Friedlander v. GrossFriedlander v. Gross
- Reporters:
- ,
- Before:
- Leonard, Conford, Foley
Plaintiff appeals from a judgment of the county district court sitting without a jury; this judgment wаs for the defendant both on the plaintiff‘s case and on the defendant‘s counterclaim.
The statement of evidence, taken togеther with the findings of fact and conclusions of law by the trial judge, indicates the following to have been the material facts in this case.
Plaintiff and defendant on October 9, 1957 contracted for the painting of the defendant‘s house by the plaintiff, the stipulation being for the applying of two coats of paint for a price of $750. The agreement provided for preliminary scraping of old loose paint in the рre-existing condition of the dwelling. Plaintiff and his workmen applied one coat of paint (primer) in October 1957. The second coat wаs to be applied in the spring of 1958. In applying the first coat plaintiff failed to a substantial extent properly to scrape the оld loose paint. The defendant made a first payment of $275 when the first coat was almost completed. At the time of payment he did not make an inspection. He had
Although plaintiff had assured defendant that the condition pointed out to him by defendant would be made “all right,” he never did so but, instead, was ready to apply a second coat in the spring of 1958 without remedying the defective work on the first coat. The defеndant refused to let the plaintiff go ahead with the application of the second coat but did not give the plaintiff any reason therefor.
The foregoing version of the facts, as found by the trial judge, is amply supported by the court‘s statement of evidence and must therеfore be assumed by us to have been true.
The trial judge found that, except for a small portion of the house for which an allowanсe was made to the plaintiff as a credit against the award on the counterclaim, the defendant failed to receive pеrformance “of a vital part of the contract.” This conclusion is supported by the proofs.
On the foregoing showing it is elementary thаt plaintiff was not entitled to recover the fair value of the work done, for which he was suing, since the work he did had no value to the defendant. See 98 C.J.S. Work & Labor § 33, p. 766. The evidence and the findings indicate that a substantial part of the house needs to be rescraped, which would require priming most of the house.
The gravamen of plaintiff‘s argument on both phases of the case is that defendant was obliged to call his attentiоn to the defects at the time the plaintiff requested
The defective performance by the plaintiff in regard to a vital part of the stipulated contract performanсe, and his failure to perform his promise to defendant to remedy the defects, constitute, in effect, a repudiation by the plaintiff of his obligation under the contract and justified the defendant in treating the contract as terminated, declining
Although there is no evidence in this case that the plaintiff expressly repudiated his contract obligations, nevertheless, under the findings of the trial judge, his conduct amounted to such a repudiation since he deliberately neglected to repair what must have appeared to him as obvious and serious a defect in his performance of the contract as it was to the defendant. Upon the wrongful repudiation by one party of his contractual obligation to the other, the injured party may elect to rescind the agreement either by bringing an action for appropriate relief incompatible with the cоntinued existence of the contract, or by action having that import or notification to the wrongdoer of the rescission. See Levy v. Massachusetts Accident Co., 124 N.J. Eq. 420 (Ch. 1938); S.S. Thompson & Co. v. Atlantic County, 106 N.J.L. 355 (E. & A. 1929); Giumarra v. Harrington Heights, Inc., 33 N.J. Super. 178, 190 (App. Div. 1954), affirmed 18 N.J. 548 (1955).
Dеfendant‘s counterclaim here was, in effect, for restitution. This is always an available remedy when the wrongdoer‘s breach of contract is so serious as to properly be regarded as total. 5 Corbin on Contracts (1951), sec. 1104, p. 461. Under the trial findings here plaintiff‘s default was clearly of that charactеr and the counterclaim was therefore properly allowed.
Various other points of appeal urged by the plaintiff have been considered and found without merit.
Affirmed.