Opinion
This is one of several lawsuits Friends of Outlet Creek (Friends) is pursuing in an effort to prevent asphalt production at the site of an aggregate operation. The Mendocino County Air Quality Management District (District) and Grist Creek Aggregates, LLC (Grist Creek), successfully demurred on the ground Friends can only proceed against the District in an administrative mandamus proceeding under Health and Safety Code section 40864, which the District and Grist Creek contend cannot embrace a challenge under the California Environmental Quality Act (CEQA; Pub. Resources Code, § 21000 et seq.). Friends, in turn, has expressly disclaimed any reliance on Health and Safety Code section 40864 and asserts it can sue the District directly under CEQA. The trial court sustained the District and Grist Creek’s demurrer, and dismissed the action.
We reverse, as there is established precedent allowing CEQA claims against air quality management districts. However, that does not mean Friends can challenge any land use designations or authorizations pertaining
Background
Since 1972, the County has granted land use approvals for aggregate and asphalt production on the site at issue.
Seven years later, in 2009, the County updated its general plan, changing the land use designation of the site from rangeland to industrial. In doing so, the County proceeded under CEQA and prepared an environmental impact report (EIR). The following year, in 2010, the County, consistent with its updated general plan, rezoned 61 parcels, including the site at issue, to conform to the updated use designations. In doing so, the County relied on its previously certified EIR. According to County planning staff the “approved zoning change thus allows, by right, industrial uses that were previously considered to be non-conforming and subject to discretionary land use entitlements.” There was no judicial challenge to either the general plan update or the rezoning.
After Grist Creek acquired the site, it applied to the County for development review of its proposed continuation and resumption of aggregate and asphalt production at the site. The County Planning and Building Services Department’s (Planning Department) staff report for the review stated there had been little asphalt production primarily due to market conditions and over the years much of the asphalt processing equipment had been removed. It further stated that due to environmental impacts that could result from asphalt
In late 2014, the Planning Department and Grist Creek again discussed the production of asphalt, and in March 2015, the matter was presented directly to the County Board of Supervisors by way of an “Operational Statement” that asked the board to decide whether the proposed resumption of asphalt production at the site would be a “new or changed” industrial use under the County’s zoning ordinance.
The board, by way of a March 2015 resolution, declared the proposed use was neither a new, nor a changed, industrial use, and that it was a permitted use subject to the conditions of approval of the 2002 use permit (which were attached to the resolution). Three days later, the Planning Department issued a “Notice of Exemption” for the “[rjesumption of activity at the . . . aggregate processing plant,” specifying the County as the “Public Agency Approving Project,” checking a box that the “Exempt Status” was “Ministerial (§ 21080, (b)(1); 51268).” Friends promptly filed a lawsuit against the County challenging this resolution.
Having obtained approval of asphalt production from the County, Grist Creek applied to the District for an Authority to Construct.
Later in the same month, the County Board of Supervisors adopted a second resolution. Expressly stating it wished to avoid protracted and expensive litigation under CEQA, the board of supervisors rescinded its March 2015 resolution. The new, June 16, 2015, resolution also expressly stated it did not impact any land use entitlements or authorizations that existed in connection with the site prior to the March 2015 resolution. Friends then filed an amended pleading in its lawsuit against the County. The County, in turn, successfully demurred on the ground the lawsuit was moot, given that the March 2015 resolution Friends was challenging had been rescinded. Friends appealed, and that appeal (Friends of Outlet Creek v. County of Mendocino, supra, A147499) now rests with another division of this court.
In the meantime, a month after the District’s air pollution control officer approved an Authority to Construct, Friends, in July 2015, filed an administrative appeal to the District’s hearing board. During these proceedings, the District presented the following in support of the air pollution control officer’s determination that the District did not need to conduct further environmental review: (1) the County’s 2009 EIR done in connection with updating its general plan; (2) the County’s approval of the general plan changes; (3) the County’s rezoning of the site to industrial; and (4) the 2002 mitigated negative declaration adopted by the County and the prior use permit issued by the County authorizing an asphalt plant at the site. The hearing board denied Friends’ appeal in early September in a written decision, setting forth its findings and the evidence supporting them.
The District and Grist Creek demurred to both causes of action on the ground Friends cannot sue the District directly under CEQA, but, instead, can only sue it under Health and Safety Code section 40864, which they maintain cannot be used to make a CEQA challenge. The trial court agreed and sustained the demurrers. Although granted leave to amend, Friends elected to stand on its allegations, and the court subsequently dismissed the case.
