*1 Before BYE, BEAM, and SHEPHERD, Circuit Judges.
___________
BEAM, Circuit Judge.
Fru-Con Construction Corporation and Austin Maintenance and Construction, Inc. (the Joint Venture) appeal the district court's application of Colorado River [1] abstention to dismiss the Joint Venture's breach of contract action against Controlled Air, Inc. We reverse.
I. BACKGROUND
Nordic Biofuels of Ravenna, L.L.C., hired the Joint Venture through a real estate improvement contract as defined by Nebraska Revised Statute § 52-130 to construct an ethanol production facility in Ravenna, Nebraska. The Joint Venture engaged Controlled Air to construct the grain receiving, storage, and milling system for the facility. Their agreement contained law and forum selection clauses requiring all disputes between the parties to be governed by Missouri law and brought in Missouri state court or the federal district court for the Eastern District of Missouri. Additionally, the contract allowed the Joint Venture to terminate Controlled Air for specified reasons and to take over the work being performed after giving seventy-two hours written notice.
A dispute between Controlled Air and the Joint Venture arose and work ceased on the project. Controlled Air supplied labor and materials through January 14, 2007, and the Joint Venture assumed responsibility for the work on January 17, 2007. Pursuant to the Nebraska Construction Lien Act (NCLA), Controlled Air recorded a construction lien on March 1, 2007, for purportedly unpaid labor and materials. The recording alleged that the Joint Venture owed Controlled Air $1,496,636 for labor and materials provided through January 14. Controlled Air filed suit to foreclose the construction lien in the District Court of Buffalo County, Nebraska, on May 18, 2007. The Joint Venture, however, had previously filed a breach of contract action against Controlled Air in the United States District Court for the Eastern District of Missouri. The complaint alleged that the Joint Venture incurred damages of $1,500,000 after January 17, 2007, as a result of Controlled Air's breach of the agreement.
Believing that its Nebraska lien foreclosure action could serve to litigate the entire dispute between the parties, Controlled Air filed a motion asking the federal court to abstain from or dismiss the Joint Venture's breach of contract claim in the Eastern District of Missouri. Believing that the federal court forum could serve the *3 same purpose, the Joint Venture filed a lien relief bond in Buffalo County, Nebraska, in accordance with the NCLA, releasing the construction lien and clearing the lien from the title to the real estate in question. A motion to dismiss or stay Controlled Air's lien foreclosure proceeding was then filed by the Joint Venture in the District Court of Buffalo County. Thus, a federal-state forum fight came to life.
A. Nebraska Proceedings
The Joint Venture's motion to dismiss the lien foreclosure proceeding alleged that by filing a surety bond issued by a company authorized to do business in Nebraska, the action was no longer in rem and the forum selection clause applied, mandating jurisdiction in Missouri. During the first hearing on this matter, the Nebraska court held that the bond was ineffective because only a person having an interest in the real estate may file a bond under Nebraska Revised Statute § 52-142, and the Joint Venture did not have an interest in the lien property. [2] After the Joint Venture amended the bond, the Nebraska court again held the bond ineffective because it failed to identify where and upon whom service should be made. Finally, after the Joint Venture corrected all purported mistakes, the Nebraska court ruled on the motion to dismiss.
The Nebraska court first noted that the bond discharged the real estate lien, [3] but then concluded that the foreclosure action was still in existence "in so much as the lien is transferred to the submitted surety bond." On this basis, the court held that the *4 validity of the original construction lien and the amounts that might be owed on it were still in question. Thus, the court decided that an appropriate remedy was not available in the federal forum and denied the motion to dismiss.
Although the contract action had not been asserted in Nebraska, the state court, in making its ruling, applied Nebraska Revised Statute § 25-415 to dispose of the contract's forum selection clause. That section codifies Nebraska's recognition of forum selection clauses, but provides five exceptions. While the court originally viewed three of the exceptions as potentially applicable, it ultimately determined that the Joint Venture's bond was ineffective in releasing the lien from the real estate, creating an in rem action that had to be resolved at the situs of the dispute–Nebraska. However, as earlier stated, the Nebraska court later recognized its error as to the efficacy of the bond in releasing the real estate lien and thereafter, upon reconsideration, made its dismissal decision based upon the purported "unique[ness of the lien action] to the Nebraska jurisdiction"–making a remedy not available in the federal forum. As mentioned below, the federal district court found this to be error, a matter with which we agree and discuss in greater detail in Section IIA.
