FREDERICK OLSON et al. v. TOWN OF YARMOUTH et al.
2018 ME 27, Docket: Cum-17-274
MAINE SUPREME JUDICIAL COURT
Argued: December 13, 2017, Decided: February 22, 2018
2018 ME 27
SAUFLEY, C.J., and ALEXANDER, MEAD, GORMAN, JABAR, HJELM, and HUMPHREY, JJ.
Reporter of Decisions
[¶1] Frederick Olson and Leora Rabin appeal from a judgment of the Superior Court (Cumberland County, Warren, J.) affirming, pursuant to
I. BACKGROUND
[¶2] In 2001, Sprint Spectrum L.P. (Sprint) submitted a site plan application to the Town of Yarmouth in which it applied to install a wireless communication antenna array on a water tower owned by the Yarmouth Water District and to install equipment cabinets on the ground near the tower. The Planning Board denied the application because it did not meet zoning and site plan ordinance standards. In April 2016, Verizon applied to the Planning Board for a similar use at the same site.
[¶3] At a public meeting on May 25, 2016, the Planning Board reviewed Verizon‘s plan. The Planning Board and neighboring residents, including Olson and Rabin, questioned the location of the equipment enclosure and the related visual, noise, and health effects on the neighborhood. Olson‘s property abuts the Yarmouth Water District site, and Rabin resides within 500 feet of the site. Verizon represented that it would examine other sites and look at the gaps in
[¶4] On July 20, 2016, Verizon submitted its final site plan application to install equipment on the Yarmouth Water District site. Verizon asserted in its application that, by installing the equipment on the Yarmouth Water District site, Verizon would “be able to fill the substantial coverage gap that it now experiences, and provide improved coverage and capacity to residents, businesses, and traffic corridors within sections of Yarmouth that are currently located within deficient service areas of Verizon Wireless‘[s] network.”
[¶5] The Town of Yarmouth Director of Planning and Development (Director) submitted a report to the Planning Board on September 23, 2016. The Director detailed how Verizon‘s application complied with individual site plan and zoning standards and concluded that the project conformed to the Town‘s comprehensive plan and submission requirements. As to the Ordinance‘s requirement that Verizon investigate other technically feasible sites, he concluded that Verizon had “described [its] site selection process,” and the Yarmouth Water District site allows “the antenna to be located on an existing water tower which avoids the need to construct a new tower.” The
[¶6] The Director‘s report included the 2001 letter denying Sprint‘s site plan application and the Planning Board‘s findings on Sprint‘s application. The 2001 Planning Board report stated that “[t]he size and configuration of the lot on which the water tower is located and upon which equipment is located is too small in area and too narrow in width and therefore too constrained for ‘adverse impacts’ of the proposed equipment installation on the ground to be adequately minimized, per [
[¶7] On September 28, 2016, the Planning Board considered Verizon‘s final site plan application at a public meeting. The Planning Board asked about alternative sites that Verizon had considered, and a Verizon representative explained that it looked at the gaps in its area of coverage and then looked for sites that could fill the gaps with a minimal impact on the Town. The Verizon
[¶8] On November 8, 2016, Olson and Rabin, who both appeared and commented at the Planning Board meetings, filed a complaint and petition for review of final municipal action pursuant to
[¶9] Olson and Rabin filed a timely appeal. See
II. DISCUSSION
[¶10] Olson and Rabin raise two issues on appeal. First, they argue that the Planning Board erred in its approval of Verizon‘s site plan application because, pursuant to
[¶11] “We review the Planning Board‘s approval of the [site plan application] directly for error of law, abuse of discretion or findings not supported by substantial evidence in the record.” Osprey Family Tr. v. Town of Owls Head, 2016 ME 89, ¶ 9, 141 A.3d 1114 (quotation marks omitted). “Substantial evidence exists when a reasonable mind would rely on that evidence as sufficient support for a conclusion.” Id. (quotation marks omitted). “Although interpretation of an ordinance is a question of law, we accord substantial deference to the Planning Board‘s characterizations and fact-findings as to what meets ordinance standards.” Bizier v. Town of Turner, 2011 ME 116, ¶ 8, 32 A.3d 1048 (quotation marks omitted). When interpreting
A. Application of the Presumption of Unsuitability
[¶12] We first consider Olson and Rabin‘s argument that, pursuant to
[¶13]
Once the Planning Board has determined that telecommunications equipment proposed by the applicant cannot be accommodated on an existing or approved tower or Alternative Tower Structure, each tower or Alternative Tower Structure so found is presumed unable to accommodate similar equipment that may be proposed in the future unless the Board determines, after
additional information is provided, that new technology or other considerations enables the existing or approved tower or Alternative Tower Structure to accommodate the equipment.