Discussion
Friends continues to disclaim any reliance on Health and Safety Code section 40864, contending it can sue the District directly under CEQA. When asked, at oral argument, why it has taken this procedural posture, Friends stated it believes it can obtain greater relief under CEQA than it can under Health and Safety Code section 40864.
Suing “Under” CEQA
There is considerable precedent that air quality management districts can be sued for failing to comply with CEQA. Most of these cases involved challenges to district-adopted rules and regulations, and, thus, were brought as ordinary mandamus actions challenging quasi-legislative action under Code of Civil Procedure section 1085 in conjunction with declaratory relief claims. (E.g., California Building Industry Assn. v. Bay Area Air Quality Management Dist. (2015)
Other cases, however, involved challenges to individual permit decisions, like the District’s approval here of an Authority to Construct. (E.g., Communities for a Better Environment v. South Coast Air Quality Management
No case, however, suggests that only Health and Safety Code section 40864 can be invoked in challenging an action by an air quality management district, whether it be quasi-legislative or quasi-adjudicative in nature. And, as we have set forth, there is established authority that an air quality management district can be sued in both contexts “under” CEQA.
Moreover, the District’s hearing board’s decision expressly recognizes that the District has an obligation to determine whether there has been adequate compliance with CEQA. For example, the hearing board explained: “Upon every application for an Authority to Construct or Permit to Operate, the District must either prepare a CEQA document or the [air pollution control officer] must make one of the following findings: ‘(1) the application is for a project or a portion of a project for which another public agency has already acted as the lead agency in compliance with CEQA; (2) the project is categorically exempt; (3) the project is ministerial; or (4) it can be seen with certainty that the project will not have a significant effect on the environment.’ ([Regs., reg. 1, appen.] A, § 111(a).) The [air pollution control officer]’s determination ‘will be set forth in a written statement which shall be furnished to the applicant and made available to any members of the public upon request. A copy of said statement shall be affixed to any permit granted or denied.’ ” Specifically, “District Regulation 1, Appendix A requires the District to either prepare a CEQA document or make certain preliminary findings. ... If the District determines that an application is for a project that has not previously undergone CEQA and is not otherwise exempt, the District must prepare its own CEQA document.” The hearing board went on to state: “Here, the [air pollution control officer] prepared an Engineering Statement wherein he determined that ‘[t]he project as proposed is not categorically exempt from the requirements of [CEQA] . . . , but is a project or portion of a
Accordingly, we conclude Friends can sue directly “under” CEQA and its petition is not fatally deficient for failure to invoke Health and Safety Code section 40864.
The Scope of a “CEQA Challenge ” in This Case
However, the fact Friends can bring this lawsuit “under” CEQA does not mean it can obtain relief, if any, beyond overturning the decision of the hearing board and invalidating the Authority to Construct. In suggesting it can obtain greater relief, such as obtaining a declaration or injunction against use of the site for aggregate and asphalt production, Friends ignores that the District has had only a limited role in this ongoing land use controversy— namely, assessing air quality impacts and approving issuance of an Authority to Construct for Grist Creek’s proposed asphalt production.
While Friends, in this lawsuit, can challenge the District’s approval of the Authority to Construct, it cannot challenge any of the County’s land use designations or approvals for use of the site. Rather, to challenge the County’s legislative, regulatory and administrative land use actions, it must seek recourse against that governmental body. Thus, Friends cannot, in this case, challenge the adequacy of the County’s prior CEQA reviews, for example, by asserting the County should have prepared a full EIR, rather than a mitigated negative declaration, in connection with any prior use designations or approvals.
Furthermore, the instant lawsuit against the District is—under controlling procedural law—an administrative mandamus proceeding. There is no ignoring that the requisites of administrative mandamus were met—a hearing was required, evidence was taken, and there was discretion in the determination of the facts vested in the administrative agency. (Code Civ. Proc., § 1094.5, subd. (a); Health & Saf. Code, § 40820 et seq.) Accordingly, even under CEQA, this lawsuit must proceed as an administrative mandamus proceeding under Code of Civil Procedure section 1094.5. (Pub. Resources Code, §§ 21168, 21168.5 [expressly providing for review in accordance with Code Civ. Proc., § 1094.5],)
That this is an administrative mandamus proceeding will not, as Friends seems to suggest, constrain its ability to challenge the Authority to
Thus, Friends can advance claims that, in approving the Authority to Construct, the District acted in violation of the law, either CEQA or its own rules. For example, whether the proposed asphalt operation is a “project for which another public agency has already acted as the lead agency in compliance with CEQA” as the air pollution control officer determined (and a determination the hearing board sustained) is, ultimately, a question of law to be decided on the underlying facts and any matters properly subject to judicial notice—and it appears to be the pivotal issue in this case.