B. Federal Proceedings
The District Court for the Eastern District of Missouri recognized its subject matter jurisdiction but granted Controlled Air's motion to abstain from and dismiss the Joint Venture's breach of contract action, but only after the Nebraska court retained jurisdiction over the lien foreclosure proceeding. [4] The Joint Venture disputed Controlled Air's motion to abstain in the federal case on grounds that the construction lien property was no longer under the exclusive control of the Nebraska court and *5 because the forum selection clause mandated that jurisdiction over its contract action was properly in the federal court.
Clearly believing that the federal contract action and the state lien foreclosure proceeding were parallel matters [5] –unaware of the fact that the Joint Venture, under protest and out of an abundance of caution, had later asserted its contract action against Controlled Air in the Nebraska court, Controlled Air, Inc. v. Abengoa Bioenergy of Neb., LLC, No. CI07319 (D. Ct. Buffalo County, Neb. Oct. 22, 2007) (answer and counterclaim)–the federal district court first referenced the six abstention factors created by Colorado River and then proceeded to discuss each in turn. The court found that the following factors favored abstention: (1) while the Nebraska action is not in rem and the state court does not have exclusive jurisdiction, the state court has an interest in adjudicating the contract dispute; (2) allowing the federal action to continue would result in piecemeal litigation; (3) the Nebraska court is a more convenient forum; (4) state law controls; and (5) the state court can adequately protect the Joint Venture's rights. The sixth and final factor regarding priority of filing (of the federal contract action and the state lien foreclosure action) was held neutral. Then, the district court abstained from and dismissed the federal case.
Turning to the forum selection clause, which it separately considered, the district court concluded that "any questions of forum were validly decided by the Nebraska court." The district court concluded that abstention was a question for it to decide while enforcement of the forum selection clause was a question best left "to the *6 sound judgment of the Nebraska state court." The Joint Venture filed a timely appeal alleging that the district court improperly abstained and dismissed.
II. DISCUSSION
Because the availability of a federal forum for the lien foreclosure claim has been an issue in both the Colorado River abstention ruling and the enforceability of the forum selection clause, we discuss that matter at the outset.
A. Lien Foreclosure Jurisdiction
Nebraska jurisdiction over the lien dispute is "unique" only in the sense that the Nebraska statute, here the NCLA, governs the nature and amount of damages the lien claimant may recover in its construction lien dispute, nothing more. Of course, federal courts routinely interpret and apply state law. Frequently, as in this appeal, statutes from more than one state are in play in a single piece of litigation.
The NCLA does not specify the forum or procedure that must be used to
determine rights and remedies under the legislation. Neb. Rev. Stat. § 52-155. A
court may use any procedure applicable to a realization on judgments to satisfy a
NCLA-based claim. Tilt-Up Concrete, Inc. v. Star City/Fed., Inc.,
*7 Under the NCLA, "[a]ny person having an interest in real estate may release the real estate from liens . . . by [d]epositing in the office of the clerk of the [appropriate Nebraska] district court . . . a surety bond." Neb. Rev. Stat. § 52-142(1)(a). Upon the deposit of a bond, "the claimant's rights are transferred from the real estate to [that] bond and the claimant may establish his or her claim under the [Act]." [6] Id. § 52- 142(3). Upon determination of the validity and amount of a lien claim, the court shall render judgment against the surety company. Id. Thus, whether Controlled Air files a foreclosure suit in Nebraska or Missouri, only the amount of a claim against the bonding company is dictated by the NCLA. Recovery under the bond first requires proof that a "real estate improvement contract" has actually been entered into. Id. § 52-131(1). In this case, the question of whether such a contract exists between the Joint Venture and Controlled Air is answered by Missouri law–the law selected under their agreement. And even if the applicable law is governed by Nebraska statute, the federal court can make that determination. So, once it is established that a valid real *8 estate improvement contract exists and that the Joint Venture breached that contract by receiving and failing to pay for labor and materials provided by Controlled Air, recovery under the bond is had through a judgment against the surety company. Id. § 52-142(3).
In the event that such a judgment is rendered by the federal district court for the Eastern District of Missouri, it may be transferred, if necessary, to the District Court of Buffalo County, Nebraska, through the Uniform Enforcement of Foreign Judgments Act long ago enacted in Nebraska. See id. §§ 25-1587.01 to 1587.09. It is likely, however, that any bonding company authorized to do business in Nebraska is also directly subject to service of process in the federal courts of Missouri.
