*1
Fund, particularly un
argues
benefits from the
statute of limitations.5 The Fund
case,
Employer
standing
peti
file a
In
has no
to
der the facts of this case.
did,
and,
if it
specific
tion under Section 306.1
even
was awarded
loss benefits
Claimant
payments
benefit
af
Employer’s
Claimant
paid
Employer
that were to be
expiration
specific
period
loss
ter the
20,
August
Upon
expiration
until
1973.
1973)
(i.e.,
20,
August
after
did not toll
date,
Employer’s obligation
on that
Claim
agree
statute of limitations. We
option
petition
had
the Fund for
ant
Employer
has no stand
Commonwealth
continuing benefits under Section 306.1. For
306.1,
petition
to file a
under
unknown, Employer
reasons
continued to
not,
not,
therefore need
and do
reach the
an
pay benefits to Claimant for
additional
tolling
issue of the
of the statute of limita
(20)
twenty
years
peti
never
Claimant
tions.
However,
Fund.
tioned for benefits from the
Employer
argues
now
that the Fund should
statute,
construing
meaning
In
of a
we
payments
it for
reimburse
its
Claimant
Statutory
must observe
rules
Con-
eligible to file for ben
because Claimant was
1972,
struction Act of
Pa.C.S.
1501-
Employer’s
from the Fund in 1973.
efits
doing so would result
unless
responsibility,
predicament is not
Fund’s
interpretation that
is inconsistent
expect
the Fund to “bail it
cannot
out”
Assembly. Pennsylva-
intent
General
making payments
because it failed to cease
Pennsyl-
nia Association Milk Dealers v.
obligation
to Claimant when its
to do so
Board,
Marketing
vania Milk
subsequent injury, compensation additional paid during
shall be the continuance of disability_
total This additional com-
pensation paid by department shall be the ATGLEN FRIENDS OF subsequent injury
out of the All fund.... SUSQUEHANNA TRAIL, compensation claims for such additional INC., Petitioner, employ- shall be forever barred unless the petition ee shall have filed a therefor with department.... PENNSYLVANIA PUBLIC UTILITY added). (emphasis 77 P.S. Because COMMISSION, Respondent. clearly unambiguously the statute states Pennsylvania. Commonwealth Court of compensation that all claims for from the employe,” Fund filed “the we must be Argued April 1998. employer conclude that an does not have Aug. Decided 1998. standing petition file benefits the Fund.
Furthermore, common sense dictates standing employer has no to file a claim for a Section 306.1. See footnote 3 brief discussion tolling applicable of limitations of the statute *3 Nettke,
Joyce A. Strasburg, petitioner. for Colwell, Harrisburg, respon- Susan D. dent. Eaton, Harrisburg,
David C. for interve- nor, Corp. Rail Consol. COLINS, Judge,
Before President McGINLEY, SMITH, PELLEGRINI, FRIEDMAN, KELLEY and LEADBETTER, JJ.
