W.2d 70, 73-74 (Mo. Ct. App. 1986) (outlining the five breach of contract elements). The difference in recoveries for these claims was highlighted in Preston Refrigeration Co. v. Omaha Cold Storage Terminals, where the court said a lien is “the unpaid cost of materials and labor actually expended,” while a breach of contract action concerns the damages incurred as a result of incomplete performance. 742 N.W.2d 782, 788 (Neb. Ct. App. 2007); see also Info. Sys. & Networks Corp. v. City of Kansas City, 147 F.3d 711, 713 (8th Cir. 1998) (addressing breach of contract damages). Finally, a lien foreclosure is grounded in equity, tried to the court and on appeal is reviewed de novo on the record, while the breach of contract claim is an action at law which may be presented to a jury and is factually reviewed for clear error. Par 3, Inc. v. Livingston, 686 N.W.2d 369, 372 (Neb. 2004); Lincoln Lumber Co. v. Lancaster, 618 N.W.2d 676, 679 (Neb. 2000); C.F.S. v. Mahan, 934 S.W.2d 615, 618 (Mo. Ct. App. 1996); Old v. Heibel, 178 S.W.2d 351, 352 (Mo. 1944).
Almost identical facts were addressed by the Fourth Circuit in Gannett Co., Inc. v. Clark Construction Group, Inc. Gannett Co., Inc. v. Clark Construction Group, Inc., 286 F.3d 737 (4th Cir. 2002). Gannett hired Clark to build a new USA Today headquarters, a dispute arose, and work ceased. Id. at 740. Gannett filed a federal action for breach of contract and Clark filed a lien foreclosure action in Virginia state court. Id. Clark subsequently filed a motion to dismiss or stay the federal proceedings pending the outcome of the state action, and Gannett filed a motion to abate or stay the state proceedings. Id. The federal district court granted Clark‘s motion to stay the proceedings pursuant to the Colorado River abstention doctrine. Id. at 740-41.
The Fourth Circuit reversed, holding that the state lien proceeding and the federal breach of contract action were not parallel. Id. at 741-43. The court found the federal contract action and the state lien action involved different issues with different requisites of proof. Id. at 742. Further, the remedies were different as the state lien action sought foreclosure on property (here, the bond proceeds) and the federal contract action sought compensatory damages. Id. at 743. Thus, the federal contract action and the state lien action were not parallel proceedings and Colorado River abstention did not apply. Id.; see also New Beckley Mining Corp. v. UMW, 946 F.2d 1072, 1074 (4th Cir. 1991) (holding state and federal actions not parallel for Colorado River purposes because the remedies were different—one was equitable and the other compensatory—and the sources of law came from different states).
In sum, the state lien foreclosure proceeding will not dispose of the federal contract action and the sources of law, remedies sought, elements of proof, review on appeal, and events giving rise to each cause of action are different. Additionally, Controlled Air has never asserted the lien foreclosure claim in the federal district
b. Similar Claims
The foregoing analysis does not end our inquiry. When the Nebraska court denied the Joint Venture‘s motion to dismiss the lien claim, the Joint Venture answered Controlled Air‘s lien foreclosure action in the Nebraska court. At that same time, to protect its contract interests in the face of Controlled Air‘s federal motion to dismiss, the Joint Venture, while refusing to acknowledge the correctness of Nebraska venue, asserted its breach of contract action in state court, but “only out of an abundance of caution.” Controlled Air, No. CI07319, answer and counterclaim at 2. So, at that point in time, the contract action asserted by the Joint Venture against Controlled Air was, ostensibly, pending in both the Nebraska court and the federal district court for the Eastern District of Missouri.8
2. Colorado River Abstention
Assuming, for discussion, that assertion of purportedly parallel common law contract claims occurred in both forums, we must assess the federal district court‘s findings for conformance with Colorado River. First, we reiterate, however, that for Colorado River abstention purposes, any conclusion reached by the federal court arising from comparisons of the common law contract action and the statutorily based lien foreclosure claim were wholly irrelevant under both Supreme Court and Eighth Circuit precedent. Because of use of this improper mismatch, there has been, to date, no reference in the record to a comparative analysis under Colorado River of the Nebraska forum and the federal forum by the federal district court with regard to these contract actions as they may have purportedly lately pended in both jurisdictions. With that in mind, we turn again to and analyze each of the federal court‘s findings as set forth in its judgment of abstention and dismissal.