B. Federal Court Jurisdiction
1. Abstention
We review a district court's decision to abstain from exercising jurisdiction over
the federal court contract action under Colorado River for an abuse of discretion.
Mountain Pure, LLC v. Turner Holdings, LLC,
Six non-exhaustive factors have been developed to determine whether, in the case of parallel state and federal proceedings, exceptional circumstances warrant abstention. These six factors are:
(1) whether there is a res over which one court has established
jurisdiction, (2) the inconvenience of the federal forum, (3) whether
maintaining separate actions may result in piecemeal litigation, unless
the relevant law would require piecemeal litigation and the federal court
issue is easily severed, (4) which case has priority–not necessarily which
case was filed first but a greater emphasis on the relative progress made
in the cases, (5) whether state or federal law controls, especially favoring
the exercise of jurisdiction where federal law controls, and (6) the
adequacy of the state forum to protect the federal plaintiff's rights.
Mountain Pure,
a. Parallel Proceedings
As a threshold matter, as above indicated, there must be pending parallel state
and federal court proceedings before Colorado River is implicated. In re Burns &
Wilcox, Ltd.,
The pendency of a state claim based on the same general facts or subject matter
as a federal claim and involving the same parties is not alone sufficient. Federated
Rural Elec. Ins. Corp. v. Ark. Elec. Coop., Inc.,
With these principles in mind, we start with a specific finding that Controlled
Air's lien foreclosure proceeding is not parallel to the Joint Venture's breach of
contract action for purposes of Colorado River abstention. Controlled Air is seeking
to foreclose a Nebraska statutory lien for labor and materials furnished on and before
January 14, 2007. The Joint Venture, however, seeks common law contract damages
*11
for losses incurred after January 17, 2007, as a result of Controlled Air's breach of the
subcontract. While both actions stem from the same project and contractual
relationship, each is premised on a different wrong arising from different occurrences.
Upon completion of the lien foreclosure, the only issue decided will have been
whether labor and materials were provided for which the Joint Venture has failed to
pay. A decision on that claim, which has been asserted only in state court, will not
foreclose the issue of whether Controlled Air breached the subcontract and whether
the Joint Venture incurred damages as a result. Accordingly, the state lien foreclosure
action will not dispose of all issues in the federal contract action. See, e.g., George
Weis Co. v. Stratum Design-Build, Inc.,
The sources of law, required evidentiary showings, measures of damages, and
treatment on appeal are also distinct for each claim. The lien amount is, at least in
part, based on Nebraska statute and is limited by the NCLA. The breach of contract
claim, on the other hand, is based on Missouri common law and entails the satisfaction
of five different elements. Berra v. Papin Builders, Inc.,
Almost identical facts were addressed by the Fourth Circuit in Gannett Co., Inc.
v. Clark Construction Group, Inc.,
The Fourth Circuit reversed, holding that the state lien proceeding and the federal breach of contract action were not parallel. Id. at 741-43. The court found the federal contract action and the state lien action involved different issues with different requisites of proof. Id. at 742. Further, the remedies were different as the state lien action sought foreclosure on property (here, the bond proceeds) and the federal contract action sought compensatory damages. Id. at 743. Thus, the federal contract action and the state lien action were not parallel proceedings and Colorado River abstention did not apply. Id.; see also New Beckley Mining Corp. v. UMW, 946 F.2d 1072, 1074 (4th Cir. 1991) (holding state and federal actions not parallel for Colorado River purposes because the remedies were different—one was equitable and the other compensatory—and the sources of law came from different states).
In sum, the state lien foreclosure proceeding will not dispose of the federal contract action and the sources of law, remedies sought, elements of proof, review on appeal, and events giving rise to each cause of action are different. Additionally, Controlled Air has never asserted the lien foreclosure claim in the federal district *13 court. So, as to the lien foreclosure, there is neither similar claims nor similar parties in both state and federal courts as required for parallelism. Thus, Colorado River was not available to the federal court in adjudication of the correct locus of the contract action.