[¶14] Olson and Rabin argue that
[¶15] The question to be answered is whether the presumption of unsuitability attaches to a co-location site only when an applicant initially proposes to construct a new tower, or whether it also attaches when the applicant‘s initial proposal is to co-locate by installing equipment on that site. If the latter, a rebuttable presumption of unsuitability attached to the Yarmouth Water District site after the Planning Board denied Sprint‘s application in 2001.
[¶16] As is the case with statutes, our single goal in interpreting an ordinance is to give effect to the Town‘s intent in enacting the ordinance. See Dickau v. Vt. Mut. Ins. Co., 2014 ME 158, ¶ 19, 107 A.3d 621. We first determine if the language of the ordinance is plain and unambiguous. See id. Our
[¶17] At the outset, article II(Z) announces that one of the purposes of the Ordinance is to encourage co-location and “[p]ermit the construction of new towers only where all other reasonable opportunities have been exhausted.” See
[¶18] No language in
[¶19] The Planning Board did not err in declining to require Verizon to rebut a presumption of unsuitability.
B. Investigation of Other Technically Feasible Sites
[¶20] Olson and Rabin next assert that we should vacate the Planning Board‘s decision or remand for further fact-finding because the Board did not receive substantial evidence that Verizon investigated other “technically feasible sites,” as required by
[¶21] The Board did not make specific findings on Verizon‘s compliance with particular aspects of the zoning and site plan ordinances and made only the following finding: “On the basis of the application, plans, reports and other information submitted by the applicant, information from the public hearing, information and the findings and recommendations contained in [the] Planning
[¶22] Planning Board findings must be supported by substantial evidence in the record. See Osprey Family Tr., 2016 ME 89, ¶ 9, 141 A.3d 1114. The Planning Board had substantial evidence that Verizon had investigated other technically feasible sites and concluded that none was available. Although Verizon‘s written submissions to the Planning Board did not contain information about alternative sites that it had considered, Verizon‘s application included detailed information about its site selection process, and, during the May and September meetings, the Planning Board asked the Verizon representative about alternative sites that Verizon had considered. At the September 28 Planning Board meeting, a Verizon representative explained that its site selection process consisted of looking for gaps in coverage and identifying sites that would fill those gaps and have a minimal effect on the Town. Verizon‘s representative reported that the only feasible site for co-location was the Yarmouth Water District site because other sites were not tall enough or would not fill the coverage gap. The Director‘s report to the Planning Board referred to the requirement of
[¶23] Because the Planning Board‘s finding was supported by substantial evidence, we will not disturb the Board‘s conclusion that the application met ordinance standards. See Bizier, 2011 ME 116, ¶¶ 8, 12, 32 A.3d 1048 (“[W]e accord substantial deference to the Planning Board‘s characterizations and fact-findings as to what meets ordinance standards.“) (quotation marks omitted)).
The entry is:
Judgment affirmed.