Finding One:
While the action was not in rem and the Nebraska court does not have exclusive jurisdiction, the state court has an interest in adjudicating the contract dispute.
The in rem and exclusive jurisdiction references obviously refer to the lien foreclosure claim because the contract claim presents no such issues. While the state court may have an interest in adjudicating the late blooming contract claim, the Missouri courts have an equal or significantly greater interest in adjudicating the contract claim because the forum selection clause agreed upon by the parties specifies a Missouri court applying Missouri law. And, the enforceability of the forum selection clause by the federal district court is one of federal procedural law and not Nebraska substantive law as erroneously indicated by the federal court. Also, the federal district court has little or no discretion to ignore the Joint Venture‘s choice of the federal forum for the filing of its contract claim, even in the absence of a forum selection clause.
Finding Two:
Allowing the federal action to continue would result in piecemeal litigation.
Analysis:
There will be no piecemeal litigation involving the contract claim. Litigating the lien foreclosure claim, if that is the comparison being made by the federal court in this finding, will require separate, and thus piecemeal, litigation in either jurisdiction, although joinder of the separate claims may be possible under Rule 18 of the Federal Rules of Civil Procedure. Likewise, there is no certainty that the Nebraska court, even correctly applying Nebraska forum selection precedent, could or would fail to enforce the contract‘s Missouri forum selection clause when faced with the issue in the contract claim.
Finding Three:
The Nebraska court is a more convenient forum.
Analysis:
Given the contract agreement to apply Missouri law, the Nebraska forum is at least incrementally less convenient than the Missouri forum. And, “mere inconvenience to a party is an insufficient basis to defeat an otherwise enforceable forum selection clause.” Servewell Plumbing, 439 F.3d at 790.
Finding Four:
State law controls.
It is likely correct that state law will apply, except, of course, to forum enforcement. Forum clause enforcement in the federal court will require application of federal law. Otherwise though, state law will apply in the federal court and in the Nebraska forum and, as to the contract claim, it will be Missouri law, not that of Nebraska. And “the presence of state law issues [in federal court] will weigh in favor of abstention only in rare circumstances.” Federated Rural Elec. Ins. Corp. v. Arkansas Elec. Coop., Inc., 48 F.3d 294, 299 (8th Cir. 1995).
Finding Five:
The state court can adequately protect the Joint Venture‘s rights.
Analysis:
While it is true that the Nebraska court can adequately protect the Joint Venture‘s rights, it can do so no more efficiently than the federal district court. And, this factor counts for or against abstention and dismissal only where “one of the forums is inadequate to protect a party‘s rights.” Gov‘t Employees Ins. Co. v. Simon, 917 F.2d 1144, 1149 (8th Cir. 1990) (emphasis in original) (quoting Noonan S., Inc. v. County of Volusia, 841 F.2d 380, 383 (11th Cir. 1988)). Thus, this reason is no better than an even push for each forum and certainly does not provide an “exceptional circumstance” as required by Colorado River.
Finding Six:
Priority of filing the cases is neutral.
Analysis:
It may be true that “time of filing” of the contract claim and the lien foreclosure claim could be fairly evaluated as neutral. But, when compared with the forced filing time of the contract counterclaim in state court, it is a different matter. Further, priority of filing includes a plaintiff‘s choice of forum. “‘[T]he plaintiff‘s choice of forum should rarely be disturbed.‘” Reid-Walen v. Hansen, 933 F.2d 1390, 1395 (8th Cir. 1991) (quoting Gulf Oil Corp. v. Gilbert, 330 U.S. 501, 508 (1947)). “[F]ederal courts give considerable deference to a plaintiff‘s choice of forum.” Terra Int‘l, Inc. v. Mississippi Chem. Corp., 119 F.3d 688, 695 (8th Cir. 1997). Accordingly, this factor clearly favors retention
In summary, although there has been a purported Colorado River analysis of non-parallel filings of the parties by the district court, the court has never undertaken a review of the contract pleadings under that case‘s doctrine. So, at the very least, there must be a remand to the district court for that purpose. A reading of the entire record, however, dictates that such a course is unnecessary. Under the uncontested circumstances of this case, abstention is unsupportable as a matter of law. None of the reasons advanced or that could be advanced by the federal court provide the extraordinary conditions required by Colorado River for a federal court to disregard its “virtually unflagging obligation . . . to exercise the jurisdiction” it is given even when there is also pending a state court action involving the same subject matter. Mountain Pure, 439 F.3d at 926. In analyzing the Colorado River factors, the district court‘s task was and is “to ascertain whether there exists exceptional circumstances, the clearest of justifications, that can suffice . . . to justify the surrender of [] jurisdiction.” Id. Indeed, even though we are a court of appellate review, “not of first view,” Cutter v. Wilkinson, 544 U.S. 709, 718 n.7 (2005), it is more than obvious that no such circumstances or justifications exist under any acceptable analysis of any of the causes of action. Thus, abstention from and dismissal of the Joint Venture‘s federal contract claim was and would be an abuse of discretion and reversible error.
