This is an appeal of a declaratory judgment in a bond validation action authorizing the Guadalupe-Bianco River Authority (“the Authority”) to issue bonds relating to a water project that had been approved by the Texas Natural Resource Conservation Commission (“the TNRCC” or “the Commission”).
1
Appellant Friends of Canyon
BACKGROUND
The Authority is a ten-county conservation and reclamation district and agency of the State of Texas. See Tex. Const, art. XVI, § 59. On August 29, 1997, the general manager of the Authority, William E. West, filed an application (“the Application”) with the TNRCC requesting authorization to meet increasing demands for surface water in central Texas communities. The Application sought to: (1) increase the annual take from Canyon Reservoir from a maximum of 62,900 acre feet of water to 120,000 acre feet, (2) increase the maximum allowable over five consecutive years from 250,000 acre feet to 450,000 acre feet, and (3) sell the water outside of the Authority’s ten county area. On August 15, 1999, shortly after the Application had been declared administratively complete, notice of the Application was published in the San Antonio Express-News and the New Braunfels Herald-Zeitung, newspapers of general circulation in the area surrounding Canyon Reservoir. The TNRCC approved the Application and on August 9, 2001, issued an Amendment, to the Authority’s Certificate of Adjudication No. 18-2074 (“the Amendment”).
Shortly thereafter, appellant was incorporated and immediately filed three lawsuits contesting the TNRCC’s amendment decision. 2 Meanwhile, for the purpose of undertaking the water project, the Authority approved a resolution to issue $75,000,000 in contract revenue bonds. Issuance of the bonds was not approved by the Attorney General, however, because their security was jeopardized by the pending lawsuits. Therefore, the Authority brought this declaratory judgment action to resolve the controversy surrounding the issuance of the bonds. See Tex. Gov’t Code Ann. § 1205.021 (West 2000) (“Expedited Declaratory Judgment Act”).
FOCL and the other appellees, including the TNRCC, intervened in the Authority’s
However, the district court did not dismiss FOCL’s Open Meetings Act challenge, and on March 18, 2002, it conducted a trial on the Authority’s request for relief under the Expedited Declaratory Judgment Act and FOCL’s Open Meetings Act claims. In its final judgment, the district court ruled that the Authority had shown itself entitled to the relief sought and FOCL had failed to demonstrate any violation by the Authority of the Open Meetings Act. In its findings of fact and conclusions of law, the district court determined, among other things, that: (1) the actions relating to the Application that were taken by the Authority at its October 16, 1996 and August 20, 1997 board meetings were a “logical consequence” of the meetings and were, therefore, in compliance with the Open Meetings Act; (2) neither FOCL nor any of its members requested a contested case hearing on the Application; (3) FOCL’s Open Meetings Act claims were moot and impermissible collateral attacks on the Amendment; 4 and (4) the Application was, in any case, approved and ratified by the Authority’s Board on June 13, 2001, in a meeting that complied with the Open Meetings Act. FOCL’s challenges to the Amendment were thus without merit, and the Amendment constituted a valid and binding action of the TNRCC. The district court’s judgment authorized the Authority to issue the bonds necessary for its water project. This appeal followed.
DISCUSSION
On appeal, FOCL presents its Open Meetings Act issue first and the plea to the jurisdiction issue second. Because some arguments relevant to the first issue are addressed in our discussion of the
Plea to the Jurisdiction
A plea to the jurisdiction challenges the district court’s authority to determine the subject matter of the cause of action.
Bland Indep. Sch. Dist. v. Blue,
It is well settled that a party must exhaust its administrative remedies before seeking judicial review of an agency decision.
