OPINION
In this appeal, we address two primary issues: (1) whether the contract in this case providing for construction of a hotel in Tennessee “involves” interstate commerce so as to implicate the Federal Arbitration Act, and (2) whether the chancery court erred in withholding contract formation issues from arbitration. We hold that the contract in this case plainly involves interstate commerce and that the parties did not intend to arbitrate a claim of fraudulent inducement to enter a contract. Therefore, in accordance with the Federal Arbitration Act, the chancery court properly retained jurisdiction over the claim of fraudulent inducement to enter a contract. The judgment of the Court of Appeals is affirmed.
BACKGROUND
On April 4, 1995, Gatlinburg, L.L.C. (“Gatlinburg”), entered into a contract with Frizzell Construction Company, Inc. (“Frizzell”), for the construction of a hotel in Sevier County, Tennessee. Gatlinburg owned the project, and Frizzell served as the management company in charge of constructing the hotel. The contract contained a provision stating that the laws of Tennessee would govern the contract and a provision requiring arbitration of “[a]ll claims, disputes and or other matters in questions arising out of, or relating to, this Agreement or the breach thereof....” 1
Shortly after the substantial completion of the hotel, a dispute arose between the parties relating to certain payments due to Frizzell under the contract. This dispute ultimately culminated in Frizzell filing a “Complaint to Enforce Mechanic’s Lien and for Breach of Contract” in the Sevier *82 County Chancery Court on August 22, 1997. On October 27, 1997, Gatlinburg filed its Answer, and in an amended counterclaim, Gatlinburg alleged that the contract was fraudulently induced through Frizzell’s misrepresentation of its expertise and ability to complete the project for the stated amount. On November 3, 1997, Frizzell made a demand for arbitration, and eight days later, Frizzell filed a motion to stay the court proceedings pending arbitration.
The chancellor granted Frizzell’s motion to stay and submitted the issues concerning overdue payment to arbitration. However, the court withheld from arbitration Gatlinburg’s allegation of fraudulent inducement because Tennessee law does not permit arbitration of this claim. In a motion to reconsider, Frizzell argued that because the contract involves interstate commerce, the Federal Arbitration Act (“FAA”) required submission of all disputes, including that of fraudulent inducement, to the arbitrator. The chancellor disagreed and held that the contract did not “involve interstate commerce so as to bring the contract under the FAA.” The chancellor also held, without stating any reasons, that even if the contract did involve interstate commerce, the FAA was nevertheless inapplicable.
The Court of Appeals affirmed the decision of the trial court to withhold the issue of fraudulent inducement from arbitration. While the Court of Appeals did not decide whether the contract involves interstate commerce, the court held that because the parties had chosen Tennessee law to govern the contract, the issue of fraudulent inducement could not be submitted to the arbitrator. The Court of Appeals also held that any decision as to whether the contract was subject to the FAA was “premature” until a determination was made under Tennessee law that the contract was valid. 2
We granted review to decide (1) whether this contract involves interstate commerce, and (2) whether the trial court erred in withholding the claim of fraudulent inducement from arbitration. We hold that this contract plainly involves interstate commerce and that the FAA does apply to enforce the agreement according to its terms. Because we find that the contract evidences the intent of the parties to judicially resolve a claim of fraudulent inducement, we also hold that the chancellor properly withheld this issue from arbitration.
ANALYSIS
The FAA ensures the enforcement of written agreements to arbitrate “in any maritime transaction or a contract evidencing a transaction involving commerce.... ” See 9 U.S.C. § 2 (1994). Therefore, we must first decide whether this contract is one “evidencing a transaction involving commerce” before we can decide the proper application of the FAA.
On their face, .the words “evidencing” and “involving commerce” do not seem as broad as the phrase “affecting commerce,” which is the language typically used by Congress to invoke the full range of its commerce power.
3
However, the United States Supreme Court has stated that “the word ‘involving’ is broad and is indeed the functional equivalent of ‘affect-
*83
mg.’
” Allied-Bruce Terminix Cos. v. Dobson,
As part of its constitutional authority to regulate interstate commerce, Congress may regulate intrastate activities that have a substantial relation to interstate commerce.
See United States v. Lopez,
Because the contract in this case is one that involves interstate commerce, the
*84
FAA applies to ensure that the arbitration agreement between the parties is enforced according to its terms. Section two of the FAA states that a written agreement to arbitrate “shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.”
See
9 U.S.C. § 2. Although the provisions of the FAA are to be applied in both state and federal courts,
Doctor’s Assocs., Inc. v. Casarotto,
The purpose of the FAA is “to ensure the enforceability, according to their terms, of private agreements to arbitrate.”
Mastrobuono v. Shearson Lehman Hutton, Inc.,
Arbitration under the [FAA] is a matter of consent, not coercion, and parties are generally free to structure their arbitration agreements as they see fit. Just as they may limit by contract the issues which they will arbitrate, so too may they specify by contract the rules under which that arbitration will be conducted.
Volt Info. Sciences, Inc.,
The FAA’s “proarbitration policy does not operate without regard to the wishes of the contracting parties.” Mas-
trobuono,
Therefore, the question essentially becomes “what the contract has to say about the arbitrability of petitioner’s claim.... ”
Mastrobuono,
*85
Courts should generally apply “ordinary state-law principles” in deciding whether the parties agreed to submit certain issues to arbitration.