III. CONCLUSION
For the foregoing reasons, we reverse and remand to the district court for proceedings consistent with this opinion.
I conclude the district court‘s decision to abstain from exercising jurisdiction under Colorado River Water Conservation District v. United States, 424 U.S. 800 (1976), was an abuse of discretion. Thus, I concur in the result of the court‘s decision reversing the district court. I agree, however, with the dissent‘s view as to the Colorado River abstention doctrine applying to this dispute and with its rejection of the “originally filed” approach. I would hold that as a result of the Joint Venture‘s breach-of-contract counterclaim, the Nebraska lien and federal contract suits are parallel proceedings as they actually existed when the district court issued its abstention order. I would apply the Colorado River abstention doctrine as articulated by the dissent, but would hold the district court abused its discretion in declining to exercise jurisdiction.
SHEPHERD, Circuit Judge, dissenting.
Because I believe we should affirm the judgment of the district court, I respectfully dissent. This appeal presents two issues: (1) Are the Nebraska and federal actions “parallel proceedings“? (2) If so, did the district court abuse its discretion by abstaining under Colorado River? On the first issue, I disagree with Judge Beam‘s conclusion in Part II.B.1 of his opinion that the Nebraska and federal suits are not parallel. See ante at 8-15. On the second issue, I disagree with the majority‘s conclusion that the district court abused its discretion by abstaining. See id. at 15-18.
I.
The Nebraska and federal actions are “parallel proceedings.” Judge Beam contends the cases are not parallel because Controlled Air‘s lien foreclosure suit and the Joint Venture‘s action for breach of contract involve different “sources of law,
Judge Beam asserts that the filing of the counterclaim for breach of contract “did not trigger parallelism between the proceedings pending in the two courts.” Ante at 14. He asserts that we are bound by Scottsdale Insurance Co. v. Detco Industries, Inc., 426 F.3d 994 (8th Cir. 2005). In Scottsdale, this court held that multiple state tort suits and a federal declaratory judgment action11 were not parallel because they
Contrary to this belief, Scottsdale does not mandate an “originally filed” approach. At best, the language in Scottsdale is dicta and, therefore, does not bind this panel‘s decision. See Passmore v. Astrue, 533 F.3d 658, 661 (8th Cir. 2008) (“[w]e need not follow dicta” (quotation omitted)); John Morrell & Co. v. Local Union 304A of United Food & Commercial Workers, 913 F.2d 544, 550 (8th Cir. 1990) (“[w]e need not follow dicta,” which is “language . . . in [an] earlier [] opinion [that] was not essential to the judgment in that case“). Unlike in the present case, the parties in Scottsdale never filed counterclaims or otherwise altered the parties or issues involved in their state and federal actions. See Scottsdale, 426 F.3d at 996-97. Because the suits were never altered, it was not essential to the Scottsdale court‘s judgment to determine that we must view the proceedings as they existed when originally filed, as opposed to some other point in time.