See
Tex. Gov’t Code Ann. § 2001.171 (West 2000);
see also Wilmer-Hutchins Indep. Sch. Dist. v. Sullivan,
FOCL, however, contests the applicability of the exhaustion doctrine to its case. It contends that the Authority places FOCL in an impossible situation because neither it, nor any of its members, was ever provided with notice of the Application. According to FOCL:
The trial court’s dismissal of [FOCL’s] claims for failure to request a contested case hearing begs the question of how a protestant can challenge an agency’s failure to post adequate notice of a permit. Neither [FOCL], nor any of its members, requested a contested case hearing from the TNRCC upon the [Authority] permit application precisely because the TNRCC and the [Authority] failed to follow the requirements for notice of such a permit.
In reviewing
de novo
the district court’s determination of subject-matter jurisdiction, we are to “construe the pleadings in favor of the plaintiff,” look to the pleader’s intent, and accept the pleadings’ factual allegations as true.
Rylander v. Caldwell,
We need not examine the merits of these factual allegations to determine whether the district court has jurisdiction.
See Bland Indep. Sch. Dist.,
(1) not less than 30 days before the date of action on the application by the commission, the applicant has published the commission’s notice of the application at least once in a newspaper regularly published or circulated within the section of the state where the source of water is located;
[[Image here]]
(3) within 30 days after the date of the newspaper publication of the commission’s notice, a public hearing has not been requested in writing by a commissioner, the executive director, or an affected person who objects to the application.
Tex. Water Code Ann. § 11.132(d)(l)(3) (West 2000). FOCL admits that neither it, nor any of its members, requested a contested case hearing within 30 days following the publication in these newspapers of notice of the Authority’s application. Nor is there an attempt to show that these notices were insufficient or not in compliance with the Water Code.
FOCL contends that even if the exhaustion doctrine controls in this case, its failure to exhaust should be excused because certain exceptions apply. FOCL argues that it should not be required to exhaust when its challenge of agency action is based upon allegations that the Authority and the TNRCC “exceeded its statutory authority or jurisdiction” or violated a statute. FOCL also contends that its petition in intervention raised questions of law not governed by the exhaustion doctrine.
9
Texas courts have held the exhaustion doctrine inapplicable when the action complained of was taken without authority or in violation of a statute.
See Westheimer Indep. Sch. Dist. v. Brochette,
In this case, where the dispute focuses on issuance of an amendment after a lengthy administrative process, these exceptions to the exhaustion doctrine could only have been invoked if FOCL had sought judicial relief before the final agency order. For example, in
Yamaha v. Motor Vehicle Div.,
We recognize that in certain limited circumstances, e.g., when an agency acts outside its constitutional or statutory authority, a party may challenge the agency’s action independent of the procedural requirements imposed by APTRA in a statutory suit for judicial review.... This exception, however, allows a party to challenge the agency’s action prior to the rendition of a final order.
Id.
at 229 (emphasis in original) (citations omitted). Similarly, FOCL has waited until
after
the issuance of the Amendment to make any challenge to the actions taken by the Authority and the TNRCC. Although the situation confronting FOCL differs
Furthermore, while FOCL’s petition in intervention alleges that the TNRCC exceeded its statutory authority, the basis alleged for that complaint is not sufficient to confer jurisdiction. FOCL asserts that “Senate Bill 1 and the Coastal Management Act applied to the [Authority’s] Application because neither the TNRCC nor the [Authority] were complying with the requirements of these acts in the processing of the Application.” FOCL contends that the agencies failed to provide notice of the Application and the Authority failed to provide statutorily required information to the TNRCC as part of the application process; therefore, the TNRCC exercised authority beyond that conferred by the legislature. But whether the agencies correctly complied with all of the intricacies of the application process cannot be the factor that confers jurisdiction. Rather, FOCL was required to allege that the TNRCC, by approving the Application and issuing the Amendment, acted wholly outside its jurisdiction.
See Gonzalez v. Texas Edu. Agency,
FOCL also argues that because the Authority brought this action pursuant to Chapter 1205 of the Government Code, standing was thereby conferred on FOCL “to contest the validity of any of the actions taken by the [Authority].”