SMITH, Judge. Trail, Atglen-Susquehanna
Friends of the (FAST) petitions Inc. for review of an order Pennsylvania Commis- (Commission) sion that with minor modifica- adopted the tions decision of an Administra- (ALJ) Judge approved tive Law two (Settlements) Stipulations of Settlement (Conrail) Corporation Rail the Consolidated townships entered into with seven in Lancas- County Pennsylvania ter and with the De- (DOT). partment Transportation rail-highway crossings The of the abolition of 31 permit- along to the Enola Branch. was Settlements relate abolition rail- highway along May ted crossings the former Enola to intervene in 1994. On March rail line to the Branch transfer Con- the Commission issued an order abol- property. ishing crossings listing rail’s others separate A hearing. proceeding involving a questions whether the Commission single crossing was consolidated preempted ordering the demolition larger case. matter was submitted bridges by of historic Interstate Commerce dispute proceedings, alternative resolution (ICC) Transporta- Surface and, negotiations, parties after extensive (STB) orders; tion Board whether Com- agreed at the Conrail arrived Settlements. complied History Code, *4 convey in the Settlements to the entire rail 101-906; §§ Pa.C.S. whether the Commis- segments townships through line in to the including sion erred this case in a passed give township it a which each adopted on cases it moratorium such money lump of related to the condition sum bridge the policy to of Governor’s crossings. majority of The the cross- preservation; the whether Commission com- kept place; to in structures were be Act, plied the Rails to Trails Act of however, to re- some were scheduled 18, 1990, 748, 32 December P.L. P.S. safety moved for reasons. 5611-5622; and whether the Commis- bridges sion’s conclusion that certain are objected, and the ALJ held FAST span supported near the end of their life in hearings June 1997. The Historic Preser by substantial evidence. The Commission (Lancaster County Trust of Lancaster vation standing questions ap- whether FAST has to Trust) joined opposition. in FAST’s brief peal. Department The Conservation and of Natu (DCNR) approved ral Resources of the Set Conrail filed notice with the ICC Octo- adopting The issued an order tlements. ALJ ber of its intent to abandon the Enola 1989 Settlements, slightly, Sep the on as modified Branch, primarily through which runs seven 23, 1997, September tember 1997. On In an townships County. Lancaster order STB, ICC, the the to issued an successor February 14, of the authorized ICC it, proceeding reopening order the before subject of to termination rail service condi- to denying request FAST’s extend histor including not transfer the tions that Conrail preservation ic to the entire Enola condition property steps and alter his- take no to preser reaffirming Branch and the historic integrity bridges toric on the line until slightly vation condition modified. as Sever completion process historic review un- parties to AL exceptions al filed J’s der of the National Section 106 Historic final order the Commission entered its Act, § 470f. Preservation 16 The U.S.C. 9, 1997, only from which FAST now October Pennsylvania Historical and Museum Com- appeals.1 (Historical Commission) commenced álong a review of the the Enola structures I part process, 106
Branch as
Section
through
but
failed to
when
it
follow
Conrail
to
turns first
Court
required
In a
sent in
information.
decision request
quash
petition for
this
Court
19, 1993,
April
the ICC authorized Conrail
review based on its contention
line but made no mention of
abandon
standing
appeal.
lacks
The Commission
concerning
106 re-
condition
citizen-based,
acknowledges
a
that FAST is
process.
view
not-for-profit organization formed
Branch to
application
purpose
acquiring
filed
Enola
Conrail
Com-
preserve
resources
September
approval
the natural
historical
mission on
Cab
a
or a
violation. Yellow
Co.
1. This Court's review of decision of
Com-
constitutional
determining
mission is limited to
whether
Pittsburgh Pennsylvania
Commis-
supported by
necessary findings are
substantial
(Pa.Cmwlth.1996).
sion,
the intervenor a direct has interest the proceeding might aggrieved by or an or- subject contends that the mat- first proceeding.” der of the Commission jurisdiction ter was 5.75(b). § 52 Pa.Code preempted by the the and the orders of ICC issue, STB, standing provided
On the merits of the
the
where the Settlements
requirement
bridges.
FAST notes that the
of a “sub
demolition of certain
The Commis-
simply
authority
crossings
stantial” interest
means
that must
sion’s
over abolition of
have substance —there must be some discer
derives from the mandate of Section 2702 of
Code,
nible adverse effect to some interest other
the Public
66 Pa.C.S.
2702.
(b)
general
having
than the
the
interest
others
Subsection
vests
Commission with
comply
power
prescribe,
with the law.
Penn Park
“to determine and
William
exclusive
Inc.,
ing Garage,
by regulation
at
...
manner in
binding upon
agencies,
other
but
contends
preservation
the record shows that
also asserts that
the historic resources involved here has not
by
including
in a
erred
this case
morato
adequately.
argues
been considered
It
upon
rium
such cases that was issued
preservation-focused
perspective is ex
poli
to the Governor’s
tended even further
properties
when historic
cy
bridge preservation.