b. Similar Claims The foregoing analysis does not end our inquiry. When the Nebraska court denied the Joint Venture's motion to dismiss the lien claim, the Joint Venture answered Controlled Air's lien foreclosure action in the Nebraska court. At that same time, to protect its contract interests in the face of Controlled Air's federal motion to dismiss, the Joint Venture, while refusing to acknowledge the correctness of Nebraska venue, asserted its breach of contract action in state court, but "only out of an abundance of caution." Controlled Air, No. CI07319, answer and counterclaim at 2. So, at that point in time, the contract action asserted by the Joint Venture against Controlled Air was, ostensibly, pending in both the Nebraska court and the federal district court for the Eastern District of Missouri. [8]
This event, however, did not trigger parallelism between the proceedings
pending in the two courts. The principle cases in this circuit defining when actions
become parallel for abstention purposes are Scottsdale Insurance Co. v. Detco
Industries, Inc.,
*15
17, 19 (2d Cir. 1990); Manetti-Farrow, Inc. v. Gucci Amer., Inc.,
2. Colorado River Abstention
Assuming, for discussion, that assertion of purportedly parallel common law contract claims occurred in both forums, we must assess the federal district court's findings for conformance with Colorado River. First, we reiterate, however, that for Colorado River abstention purposes, any conclusion reached by the federal court arising from comparisons of the common law contract action and the statutorily based lien foreclosure claim were wholly irrelevant under both Supreme Court and Eighth Circuit precedent. Because of use of this improper mismatch, there has been, to date, no reference in the record to a comparative analysis under Colorado River of the Nebraska forum and the federal forum by the federal district court with regard to these contract actions as they may have purportedly lately pended in both jurisdictions. With that in mind, we turn again to and analyze each of the federal court's findings as set forth in its judgment of abstention and dismissal.
Finding One:
While the action was not in rem and the Nebraska court does not have exclusive jurisdiction, the state court has an interest in adjudicating the contract dispute. *16 Analysis:
The in rem and exclusive jurisdiction references obviously refer to the lien foreclosure claim because the contract claim presents no such issues. While the state court may have an interest in adjudicating the late blooming contract claim, the Missouri courts have an equal or significantly greater interest in adjudicating the contract claim because the forum selection clause agreed upon by the parties specifies a Missouri court applying Missouri law. And, the enforceability of the forum selection clause by the federal district court is one of federal procedural law and not Nebraska substantive law as erroneously indicated by the federal court. Also, the federal district court has little or no discretion to ignore the Joint Venture's choice of the federal forum for the filing of its contract claim, even in the absence of a forum selection clause. Finding Two:
Allowing the federal action to continue would result in piecemeal litigation. Analysis:
There will be no piecemeal litigation involving the contract claim. Litigating the lien foreclosure claim, if that is the comparison being made by the federal court in this finding, will require separate, and thus piecemeal, litigation in either jurisdiction, although joinder of the separate claims may be possible under Rule 18 of the Federal Rules of Civil Procedure. Likewise, there is no certainty that the Nebraska court, even correctly applying Nebraska forum selection precedent, could or would fail to enforce the contract's Missouri forum selection clause when faced with the issue in the contract claim. Finding Three:
The Nebraska court is a more convenient forum.
Analysis:
Given the contract agreement to apply Missouri law, the Nebraska forum is at
least incrementally less convenient than the Missouri forum. And, "mere
inconvenience to a party is an insufficient basis to defeat an otherwise
enforceable forum selection clause." Servewell Plumbing,
State law controls. *17 Analysis:
It is likely correct that state law will apply, except, of course, to forum enforcement. Forum clause enforcement in the federal court will require application of federal law. Otherwise though, state law will apply in the federal court and in the Nebraska forum and, as to the contract claim, it will be Missouri law, not that of Nebraska. And "the presence of state law issues [in federal court] will weigh in favor of abstention only in rare circumstances." Federated Rural Elec. Ins. Corp. v. Arkansas Elec. Coop., Inc.,48 F.3d 294 , 299 (8th Cir. 1995).
Finding Five:
The state court can adequately protect the Joint Venture's rights.
Analysis:
While it is true that the Nebraska court can adequately protect the Joint Venture's rights, it can do so no more efficiently than the federal district court. And, this factor counts for or against abstention and dismissal only where "one of the forums is inadequate to protect a party's rights." Gov't Employees Ins. Co. v. Simon, 917 F.2d 1144, 1149 (8th Cir. 1990) (emphasis in original) (quoting Noonan S., Inc. v. County of Volusia,841 F.2d 380 , 383 (11th Cir. 1988)). Thus, this reason is no better than an even push for each forum and certainly does not provide an "exceptional circumstance" as required by Colorado River.