See
Tex. Gov’t Code Ann. § 1205.021 (West 2000) (“Expedited Declaratory Judgment Act”). Appellees respond that this is an incorrect view of the Expedited Declaratory Judgment Act because it does not alter the “preconditions to filing a suit for administrative review.” We agree with the appellees. The legislature enacted the Expedited Declaratory Judgment Act to provide a method of adjudicating the validity of public securities in an efficient and quick manner.
Hatten v. City of Houston,
Finally, FOCL cannot confer or create jurisdiction solely because it sought a declaratory judgment under the Administrative Procedure Act (“APA”). Section 2001.038 of the APA authorizes a suit for declaratory judgment to determine “the validity or applicability of a rule,” and states that “a court may render a declaratory judgment without regard to whether the plaintiff requested the state agency to
In
WBD,
the declaratory judgment action under the APA sought to challenge the “validity or applicability” of rulings adopted by the Railroad Commission for the consolidation of an oilfield; we determined that these met the APA’s general requirements of an administrative rule.
WBD Oil & Gas,
Challenges to the Amendment are effective only within the context of an appeal to the TNRCC through administrative channels, not by seeking a declaratory judgment that the TNRCC violated the administrative code. As this Court recently held, section 2001.038 of the Texas Government Code does not confer jurisdiction upon a court to determine whether an administrative agency has complied with the administrative code.
See Texas Dep’t of Transp. v. City of Sunset Valley,
Texas Open Meetings Act
In its first issue, FOCL complains that the district court erred in failing to find the Authority violated the Open Meetings Act (“the Act”). FOCL contends the Authority violated the Open Meetings Act as a matter of law because the notice it published before the August 20, 1997 board meeting was inadequate to inform the public of the meeting’s subject matter. Because the facts are undisputed as to the content of the notice, a determination of its adequacy under the Open Meetings Act is a question of law.
See Rettberg v. Texas Dep’t of Health,
In
Lower Colorado River Authority v. City of San Marcos,
Two years later, in
Texas Turnpike Authority v. City of Fort Worth,
In
Cox Enterprises, Inc. v. Board of Trustees of the Austin Independent School District,
In
City of San Antonio v. Fourth Court of Appeals,
Applying the supreme court’s rulings about the purpose of giving notice to the public, we hold that the Authority’s notice is adequate. The supreme court has held notices to be sufficiently descriptive that alerted readers to the particular issue the governing bodies would address — changes in electric power rates, the enlargement of the Dallas-Fort Worth turnpike, and condemnation of land located in a specific area of Bexar County. Although we agree that the Authority’s notice is not as clear as it might be, we believe that the notice is sufficient to give adequate notice to the public and certainly more descriptive than, for example, the broad topics held to be inadequate in Cox Enterprises. The Authority notified the public that it would consider a ‘Water Purchase Contract among” a list of entities, including the Authority, and “Outline of Preliminary Agreement concerning joint participation in a treated water supply for portions of’ three particular counties. 10
The notice here is substantially more descriptive than the posting in
Hays County Water Planning Partnership v. Hays County,
In
City of San Antonio,
the court recognized that the notice at issue was “insufficient to inform the individual landowners that their particular tracts of land were the subject of the proposed condemnation ordinance.”
City of San Antonio,
Even if we were to conclude that the notice was inadequate, we question how FOCL would then be able to attack the TNRCC Amendment. As the Authority points out, FOCL seeks to invalidate the TNRCC Amendment by attacking the validity of the Application leading to the Amendment. FOCL alleges that the Application filed with the TNRCC by another agency was improperly approved pursuant to the other agency’s Open Meetings Act violation. But this reasoning conflicts with the well established principle that an agency’s final order, like the final judgment of a court of law, is immune from collateral attack.