Ministerial or Discretionary Action
As an alternative ground to affirm, Grist Creek contends the District’s issuance of the Authority to Construct was, in any event, a ministerial action falling outside CEQA.
There is no dispute “CEQA applies to discretionary actions but does not apply to ministerial actions: ‘Public Resources Code section 21080, subdivision (a) states that the provisions of CEQA apply only to “discretionary projects [fn. omitted] proposed to be carried out or approved by public agencies, including, but not limited to, the enactment and amendment of zoning ordinances, the issuance of zoning variances, the issuance of conditional use permits and the approval of tentative subdivision maps Section 21080, subdivision (b)(1) specifically excludes from coverage by CEQA “ministerial projects” approved by public agencies.’ ” (Health First v. March Joint Powers Authority (2009)
However, neither the air pollution control officer, nor the hearing board, appear to have treated approval of the Authority to Construct as a ministerial
Generally, an agency’s determination of whether an activity falls under the ministerial exemption is reviewed for “ ‘a prejudicial abuse of discretion.’ ” (Muzzy Ranch Co. v. Solano County Airport Land Use Com. (2007)
Given the paucity of the record currently before us in connection with the demurrer, we cannot now evaluate the air pollution officer’s apparent determination that the permit was not a ministerial act. In fact, on a fully developed record, it may be that Grist Creek is correct in asserting issuance of the Authority to Construct was, under the circumstances, a ministerial act. But that is not an issue we are able to fully consider, let alone rule on as an alternative basis to affirm the dismissal.
Exhaustion
As a further alternative ground for affirmance, Grist Creek maintains Friends did not sufficiently exhaust administrative remedies. Grist Creek does not contend Friends failed to pursue its internal administrative remedy— indeed, Friends timely appealed to the District’s hearing board. Rather, Grist Creek asserts: “The trial court does not have jurisdiction to determine whether the 2002 mitigated negative declaration and/or 2009 EIR properly analyzed the environmental impacts of asphalt production at the Property because Appellant did not exhaust its administrative remedies challenging these CEQA determinations.”
Disposition
The judgment of dismissal is reversed. Costs to appellant.
A petition for a rehearing was denied April 12, 2017, and on May 25, 2017, the opinion was modified to read as printed above. The petition on the court’s own motion for review by the Supreme Court was granted May 24, 2017, S241669. On May 24, 2017, cause transferred to Court of Appeal, First Appellate District, Division One, with directions.
Notes
On our own motion and after notice to the parties (Evid. Code, § 459), we have taken judicial notice of the record and appellate briefs in another appeal by Friends pending in another division of this court. Friends of Outlet Creek v. County of Mendocino (A147499, app. pending).
At that time, the owner of the site was “ ‘strongly encouraged’ ” by the County to seek a general plan amendment and rezoning prior to the permit’s expiration in 2012 “as a means of avoiding issues stemming from potential zoning conflicts between the Rangeland zoning and the continued non-conforming use.”
The County Board of Supervisors has reserved to itself original jurisdiction to review land use matters and can request direct review of development applications. (County Code, ch. 2.54, § 2.54.010.) Under the County Code, chapter 20.188, section 20.188.025, subdivision (C), a “new or changed industrial use shall require further review.” Review entails following “the ‘State CEQA Guidelines.’ ” (County Code, ch. 20.188, § 20.188.025, subd. (A).)
“California has divided responsibility for control of ah pollution between the [State Ah Resources] Board and 35 local and regional air quality management districts. . . . [¶] The Board is ‘charged with coordinating efforts to attain and maintain ambient air quality standards, to conduct research into the causes of and solution to air pollution, and to systematically attack the serious problem caused by motor vehicles, which is the major source of ah pollution in many areas of the state.’ ([Health & Saf. Code,] § 39003.) The Board has exclusive responsibility for control of emissions from motor vehicles, while the local and regional districts have primary responsibility for control of ah pollution from all sources other than emissions from motor vehicles. ([M,] §§ 39002, 39500, 40000.) These districts ‘shall adopt and enforce rules and regulations to achieve and maintain the state and federal ambient air quality standards in all areas affected by emission sources under their jurisdiction, and shall
Title 42 United States Code section 7401 et seq.
We also note that exhaustion of administrative remedies is required under CEQA. (Tahoe Vista Concerned Citizens v. County of Placer (2000)