Finding Six:
Priority of filing the cases is neutral.
Analysis:
It may be true that "time of filing" of the contract claim and the lien foreclosure
claim could be fairly evaluated as neutral. But, when compared with the forced
filing time of the contract counterclaim in state court, it is a different matter.
Further, priority of filing includes a plaintiff's choice of forum. "'[T]he
plaintiff's choice of forum should rarely be disturbed.'" Reid-Walen v. Hansen,
In summary, although there has been a purported Colorado River analysis of
non-parallel filings of the parties by the district court, the court has never undertaken
a review of the contract pleadings under that case's doctrine. So, at the very least,
there must be a remand to the district court for that purpose. A reading of the entire
record, however, dictates that such a course is unnecessary. Under the uncontested
circumstances of this case, abstention is unsupportable as a matter of law. None of the
reasons advanced or that could be advanced by the federal court provide the
extraordinary conditions required by Colorado River for a federal court to disregard
its "virtually unflagging obligation . . . to exercise the jurisdiction" it is given even
when there is also pending a state court action involving the same subject matter.
Mountain Pure,
III. CONCLUSION
For the foregoing reasons, we reverse and remand to the district court for proceedings consistent with this opinion.
BYE, Circuit Judge, concurring in the result and joining the dissent in part.
I conclude the district court's decision to abstain from exercising jurisdiction
under Colorado River Water Conservation District v. United States,
SHEPHERD, Circuit Judge, dissenting.
Because I believe we should affirm the judgment of the district court, I respectfully dissent. This appeal presents two issues: (1) Are the Nebraska and federal actions “parallel proceedings”? (2) If so, did the district court abuse its discretion by abstaining under Colorado River? On the first issue, I disagree with Judge Beam’s conclusion in Part II.B.1 of his opinion that the Nebraska and federal suits are not parallel. See ante at 8-15. On the second issue, I disagree with the majority’s conclusion that the district court abused its discretion by abstaining. See id. at 15-18.
I.
The Nebraska and federal actions are “parallel proceedings.” Judge Beam
contends the cases are not parallel because Controlled Air’s lien foreclosure suit and
the Joint Venture’s action for breach of contract involve different “sources of law,
*20
remedies sought, elements of proof, review on appeal, and events giving rise to each
cause of action . . . .” Ante at 12. I agree that a construction lien foreclosure action
and a suit for breach of contract do not involve “substantially similar issues” and, thus,
are not “parallel proceedings” for purposes of Colorado River abstention. See Gannett
Co., Inc. v. Clark Constr. Group, Inc.,
Contrary to this belief, Scottsdale does not mandate an “originally filed”
approach. At best, the language in Scottsdale is dicta and, therefore, does not bind this
panel’s decision. See Passmore v. Astrue,
Our recent decision in Royal Indemnity Co. v. Apex Oil Co., Inc.,
insurance companies (the “state insurers”) on August 5, 2005, seeking a declaration of the parties’ rights and responsibilities under policies the state insurers had issued Apex Oil. Id. at 791. On March 22, 2006, Royal Indemnity brought a declaratory judgment action in federal court against Apex Oil that named several other insurance companies (the “federal insurers”) and sought an adjudication of the parties’ rights and obligations under policies that Royal Indemnity and the federal insurers had issued Apex Oil. Id. Two months later, on May 19, 2006, Apex Oil amended its state-court complaint to name Royal Indemnity and the federal insurers as defendants in the state lawsuit. Id. at 791-92. The district court found that the state and federal proceedings were parallel and, therefore, exercised its broad discretion to abstain in a declaratory judgment action under Wilton . Id. at 792. We agreed that the state action was parallel and affirmed the district court’s decision to abstain under the broad Wilton standard. Id. at 797. Thus, in Royal Indemnity, the amended state-court complaint, filed two months after the federal lawsuit commenced and nine months after the state lawsuit commenced, made the proceedings parallel.
