FRIENDS OF MAINE‘S MOUNTAINS et al. v. BOARD OF ENVIRONMENTAL PROTECTION et al.
2013 ME 25
Supreme Judicial Court of Maine.
March 5, 2013
61 A.3d 689
Argued: Nov. 8, 2012.
William J. Schneider, Attorney General, and Gerald D. Reid, Asst. Atty. Gen. (orally), Augusta, for appellee Board of Environmental Protection.
Gordon R. Smith, Esq. (orally), and Juliet T. Browne, Esq., Verrill Dana, LLP, Portland, for appellee Saddleback Ridge Wind, LLC.
Panel: SAUFLEY, C.J., and LEVY, SILVER, MEAD, GORMAN, and JABAR, JJ.*
SILVER, J.
[¶ 1] Friends of Maine‘s Mountains, Friends of Saddleback Mountain, and several individuals1 (collectively, Friends) appeal from a final order of the Board of Environmental Protection. The Board affirmed the Department of Environmental Protection‘s order approving the application of Saddleback Ridge Wind, LLC (Saddleback), for a permit to construct the Saddleback Ridge Wind Project.
[¶ 2] Friends argues that the Board abused its discretion when determining which nighttime sound level limit to apply to the applications. Friends also makes three constitutional arguments: (1) that the Maine Wind Energy Act,
I. BACKGROUND AND PROCEDURE
[¶ 3] On October 26, 2010, Saddleback filed with the Department applications pursuant to the Site Location of Development Law and the Natural Resource Protection Act, seeking a permit to build a wind energy development in the Towns of Carthage, Canton, and Dixfield. The applications described the development as a “12-turbine, 33 [megawatt] wind energy project and associated transmission line and substation.” The applications included a noise impact study and a visual impact assessment, which the Department hired consultants to review as part of its application review. The visual impact as
[¶ 4] Friends objected to the permit application, attaching exhibits including extensive scientific literature on the health effects of the noise emitted by wind turbines, and requested that the Department hold a public hearing. The Department reviewed the material, and the acting commissioner for the Department issued a letter denying the hearing request.
[¶ 5] In response to the public interest in the project, the Department held a public meeting, pursuant to
[¶ 6] In its final order, issued by the acting commissioner on October 6, 2011, the Department approved the application subject to certain conditions. Although only the Department has jurisdiction to grant wind energy applications,
[¶ 7] Friends appealed the Department‘s order to the Board. On appeal, Friends requested “a public hearing before an impartial hearing officer” to assist the Board in understanding the conflicting technical evidence. See
[¶ 8] Specifically, the Board affirmed the Department‘s decision to apply the nighttime sound level limit in effect at the time of the order, which was 45 dBA. The Board also found that the visual impact criteria of the Wind Energy Act provided adequate guidance for its consideration of
[¶ 9] While Saddleback‘s applications were pending before the Department, the Board, in its role as the body responsible for making rules and providing guidance to the Legislature, was studying the noise emitted by wind energy developments. A petition to amend the noise regulation at 2 C.M.R. 06-096 375-6 to -15 § 10 (2001) was filed with the Board on December 17, 2010, sixty days after Saddleback submitted its permit applications. The Board received comments and evidence regarding the amendment and held a hearing on July 7, 2011. On September 15, 2011—twenty-one days before the Department approved Saddleback‘s permit limiting the nighttime noise emission to 45 dBA—the Board provisionally adopted the amendment that, among other changes, lowered the nighttime sound limit for wind energy projects from 45 dBA to 42 dBA. Compare 2 C.M.R. 06-096 375-7 § 10(C)(1)(a)(v) (2001) with 2 C.M.R. 06-096 375-15 § 10(I)(2)(b) (2012). The Board submitted the rule to the Legislature for final adoption, pursuant to
[¶ 10] As noted above, the Board‘s affirmance of the Department‘s decision to apply the 45 dBA limit to this project occurred on February 15, 2012, five months after the Board adopted the 42 dBA nighttime sound level limits, subject only to final legislative approval.
II. DISCUSSION
[¶ 11] Friends asserts that the Board applied the incorrect nighttime sound level limit to Saddleback‘s permit applications. Additionally, it makes three constitutional arguments, two of which challenge the constitutionality of the Wind Energy Act, with the third argument asserting that the Board and Department violated Friends‘s due process rights. We review for an abuse of discretion the Board‘s decision regarding which sound level limit to apply.
A. Nighttime Sound Level Limits
[¶ 12] The Board regulates the sound levels of wind projects to protect “the health and welfare of nearby neighbors.” 2 C.M.R. 06-096 375-6 § 10(A) (2012). In order to fulfill this goal, the Board‘s rules provide it with the flexibility necessary to impose limits on proposed wind projects so that sound levels are adequately controlled. 2 C.M.R. 06-096 375-10 § 10(E) (2012).4 See also Martha A.
[¶ 13] Saddleback‘s permit application shows that the project does meet the 45 dBA nighttime sound level limit, as required by the pre-amendment rules. See 2 C.M.R. 06-096 375-7 § 10(C)(1)(a)(v) (2001). The application does not show, however, that the project meets the amended nighttime sound level limit of 42 dBA. See 2 C.M.R. 06-096 375-15 § 10(I)(2)(b) (2012). On appeal, the Board “is not bound by the [acting] commissioner‘s findings of fact or conclusions of law but may adopt, modify or reverse findings of fact or conclusions of law established by the commissioner.”