FAST notes that
“ownership
are under the
or control” of Com
adopted
the Commission
the 18-month mora
agencies
likely
monwealth
or are
to be affect
23, 1997,
is,
torium order of October
-
508(1)
by agency
ed
actions under Sections
public meeting
at its next
after the order in
(3).
this ease.
the Commission denied
request
FAST’s
for reconsideration on November
agrees
The Court
with the Commission
case,
argues that
that Goldsborough
Department
Edu
*7
bridges,
bridges
with 26
ordered to be
cation,
487,
133 Pa.Cmwlth.
ORDER NOW, day August,
AND this 18th Pennsylvania
the order of the
Commission is affirmed. COLINS,
Dissenting opinion President
Judge. notes that the STB or- requires only part der conduct on the of that the ICC vested with FAST notes was that, should a conflict Conrail asserts power regulate the broad abandonment arise, petition Conrail could the Commission lines, rail later on the which was conferred extension. quotes Hayfield R.R. STB. FAST Northern Co., v. Chicago Inc. and North Western The concludes that the Com Court Co., 622, 633, Transp. 467 U.S. S.Ct. preempted proceeding- mission not 2610, 2617, (1984), L.Ed.2d where that its is not in this matter and order Supreme [ICC] Court stated: “[U]nless requirements. There is no conflict STB postabandonment to a attaches conditions general jurisdictions question abandonment, au [ICC’sJ certificate crossing the Commission over abolition brings reg thorization an abandonment its over are dif the STB rail line abandonment ulatory Preemption to an end.” Transp., ferent matters. Inc. CSX state law federal law take various conducting .its di proceeding Commission’s forms, notes, including what is known necessary rected toward the ultimate and preemption,” “conflict law ac where state crossings unques disposition of its within tually that it conflicts with federal law such jurisdiction party tioned did violate STB’s impossible private comply for a require the order. “or law an obsta order or Conrail violate both where state ‘stands as accomplishment Although approval will cle to and execution Settlements objectives purpose ultimately prop the full of Con in transfer of Conrail result
Notes
notes The Commission removals. grade a railroad DCNR, or removal of initial re charged abandonment tunnel, suitability bridge “shall consider of this crossing, sponsibility to evaluate development, develop upon the for trail impact action railroad lines of such and other ment, proceedings party recreational existing use of was an active expansion and identify and supports act and the Settlements. pursuant to this trails Rails to Trails any under the minimize duties will Commission’s alternatives which evaluate original mandate remove the upon Act cannot actions of commission impacts adverse COLINS, dissenting. Judge, protect public safety un- President the Commission to 2702(b) of the Public der Section majority’s only far as to the I dissent so Code. V of the conclusions contained agrees This Court that the record opinion. I do scholarly well-prepared did this case shows properly considered not feel that the ALJ obligations comply with its under the Rails the Rails to “mitigating” issues under impact of its action Trails Act to consider Trails Act. identify approving Settlements participation alternatives. extensive I remand to the ALJ for additional would in this case and the admission into and, regarding mitigation findings of fact Plan, well as the evidence of its Master thereafter, propriety a reconsideration participation to the DCNR Com made with the various of the settlements procedures providing notice to mission’s townships. cases, that the ALJ and DCNR such show considered alternatives to proposed ap action. The Commission might proved letting bridges some stand that otherwise have been ordered to be removed any for the benefit of future trail use. The require Rails to Trails Act does not more. VI Finally, FAST contends that the bridges Commission’s conclusion that some span support are near the end of their life option supported for demolition was not by substantial evidence. FAST asserts that testimony the ALJ misunderstood the of its PENN SCHOOL WILLIAM concluding bridges DISTRICT, Petitioner, witness Wilson in had the end of neared their useful lives. The findings, ALJ made over 350 factual most of descriptions which concerned detailed APPEAL WORKERS' COMPENSATION here, bridges condition of each of the at issue (WESTERMAN), BOARD BTS, upon reports based Conrail and Respondent. townships. adopted The Commission findings. these Substantial evidence is such Pennsylvania. Court of Commonwealth person might evidence as a reasonable accept support finding as sufficient to of fact. July Briefs 1998. Submitted on In O’Connor. the Court’s view the record Aug. Decided ample support contains evidence to the find here, bridges that the older involved all shortly of which were constructed after the century, reasonably turn of the last nearing viewed as the end of their useful Accordingly, lives. the order of the Commis sion is affirmed.