Under Judge Beam’s approach, the Eighth Circuit panel in Royal Indemnity
necessarily erred. As the state and federal suits existed when they were originally
filed, Apex Oil was the only party common to both actions, which involved different
insurers and different policies. Id. at 791. Because Apex Oil’s state lawsuit against
the state insurers would not have disposed of the federal action against Royal
Indemnity and the federal insurers, the proceedings were not parallel as they existed
when originally filed. See TruServ,
The fact that we clearly did not view the state and federal proceedings as they
existed when originally filed was essential to our reasoning and judgment in Royal
Indemnity and is binding on this panel. See Passmore,
Moving beyond issues of
stare decisis
, the principles underlying Colorado
River abstention also counsel against adopting an “originally filed” approach to
determine whether state and federal actions are parallel. Those principles “rest on
considerations of wise judicial administration, giving regard to conservation of
judicial resources and comprehensive disposition of litigation.” Colorado River
Conservation Dist. v. United States,
The presence of parallel proceedings is a prerequisite for the application of Colorado River abstention because, unless “a parallel state-court action exists, [] the [federal] district court would have nothing in favor of which to abstain.” Baskin v. Bath Twp. Bd. of Zoning Appeals, 15 F.3d 569, 571 (6th Cir. 1994). Thus, the existence of parallel proceedings triggers the district court’s discretion to abstain under Colorado River. Under the approach advanced by Judge Beam, to determine whether its discretion to abstain is triggered, the district court must take a snapshot of the state and federal suits as they existed when originally filed.
If, as in the present case, the parties or issues involved in the proceedings have
changed since the suits were originally filed, then taking a snapshot of the proceedings
as they existed in the past says nothing about whether abstention will conserve judicial
resources and promote comprehensive disposition of the litigation in the future. If,
as in Scottsdale, the parties and issues have never changed, then there is no difference
between taking a snapshot of the proceedings as they existed in the past and taking a
snapshot of the proceedings as they currently exist. The snapshots look the same, and
*26
the answer to the parallel proceedings inquiry is the same. Therefore, in light of the
principles underlying Colorado River abstention, it only makes sense for the district
court to view the state and federal proceedings as they
currently
exist to determine
whether its discretion to abstain is triggered. See, e.g., Baskin,
Finally, and most importantly, if state and federal proceedings are parallel as
originally filed but become unparallel before the district court issues its abstention
order, an “originally filed” approach would still trigger the district court’s discretion
to abstain solely because the actions were parallel at some point in the past. Under
this approach, the district court would have discretion to abstain under Colorado River
even though there would no longer be a parallel action in favor of which to abstain.
Consequently, such an approach runs afoul of the Colorado River doctrine and should
be rejected. As a result of the Joint Venture’s counterclaim, the Nebraska and federal
actions are “parallel proceedings” as they actually existed when the district court
abstained. See TruServ,
II.
Because the proceedings are parallel, we “must consider whether the district
court abused its discretion in finding that ‘exceptional circumstances’ warranted
abstention.” Gannett, 286 F.3d at 744. Determining whether exceptional
circumstances exist requires evaluating the factors outlined in Colorado River and
Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1 (1983).
[13]
*27
Federated Rural Elec. Ins. Corp. v. Ark. Elec. Coops., Inc.,
Even though the majority will not affirm, outright reversal is not appropriate in this case. As Judge Beam acknowledges, “although there has been a purported Colorado River analysis of non-parallel filings of the parties by the district court, the court has never undertaken a review of the contract pleadings under that case’s doctrine. So, at the very least, there must be a remand to the district court for that purpose. ” Ante at 18 (emphasis added). For example, when Judge Beam finds that “there will be no piecemeal litigation,” ante at 16, his analysis—like the district court’s—is potentially flawed because he fails to consider the breach-of-contract counterclaim as part of the Nebraska action. Nonetheless, he finds that “[u]nder the uncontested circumstances of this case, abstention is unsupportable as a matter of law” and that “it is more than obvious that no such [exceptional] circumstances or justifications exist under any acceptable analysis of any of the causes of action.” Id. at 18. I believe that, “at the very least,” id., we should remand so the district court will have an opportunity to consider the Joint Venture’s Nebraska counterclaim for breach of contract in deciding whether abstention is appropriate.
______________________________
court issue is easily severed, (4) which case has priority—not necessarily which case
was filed first but a greater emphasis on the relative progress made in the cases, (5)
whether state or federal law controls, especially favoring the exercise of jurisdiction
where federal law controls, and (6) the adequacy of the state forum to protect the
federal plaintiff’s rights.” Federated Rural,
Notes
[1] Colorado River Water Conservation Dist. v. United States, 424 U.S. 800 (1976).