See Alamo Express, Inc. v. Union City Transfer,
We have already determined that the TNRCC did not act beyond its statutory authority by issuing the Amendment. And FOCL has made no attempt to prove that the Amendment is in some manner fundamentally flawed. Rather, and as we understand its argument, FOCL claims to be making a
direct
attack on the Amendment, claiming the Authority’s violation of the Act in approving the Application at an improper meeting causes the TNRCC’s Amendment to be void. This contention overlooks the express language of the Act, which states that “an action taken by a governmental body in violation of this chapter is voidable.” Tex. Gov’t Code Ann. § 551.141 (West 1994). In the context of this case, we take this language to mean that, at best, FOCL could ask this Court to set aside the voidable action taken by the Authority at its August 20, 1997 meeting.
13
If we were to do that, however, the Amendment itself would still stand. The Act does not provide an exception to the rule against collateral attack on final agency orders.
See, e.g., Carr v. Bell Sav. & Loan Ass’n,
Discovery Requests
FOCL finally argues that the district court erred by denying its discovery requests with the TNRCC. According to FOCL, these discovery requests were relevant because they were directly linked to the claims dismissed by the district court for lack of subject-matter jurisdiction. We note that this complaint is not shown in the brief as an “issue presented” but instead is raised for the first time only in discussion at the end of the brief. Nor does the argument cite any authority. The brief on this point submitted by appellant is therefore not in accordance with Tex.R.App. P. 38.1(e), (h). Also, because we have affirmed the dismissal of those claims, we need not further address this issue; to the extent the matter is asserted, we overrule the complaint.
CONCLUSION
For the reasons set forth above, we overrule FOCL’s issues on appeal. We affirm the judgment of the district court.
Notes
. By statute effective September 1, 2001, the legislature changed the name of the Texas Natural Resource Conservation Commission to the Texas Commission on Environmental Quality, to be effective January 1, 2004. The statute granted the TNRCC authority to adopt a timetable for phasing in the change of the agency’s name, so that until January 1, 2004, the agency may perform any act authorized by law under either title.
See
Act of April 20, 2001, 77th Leg., R.S., ch. 965, § 18.01, 2001 Tex. Gen. Laws 1985. On September 1, 2002, the agency began using its new name, while continuing to recognize the former. Because
. According to the final judgment of the district court, the three original lawsuits were as follows: (i) Friends of Canyon Lake, Inc. v. The Texas Natural Resource Conservation Commission and its Executive Director Mr. Jeff Saitas and the Guadalupe-Bianco River Authority, Cause No. GN-102688 (originally filed in the 200th Judicial District Court, Travis County, Texas); (ii) Friends of Canyon Lake, Inc. v. The Texas Natural Resource Conservation Commission and its Executive Director Mr. Jeff Saitas and the Guadalupe-Blanco River Authority, Cause No. GN-103054 (originally filed in the 353rd Judicial District Court, Travis County, Texas); and (iii) Friends of Canyon Lake, Inc. v. The Texas Natural Resource Conservation Commission and its Executive Director Mr. Jeff Saitas, Cause No. GN-103689 (originally filed in the 126th Judicial District Court, Travis County, Texas).
. In its findings of fact and conclusions of law, the district court states that the deadline for filing a contested case hearing on the Application was thirty days after the August 15, 1999 publication of notice in the two newspapers. See 30 Tex. Admin. Code § 295.171 (2002) (Natural Resource Conservation Commission, Water Rights, Procedural). The district court also finds that this notice was sufficient, as evidenced by the fact that a timely request for a contested case hearing was filed by Guadalupe River Trout Unlimited ("Trout Unlimited”), among others. In regard to Trout Unlimited, the district court found that the Authority's Board meeting on July 17, 2001 to approve a settlement agreement with Trout Unlimited complied with the Open Meetings Act. That finding is not on appeal here.
. Although this appears as one of the district court’s conclusions of law, the judgment is limited to holding that FOCL "has failed to demonstrate any violation by [the Authority] of the Open Meetings Act....” In fact, following these words it is stated that FOCL’s "Open Meetings Act claims also are impermissible collateral attacks.” But this statement is marked out and initialed by Judge Cooper.