[¶ 14] The Board does not commit an abuse of discretion simply by making discretionary judgments that we, as a reviewing court, disagree with. Sager, 2004 ME 40, ¶ 11, 845 A.2d 567. Here, however, the Board, in its legislative role, explicitly determined that 45 dBA does not protect nearby residents as a nighttime sound level limit for wind projects, but it does nonetheless continue to apply that sound level limit in its adjudicatory role.6
[¶ 15] As discussed above, in its legislative capacity, the Board adopted the reduced sound level limit in order to minimize the impact from wind projects on the health of nearby residents, noting “[t]he available data demonstrates that persons living near existing wind energy development with actual sound level measure
[¶ 16] Saddleback‘s noise impact study shows that the modeled nighttime sound level at the most significantly affected residence7 is 44 dBA, and it asserts that due to the use of conservative models, the monitored level is likely to be even lower. The Board appeared to rely on this model calibration in its decision to uphold the Department‘s approval of the permit application, stating:
If the Board was convinced under specific facts that requiring lower sound levels in the modeling results was necessary in order to achieve adequate control of noise from a development the Board could do so under Chapter 375(10)(E). However, the Board finds that the Chapter 375 standards currently in effect should adequately control noise due to the reliability of the model and the facts and assumptions used by the applicant in its modeling.
In essence, the Board found that the residents would not be exposed to the effects of 45 dBA nighttime sound levels, but instead the noise would be somewhere below that limit. There is no indication, however, that the nighttime sound levels would be as low as 42 dBA.8
[¶ 17] Because the Board is responsible for regulating sound levels in order to minimize health impacts—and because when doing so it determined that the appropriate nighttime sound level limit to minimize health impacts is 42 dBA—the Board abused its discretion by approving Saddleback‘s permit applications.9 Although the project‘s models predict nighttime sound levels slightly below 45 dBA, the Board failed to give the nearby residents the acknowledged protection of the amended rules. We vacate the Board‘s order and remand for further review using the 42 dBA nighttime sound level limit as introduced in 2 C.M.R. 06-096 375-15 § 10(I)(2)(b)(2012).
B. Equal Protection Clause and the Wind Energy Act
[¶ 18] Friends argues that the Wind Energy Act violates the Equal Protection Clause by refusing to treat Webb Lake as a “scenic resource of state or national significance.” Because the users of Webb Lake are not members of a suspect class, Friends must show “(1) that similarly situated persons are not treated equally under the law, and (2) that the statute is not rationally related to a legitimate state interest.” MacImage of Me., LLC v. Androscoggin Cnty., 2012 ME 44, ¶ 33, 40 A.3d 975 (quotation marks omitted).
[¶ 19] When reviewing a permit application pursuant to the Wind Energy Act, the Board determines whether the project “significantly compromises views from a scenic resource of state or national significance.”
[¶ 20] The Legislature enacted the Wind Energy Act as a means to promote wind as a renewable energy source and streamline the permitting process for wind energy. See
C. Separation of Powers Clause and the Wind Energy Act
[¶ 21] Friends argues that the Wind Energy Act‘s criteria for assessing visual impact,
[¶ 22] The criteria in dispute consist of six factors the Board considers when making its determination regarding a wind energy project‘s impact on scenic resources.
D. Due Process Rights and the Bias
[¶ 23] Finally, Friends argues that its due process rights were violated because the Department and Board were not impartial fact-finders. Due process requires a fair and unbiased hearing. Lane Constr. Corp. v. Town of Washington, 2008 ME 45, ¶ 29, 942 A.2d 1202. In order to show bias, however, Friends must present evidence sufficient to overcome a presumption that the fact-finders, as state administrators, acted in good faith. Mallinckrodt LLC v. Littell, 616 F.Supp.2d 128, 142 (D.Me.2009); see Mutton Hill Estates, Inc. v. Town of Oakland, 468 A.2d 989, 991 (Me.1983) (finding bias due to ex parte meetings). Although the Department and Board ruled against Friends, the rulings do not demonstrate bias. As a result, Friends‘s due process rights were not violated.
The entry is:
Judgment vacated and remanded for further proceedings consistent with this opinion.
Notes
The Board may, as a term or condition of approval, establish any reasonable requirement to ensure that the developer has made adequate provision for the control of noise from the development and to reduce the impact of noise on protected locations. Such conditions may include, but are not limited to, enclosing equipment or operations, imposing limits on hours of operation, or requiring the employment of specific design technologies, site design, modes of operation, or traffic patterns.
The Wind Energy Act also states findings related to the regulatory process inThe Legislature finds that it is in the public interest to explore opportunities for and encourage the development, where appropriate, of wind energy production in the State in a manner that is consistent with all state and federal environmental standards and that achieves reliable, cost-effective, sustainable energy production on those sites in the State that will attract investment and permit the development of viable wind energy projects.... The Legislature finds it is in the public interest to encourage the construction and operation of community wind power generation facilities in the State.
The Legislature finds that it is in the public interest to reduce the potential for controversy regarding siting of grid-scale wind energy development by expediting development in places where it is most compatible with existing patterns of development and resource values when considered broadly at the landscape level. Accordingly, the Legislature finds that certain aspects of the State‘s regulatory process for determining the environmental acceptability of wind energy developments should be modified to encourage the siting of wind energy developments in these areas.
- The significance of the potentially affected scenic resource of state or national significance;
- The existing character of the surrounding area;
- The expectations of the typical viewer;
- The expedited wind energy development‘s purpose and the context of the proposed activity;
- The extent, nature and duration of potentially affected public uses of the scenic resource of state or national significance and the potential effect of the generating facilities’ presence on the public‘s continued use and enjoyment of the scenic resource of state or national significance; and
- The scope and scale of the potential effect of views of the generating facilities on the scenic resource of state or national significance, including but not limited to issues related to the number and extent of turbines visible from the scenic resource of state or national significance, the distance from the scenic resource of state or national significance and the effect of prominent features of the development on the landscape.