[2] This was error. Pursuant to Nebraska Revised Statute § 52-131(1), any person
(including the Joint Venture, a prime contractor as defined in Nebraska Revised
Statute § 52-127(8)), "'who furnishes services or materials pursuant to a real estate
improvement contract has a construction lien[,]'" to secure the payment of his or her
contract price. Tilt-Up Concrete, Inc. v. Star City/Fed., Inc.,
[3] This was a correct analysis.
[4] Controlled Air's motion to dismiss for lack of personal jurisdiction and improper venue was denied. As Controlled Air did not appeal that ruling it is not before us today.
[5] The federal district court in formulating its abstention and dismissal order states, for instance, "both the contract dispute before this Court, and the collection actions in the Nebraska court, involve work performed by the respective parties on the ethanol plan located in Nebraska. This factor, although it does not mandate abstention, weighs in favor of abstention." Appellants' App. at 125-26. "There is currently pending before the Nebraska state court an action involving the same Parties and the same property at issue in the suit before this Court." Id. at 128.
[6] Under the NCLA, a contract vendor such as Controlled Air "is entitled to the
unpaid part of his or her contract price [] when the [vendor] has substantially
performed the contract," which includes profits incorporated into the contract. Tilt-up
Concrete,
[7] When a federal court moves beyond abstention to dismissal, as here,
considerably weightier reasons have to be in place. Colorado River,
[8] Unfortunately for Controlled Air, this turn of events is not advantageous to its
abstention and dismissal contentions. As already stated, there is nothing in the district
court record concerning the breach of contract counterclaim. Further, upon
questioning by this court, Controlled Air conceded that the counterclaim was "not
filed with the court." Neither was the counterclaim ever mentioned in the briefings
to this court. These facts alone foreclose any newly minted argument that the
Nebraska and federal contract actions are parallel for purposes of our consideration
of the issues in this appeal. See City of Jefferson City v. Cingular Wireless, LLC, 531
F.3d 595 (8th Cir.), cert. denied sub nom. Alltel Commc'ns, LLC v. City of
Springfield,
[9] Judge Beam contends that, because “there is nothing in the district court record
concerning the breach of contract counterclaim,” this fact “foreclose[s] any newly
minted argument that the Nebraska and federal contract actions are parallel for
purposes of our consideration of the issues in this appeal.” Ante at 13 n.8. However,
“we may take judicial notice of proceedings in other courts that relate to matters at
issue.” Great Plains Trust Co. v. Union Pacific R.R. Co.,
[10] To constitute “parallel proceedings,” state and federal actions need not be mirror images. As Judge Beam acknowledges, “a substantial similarity must exist between the state and federal proceedings, which similarity occurs when there is a substantial likelihood that the state proceeding will fully dispose of the claims presented in the federal court.” Ante at 10 (citing TruServ Corp. v. Flegles, Inc., 419 F.3d 584, 592 (7th Cir. 2005)). In the present case, it is virtually certain that the Nebraska action, which includes both Controlled Air’s lien foreclosure claim and the Joint Venture’s counterclaim for breach of contract, will fully dispose of the Joint Venture’s singular breach-of-contract claim in federal court.
[11] The “exceptional circumstances” test from Colorado River does not apply to
actions for declaratory judgment. Prudential Ins. Co. of Am. v. Doe,
[12] Judge Beam states that “[w]hile Royal Indemnity might be read to provide a
different result based strictly upon a filing time, it otherwise demands that the state
court proceeding must present [to the federal court] the same issues,
not governed by
federal law
, between the same parties.” Ante at 14 (quotation omitted). He further
opines that “enforcement, or not, of the contractual forum selection clause was a
federal court procedural matter governed by federal law” . . . [and] [t]his, of course,
defeats parallelism under Royal Indemnity precedent.” Id. at 14-15. In my view, such
an interpretation of the cited language from Royal Indemnity would give those words
unwarranted meaning. If a difference between state and federal
procedural
law
governing the two actions necessarily defeats parallelism, then there will be few, if
any, situations in which Colorado River abstention is permissible because all
procedural matters in federal court are governed by federal law. See Erie R.R. Co. v.
Tompkins,
[13] The Colorado River and Moses H. Cone factors are: “(1) whether there is a res over which one court has established jurisdiction, (2) the inconvenience of the federal forum, (3) whether maintaining separate actions may result in piecemeal litigation, unless the relevant law would require piecemeal litigation and the federal