.In its brief on appeal, FOCL lists seven of its claims alleged in the petition in intervention. According to FOCL, the Amendment is juris-dictionally and procedurally defective because: (1) the requirements of Senate Bill 1 applied to the Authority’s Application and that, having failed to comply with these requirements, the TNRCC was without jurisdiction to consider the Application; (2) the requirements of the Coastal Management Act applied to the Application and that, having failed to comply with these requirements, the TNRCC was without jurisdiction to approve the Application; (3) the Authority failed to comply with the requirements of its own enabling act when it filed the Application; (4) the TNRCC was statutorily barred from considering the Application because the Authority never paid the full fees for the Application, or paid them late and therefore Senate Bill 1 should apply; (5) the TNRCC and the Authority failed to comply with the statutory and regulatory notice requirements that applied to the Application; (6) the Amendment was void because the Authority had "used” or had "begun to use” water under the permit prior to paying its final permit fees; and (7) the Application was issued in violation of TNRCC statutes and rules because the Application was amended after public notice had issued.
. In its brief, FOCL cites generally to the entirety of Senate Bill 1, but refers specifically to the amended requirements of an "inter-basin water transfer.” See Tex. Water Code Ann. § 11.085 (West 2000) [Amended by Act of Apr. 3, 1997, 75th Leg., ch. 1010, § 2.08, 1997 Tex. Gen. Laws 3621-23].
. In its brief, FOCL cites generally to chapter 33 of the Natural Resources Code, referring to it as the "Coastal Management Act.” Chapter 33 is in fact known as the Coastal Public Lands Management Act of 1973. See Tex. Nat. Res.Code Ann. § 33.003 (West 2001). Section 33.053 of the Natural Resources Code specifies the elements of the coastal management program in Texas, which is to be in compliance with the federal Coastal Zone Management Act of 1972. See id. § 33.053(a) (citing 16 U.S.C. Section 1451 et seq.).
. Even if FOCL could prove facts amounting to insufficient notice, jurisdiction would not thereby be automatically conferred on the district court. See,
e.g., Wilmer-Hutchins Indep. Sch. Dist. v. Sullivan,
. The questions of law, according to FOCL, are whether Senate Bill 1 and the Coastal Management Act apply to the Application.
. FOCL complains that the notice in no way reflects the final action taken at the meeting, which it alleges was to, among other things, "sell a portion of the water outside its ten county area....” We note that this claim is made despite the fact that the notice clearly lists Bexar County among the counties considered for the treated water supply.
.On appeal, FOCL complains about the notice for a board meeting held by the Authority on October 16, 1996. It contends that "the certificate of authority to file the application for amendment of permit filed by [the Authority’s] general manager on August 29, 1997 indicates he was given authority to file the application at the August 20, 1997 [Authority] Board meeting, not the October 16, 1996 Board meeting.” FOCL also contends that the language of the notice, "increase yield of Canyon Reservoir,” does not adequately satisfy the Act. However, as suggested by FOCL, the Application was filed pursuant to the 1997 Board meeting. Having concluded that the 1997 meeting satisfied the Act, we need not address the 1996 meeting.
. It is undisputed that the Amendment constitutes a final agency order.
. Section 551.142 of the Act states in part that an interested person “may bring an action by mandamus or injunction to stop, prevent, or reverse a violation or threatened violation of this chapter by members of a governmental body.” Tex. Gov’t Code Ann. § 551.142(a) (West 1994).
. In
Carr,
the appellant attacked the decision of one agency, the Appraisal Review Board, based on deficiencies in meeting notices sent by another agency, the Central Appraisal District. The court held that by the terms of the
Assuming that [Carr] could qualify as an "interested person” within the Open Meetings Act, he could attack an action of a governmental body for violations of the Act only directly, not collaterally. The Act provides that any action taken by such a body in violation of the Act is only voidable, not void.
Carr v. Bell Sav. & Loan Ass’n,