See First Options of Chicago, Inc. v. Kaplan,
In this case, the arbitration clause purports to govern “[a]ll claims, disputes and other matters in questions arising out of, or relating to, this Agreement....” Viewed in isolation, the breadth of this clause appears to evidence an intent to submit all issues to arbitration, including issues of contract formation. However, reading the contract as a whole, the arbitration clause — along with every clause in the contract — is limited and subject to the additional qualification that Tennessee law provides the basis for deciding questions concerning its scope and interpretation.
Although the appellant urges that the Tennessee choice-of-law clause is without effect upon the arbitration clause, we can find no support for this proposition in the contract itself. The choice-of-law clause plainly states that it governs the entire agreement, and no provision in the contract appears to be exempt from the effects of the choice-of-law clause. By stating that the contract is to be governed by Tennessee law, the parties have indicated their intention to arbitrate all disputes “arising out of, or relating to” their agreement — but only to the extent allowed by Tennessee law. 12 Interpreting each clause in light of the other, we read the arbitration clause to more accurately state, “In accordance with Tennessee law, all claims, disputes, and other matters in questions arising out of, or relating to, this Agreement ... shall be decided by arbitration .... ” Therefore, because Tennessee law contemplates judicial resolution of contract formation issues, we conclude that the parties have indicated their intention not to submit such issues to arbitration.
The FAA requires the courts of this state to enforce arbitration agreements according to their terms. Because the parties in this case have agreed to arbitrate their disputes to the extent allowed by Tennessee law, we therefore hold that the chancery court properly submitted all issues relating to the merits of the *86 contract to arbitration. We also hold that the chancery court properly withheld the issue of fraudulent inducement from arbitration in accordance with the intention of the parties.
As evidence that a choice-of-law clause can not modify an arbitration clause, the appellant quotes our statement in
Tennessee River Pulp & Paper Co. v. Eichleay Corp.,
Therefore, consistent with the policies underlying the FAA, our holding in this case simply reflects that parties may choose the arbitration law by which they intend to be governed. The enforcement of this agreement according to the intent of the parties is in full accord with the FAA, even if the result is that the parties agree to submit some issues for judicial resolution that the FAA would otherwise permit arbitration to resolve. This Court “may give effect to the contractual rights and expectations of the parties, without doing violence to the policies behind the FAA.”
See Volt Info. Sciences, Inc.,
CONCLUSION
To summarize, we hold that the chancery court erred in finding that this contract is one not “evidencing a transaction involving commerce.” We also hold that when viewed as a whole, the contract reveals the intention of the parties to arbitrate all disputes to the extent allowed by Tennessee law. Because the parties did not intend to arbitrate contract formation issues, the chancellor’s decision not to submit the claim of fraudulent inducement to arbitration was consistent with the FAA. Therefore, we affirm the judgment of the Court of Appeals and remand the sole issue of fraudulent inducement to the chancery court for further proceedings consistent with this opinion.
Costs are assessed to the appellant, Frizzell Construction Company, Inc.
Notes
. The choice-of-law provision in section 14.2 of the contract states that "[t]his agreement shall be governed by the law of the place where the Project is located.” The parties agree that the clause contemplates application of Tennessee law.
. The Court of Appeals reasoned that "[i]f [the contract] is rescinded, there is nothing to arbitrate. On the other hand, if the contract is found to be valid and binding, the disputes between the appellant and the appellee are subject to arbitration.”
Frizzell Constr. Co. v. Gatlinburg, L.L.C.,
No. 03A01-9805-CH-00161, slip op. at 7,
. As the United States Supreme Court has stated, "Again, half a dozen enactments ... are sufficient to illustrate that when [Congress] wants to bring aspects of commerce within the full sweep of its constitutional authority, it manifests its purpose by regulating not only ‘commerce’ but also matters which 'affect', 'interrupt', or 'promote' interstate commerce.”
See Polish Nat'l Alliance v. NLRB,
.
See Tennessee River Pulp & Paper Co. v. Eichleay Corp.,
.
See United States v. Dye Constr. Co.,
.
See, e.g., American Home Assurance Co. v. Vecco Concrete Const. Co.,
.
See, e.g., Roberson v. The Money Tree of Alabama, Inc.,
.
See, e.g., Foster v. Turley,
. Gatlinburg argues primarily that this contract does not involve interstate commerce because the contract itself does not contemplate interstate activity. The test under the FAA, however., is whether interstate commerce
is present in fact,
not whether the parties contemplated that interstate activity would occur.
See Allied-Bruce Terminix Cos.,
. In
City of Blaine v. John Coleman Hayes & Associates, Inc.,
. Citing the Supreme Court’s decision in
Pri-ma Paint Corp.,
Frizzell argues that the FAA compels the conclusion that a claim of fraudulent inducement to enter a contract is to be resolved in arbitration. While a claim of fraud in the inducement of a contract is certainly arbitrable under the FAA, a more close reading of the opinion, however, shows that the issue arose because "there [was] no evidence that the contracting parties intended to withhold that issue from arbitration.”
. The parties in this case were both relatively sophisticated business contractors, and presumably, they were well aware that Tennessee law does not allow arbitration of contract formation issues. As such, the parties could have drafted the arbitration clause with some ease to specifically include arbitration of contract formation issues. The failure to do so, coupled with the express adoption of Tennessee law to govern the contract, leads this Court to conclude that the parties did not intend for contract formation issues to be decided by the arbitrator.