Our recent decision in Royal Indemnity Co. v. Apex Oil Co., Inc., 511 F.3d 788 (8th Cir. 2008), further proves that we do not follow an “originally filed” approach in this circuit. In Royal Indemnity, Apex Oil filed suit in state court against multiple
Under Judge Beam‘s approach, the Eighth Circuit panel in Royal Indemnity necessarily erred. As the state and federal suits existed when they were originally filed, Apex Oil was the only party common to both actions, which involved different insurers and different policies. Id. at 791. Because Apex Oil‘s state lawsuit against the state insurers would not have disposed of the federal action against Royal Indemnity and the federal insurers, the proceedings were not parallel as they existed when originally filed. See TruServ, 419 F.3d at 592. Only after Apex Oil added Royal Indemnity and the federal insurers as defendants in the state action did the proceedings become parallel because the state action would have disposed of the entire federal case. See id. Under the “originally filed” approach, because the suits were not parallel as originally filed, the district court could not have had broad discretion to abstain under Wilton; it could only have had limited discretion to abstain under Aetna. Contra Royal Indemnity, 511 F.3d at 797 (“[W]e affirm the district court‘s decision to apply the Wilton . . . abstention standard, and . . . we hold that the
The fact that we clearly did not view the state and federal proceedings as they existed when originally filed was essential to our reasoning and judgment in Royal Indemnity and is binding on this panel. See Passmore, 533 F.3d at 660 (we “cannot overrule an earlier decision by another panel“). In both Royal Indemnity and the present case, the proceedings were not parallel as they existed when originally filed, but they became parallel before the district court issued its abstention order. Therefore, Judge Beam‘s approach in the present case impermissibly ignores our recent decision in Royal Indemnity.12
The presence of parallel proceedings is a prerequisite for the application of Colorado River abstention because, unless “a parallel state-court action exists, [] the [federal] district court would have nothing in favor of which to abstain.” Baskin v. Bath Twp. Bd. of Zoning Appeals, 15 F.3d 569, 571 (6th Cir. 1994). Thus, the existence of parallel proceedings triggers the district court‘s discretion to abstain under Colorado River. Under the approach advanced by Judge Beam, to determine whether its discretion to abstain is triggered, the district court must take a snapshot of the state and federal suits as they existed when originally filed.
If, as in the present case, the parties or issues involved in the proceedings have changed since the suits were originally filed, then taking a snapshot of the proceedings as they existed in the past says nothing about whether abstention will conserve judicial resources and promote comprehensive disposition of the litigation in the future. If, as in Scottsdale, the parties and issues have never changed, then there is no difference between taking a snapshot of the proceedings as they existed in the past and taking a snapshot of the proceedings as they currently exist. The snapshots look the same, and
Finally, and most importantly, if state and federal proceedings are parallel as originally filed but become unparallel before the district court issues its abstention order, an “originally filed” approach would still trigger the district court‘s discretion to abstain solely because the actions were parallel at some point in the past. Under this approach, the district court would have discretion to abstain under Colorado River even though there would no longer be a parallel action in favor of which to abstain. Consequently, such an approach runs afoul of the Colorado River doctrine and should be rejected. As a result of the Joint Venture‘s counterclaim, the Nebraska and federal actions are “parallel proceedings” as they actually existed when the district court abstained. See TruServ, 419 F.3d at 592; Gannett, 286 F.3d at 742 n.4; Baskin, 15 F.3d at 572.
II.
Because the proceedings are parallel, we “must consider whether the district court abused its discretion in finding that ‘exceptional circumstances’ warranted abstention.” Gannett, 286 F.3d at 744. Determining whether exceptional circumstances exist requires evaluating the factors outlined in Colorado River and Moses H. Cone Mem‘l Hosp. v. Mercury Constr. Corp., 460 U.S. 1 (1983).13
Federated Rural Elec. Ins. Corp. v. Ark. Elec. Coops., Inc., 48 F.3d 294, 297 (8th Cir. 1995). I believe the first and third factors weigh in favor of abstention. All other factors are neutral and, as such, are “irrelevant to the existence of exceptional circumstances.” Federated Rural, 48 F.3d at 297. The district court did not abuse its discretion when it decided that this case presents the type of exceptional circumstances that warrant abstention “in order to advance the ‘clear federal policy’ of avoiding piecemeal adjudication.” Federated Rural, 48 F.3d at 297 (quoting Moses H. Cone, 460 U.S. at 16). Therefore, the judgment of the district court should be affirmed.
Even though the majority will not affirm, outright reversal is not appropriate in this case. As Judge Beam acknowledges, “although there has been a purported Colorado River analysis of non-parallel filings of the parties by the district court, the court has never undertaken a review of the contract pleadings under that case‘s doctrine. So, at the very least, there must be a remand to the district court for that purpose.” Ante at 18 (emphasis added). For example, when Judge Beam finds that “there will be no piecemeal litigation,” ante at 16, his analysis—like the district court‘s—is potentially flawed because he fails to consider the breach-of-contract counterclaim as part of the Nebraska action. Nonetheless, he finds that “[u]nder the uncontested circumstances of this case, abstention is unsupportable as a matter of law” and that “it is more than obvious that no such [exceptional] circumstances or justifications exist under any acceptable analysis of any of the causes of action.” Id. at 18. I believe that, “at the very least,” id., we should remand so the district court will have an opportunity to consider the Joint Venture‘s Nebraska counterclaim for breach of contract in deciding whether abstention is appropriate.
