153 Minn. 450 | Minn. | 1922
Plaintiffs brought this action to recover a balance claimed to be due under a contract to construct section 1 of County Ditch No. 22 in Redwood county. This section comprised the open portion of the ditch and was 89,700 feet in length. The case was before this court on a prior appeal and is reported in 148 Minn. 181, 181 N. W. 324, 182 N. W. 514, where a statement of the facts will be found. The second trial resulted in a judgment for defendant and plaintiffs appealed.
At the second trial there was little, if any, dispute as to the material facts. The contract was made in March, 1917. Several miles of the upper part of the ditch was constructed that year and the remainder was constructed the following year. In the summer of 1918, heavy rains occurred which washed large quantities of earth and silt into the upper part of that portion of the ditch constructed in 1917. The court submitted the case to the jury on the theory that the failure of the plaintiffs to remove this earth and silt from the ditch before tendering it for acceptance precluded them from recovering, and plaintiffs’ exception to the charge to that effect raises the important question presented.
Where a contractor makes an absolute and unqualified contract to construct a building or perform a given undertaking, it is the general, and perhaps universal, rule that he assumes the risks attending the performance of the contract, and must repair and make good any injury or defect which occurs or develops before the completed work has been delivered to the other party. But where he makes a contract to perform a given undertaking in accordance with prescribed plans and specifications, this rule does not apply. Under such a contract he is not permitted to vary from the prescribed
The engineer appointed by defendant as provided by statute made the survey and report on which the ditch was established, and prepared the plans and specifications and supervised and directed the work of construction. By the contract plaintiffs agreed “to dig and construct section 1 of ditch No. 22 above described in the time and manner set forth in the report of said engineer, upon which said ditch is established and according to the plans, specifications and conditions therefor on file in the office of the county auditor of said county, which plans and specifications are hereby made a part hereof, and subject to the approval of said engineer and of said county auditor.”
As remarked in the former opinion there is no provision in either the contract or the specifications requiring the contractors to remove material which should wash into the ditch after it had been dug. Defendant cannot require plaintiffs to do more than they contracted to do. They contracted to construct the ditch according to the plans and specifications furnished by defendant. They did not contract to do anything more. If the walls of the ditch when constructed as required by the contract were too'steep or unstable to withstand the action of the elements, it was not the fault of plaintiffs. By constructing the ditch as prescribed in the plans and specifications they performed all that they contracted to do. The case of Gilbertson v. County of Blue Earth, 145 Minn. 236, 176 N. W. 762, is not in point, for the specifications in that case expressly provided that the contractors should remove all sediment and other material that accumulated in the ditch during the period of construction and leave the ditch free therefrom when completed.
The contract provided that plaintiffs should receive 11^ cents per • cubic yard for constructing the ditch if they completed work in the year 1917, and 9f cents per cubic yard if they failed to complete it in that year. It was held on the former appeal that the additional compensation to be paid if the work were completed in 1917 was in the nature of extra pay for an early completion of the work, and