ORDER

The opinion reported at 253 F.3d 1161 is amended as follows:

On page 1162, line 9 of text in column one, delete “River” so that name of petitioner is corrected to “Friends of the Cowlitz”.

On page 1163, line 23 of text in column two, make the same change.

On page 1162, lines 1-4, column two, change to read: “The upstream Mossyrock Dam (185 Ft., completed in 1963), and the downstream Mayfield Dam (325 ft., completed in 1968).”

The petition for rehearing is denied.

Case Details

Case Name: Friends of the Cowlitz and Cpr-Fish, City of Tacoma, Intervenor v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Feb 27, 2002
Citations: 282 F.3d 609; 2002 Cal. Daily Op. Serv. 1822; 2002 Daily Journal DAR 2215; 2002 U.S. App. LEXIS 3032; 99-70373
Docket Number: 99-70373
Court Abbreviation: 9th Cir.