Nathaniel A. Bessey, Esq. (orally), Brann & Isaacson, Lewiston, for appellants Frederick Olson and Leora Rabin
Philip R. Saucier, Esq. (orally), Bernstein Shur, Portland, for appellee Town of Yarmouth
Scott D. Anderson, Esq. (orally), Verrill Dana, LLP, Portland, for appellee Verizon Wireless
Cumberland County Superior Court docket number AP-2016-48
FOR CLERK REFERENCE ONLY
Notes
- Co-location requirements
- On existing towers:
- Applicants for site plan review for a new wireless communication tower must send written notice by pre-paid first class United States mail to all other such tower and Alternative Tower Structure owners and licensed wireless communication providers in the Town utilizing exi[s]ting towers and Alternative Tower Structures and to owners of such towers and Alternative Tower Structures within a 1 mile search radius of the proposed tower, stating their siting needs and/or colocation capabilities. Evidence that this notice requirement has been fulfilled shall be submitted to the Planning Board and shall include a name and address list, copy of the notice which was sent, and a statement, under oath, that the notices were sent as required. An application for a new tower must include evidence that existing or previously approved towers and Alternative Tower Structures within the Town and search area cannot accommodate the communications equipment (antennas, cables, etc.) planned for the proposed tower. Such evidence would be documentation from a qualified and licensed professional engineer that:
- Planned necessary equipment would exceed the structural capacity of existing and approved towers and Alternative Tower Structures, considering the existing and planned use of those towers and Alternative Tower Structures, and the existing and approved towers cannot be reinforced to accommodate planned or equivalent equipment at a reasonable cost;
- Planned equipment will cause electromagnetic frequency interference with other existing or planned equipment for that tower or Alternative Tower Structure, and the interference cannot be prevented at a reasonable cost;
- Existing or approved towers and Alternative Tower Structures do not have space on which planned equipment can be placed so it can function effectively and at least in parity with other similar equipment in place or approved; or
- Other documented reasons that make it technically or financially unfeasible to place the equipment planned by the applicant on existing and approved towers and Alternative Tower Structures.
- Shared use shall be conditioned on the applicant‘s agreement to pay a reasonable fee and costs of adapting existing facilities to the proposed use.
- Once the Planning Board has determined that telecommunications equipment proposed by the applicant cannot be accommodated on an existing or approved tower or Alternative Tower Structure, each tower or Alternative Tower Structure so found is presumed unable to accommodate similar equipment that may be proposed in the future unless the Board determines, after additional information is provided, that new technology or other considerations enables the existing or approved tower or Alternative Tower Structure to accommodate the equipment.
- The Planning Department will maintain a list of existing and approved towers and Alternative Tower Structures, including name and address of owner(s), within the Town of Yarmouth.
- Applicants for site plan review for a new wireless communication tower must send written notice by pre-paid first class United States mail to all other such tower and Alternative Tower Structure owners and licensed wireless communication providers in the Town utilizing exi[s]ting towers and Alternative Tower Structures and to owners of such towers and Alternative Tower Structures within a 1 mile search radius of the proposed tower, stating their siting needs and/or colocation capabilities. Evidence that this notice requirement has been fulfilled shall be submitted to the Planning Board and shall include a name and address list, copy of the notice which was sent, and a statement, under oath, that the notices were sent as required. An application for a new tower must include evidence that existing or previously approved towers and Alternative Tower Structures within the Town and search area cannot accommodate the communications equipment (antennas, cables, etc.) planned for the proposed tower. Such evidence would be documentation from a qualified and licensed professional engineer that:
- Construction of new towers
A proposal to construct a new co-located communication tower taller than the maximum height permitted for a single wireless communication service must include evidence that the tower can structurally support a minimum of three (3) antenna arrays for each anticipated co-locating entity. (See Section II.Z.3.a Tower Height, above.)
Prior to the issuance of any Building permits for a co-located tower in excess of the height of a single user tower, the applicant will submit to the Code Enforcement Officer executed agreements documenting commitments to co-locate from the number of co-locators approved by the Planning Board.
- On existing towers:
