134 P. 733 | Cal. Ct. App. | 1913
In prohibition. The facts presented by the affidavit and petition are these: Frey, the petitioner, as owner, contracted with one Campbell for the construction of a building. The same was completed and thereafter an action was begun to foreclose mechanics' liens, to which Frey, the contractor and lien claimants, other than the plaintiffs, were made parties. Among the lien claimants was a corporation known as The Universal Lumber Mill Company. This company, in addition to its answer, filed a cross-complaint seeking to establish its claim of lien for lumber and materials furnished and used in the construction of said building. The court proceeded to a trial of the issues, and found that the claim of lien of the mill company was invalid in that it was defective, not specifying to whom it had furnished the materials and did not truthfully contain a statement of the terms, time given, and conditions of its contract. The claim of lien stated that the amount of the contract price for such materials furnished was $3,739.38. This the court finds is untrue; that there was an express contract between the contractor and said mill company to furnish materials for $3,219.00 and an implied contract to payquantum meruit for the balance of the materials furnished, which the court finds to be the sum of $520.38. The court found that there was the sum $2,831 in the hands of defendant Frey, the owner, being the balance due on said original contract price, and that the plaintiffs and the other lien claimants, other than the mill company, were entitled to liens for the respective amounts claimed by them; that the mill company was entitled to a judgment against the contractor for $3,739.38, and that the balance of all moneys in the hands of the owner after payment of the liens found be applied to the judgment of said mill company, and that it recover judgment against the contractor for the balance of said account. Judgment was accordingly rendered in favor of plaintiffs and the other lien claimants for the aggregate amount due them, and the balance remaining in the hands of the owner after such payments, amounting to $1,716.83, was by the court directed to be paid by the owner to the mill company, and a judgment for the remainder of $1,022.55 was rendered in favor of the mill company and against the contractor. This judgment became final; no execution was ever issued out of the same. The owner paid all of the lien claimants, but made default in *423 the payment of the money which the court directed to be paid to the mill company. Afterward certain creditors of the contractor brought suits in attachment, and served notice of garnishment upon the owner for an amount in excess of the sum directed by the court to be paid the mill company. In these last-named actions, judgment was duly entered. Thereafter the court directed notice to be served upon Frey, the owner, to show cause why he should not be punished for contempt in refusing to pay the money by the court directed to be paid the mill company, and, upon hearing, it appearing that Frey assigned no reason why the order had been disobeyed, the court adjudged that he pay the sum within a fixed time, or, in default thereof, be committed to jail until such payment be made. In this proceeding it is sought to prohibit the superior court from further proceedings in the contempt case, upon the theory that the court had no jurisdiction or authority in the action to direct the payment by Frey of the balance of the funds in his hands, after payment of the liens established; that the effect of the judgment in favor of the mill company as against Campbell was that of a personal judgment, the only remedy being to enforce the same by execution, as in other cases.
Respondents invoke the long-established and recognized rule that the judgment of a court having jurisdiction of the subject-matter and the parties is, as to the thing adjudged, conclusive upon all the parties regardless of the question whether the thing was correctly adjudged or not, and cannot thereafter be reviewed except in the manner and within the time prescribed by law. This application, therefore, presents the question of the jurisdiction of the court to direct the payment of the balance of the fund in the hands of the owner to one who had not established a lien, and to punish as for contempt for the disobedience of such order. There can be no question under the decisions of the supreme court of this state, (Weldon v. Superior Court,
The writ is, therefore, denied.
James, J., and Shaw, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on August 30, 1913.