The defendant is a real estate developer who at all material times was engaged in the renovation of an elderly seaside mansion in Dartmouth and its conversion into individual apartments which would be sold to the public as condominium
At some point following the award of the heating subcontract to Denron but prior to the flooding, the principal of Denron, one Rowan, requested the principal of the plaintiff, one Fraser, to formulate and submit to Denron a proposal for the post-construction maintenance of the equipment which was to be installed by Denron. Fraser submitted such a proposal, but it was not accepted. After the flooding Rowan asked Fraser to examine the damage, to make recommendations as to what would be required to repair the damage, and to submit a proposal for whatever work and equipment might be required. Fraser revisited the site and examined the damage in the presence of Rowan, a representative of the mechanical engineer employed by the architect, and one Bettencourt, who was the defendant’s project manager and who had been directed by him to oversee the repair or replacement of all the damaged material and equipment. Fraser inquired as to who would be the other contracting party and as to who would be responsible for paying the plaintiff if its proposal were to be accepted. Rowan, in the presence of Bettencourt, responded that the plaintiff would be paid from the proceeds of the defendant’s claim under his builder’s risk insurance but that the actual
The plaintiff’s proposal was accepted, and it entered into a written agreement with Denron for the reconditioning of two existing boilers, the installation of two new oil burners, and the installation of various electronic controls. 3 This was the first time the plaintiff had entered into a contractual relationship with Denron. The plaintiff performed the agreement in workmanlike fashion and demanded payment from Denron, which put the plaintiff off on the ground that it (Denron) had not received payment from Homar. That was not a legitimate excuse because the plaintiff’s right to receive payment from Denron was not conditioned on the latter’s first receiving payment from Homar.
The plaintiff then demanded payment from the defendant. Unbeknownst to the plaintiff, the defendant had decided not to seek recovery of its losses from his builder’s risk insurer but to pursue Piva’s liability insurer instead.
4
Following the completion of the plaintiff’s work the defendant received from
The plaintiff brought suit against Denron and the defendant in the Superior Court. The first count of the amended complaint alleged a breach of the agreement between the plaintiff and Denron arising out of the latter’s failure to pay the plaintiff the agreed price for its work and equipment. The second count was directed to the defendant and proceeded on a theory that the defendant had been unjustly enriched at the expense of the plaintiff to the extent of the fair value of the labor, material and equipment supplied by the plaintiff. The plaintiff obtained a summary judgment against Denron for the full amount of its claim, which Denron paid. The plaintiff then went forward on the count against the defendant to recover from him the reason
Neither the provisions of G. L. c. 93A, §
2(a),
nor those of G. L. c. 93A, § 11, contain a definition of an unfair act or practice. Both leave the possible existence of such to be determined on a case-by-case basis. See
Commonwealth
v.
DeCotis,
Nor do we find error in the judge’s conclusion that the defendant, in giving and failing to carry through on his assurance, committed a deceptive act within the meaning of G. L. c. 93A, §§
2(a)
and 11. As the judge noted, an act or practice can be deceptive within the meaning of either of those sections if it “[can] reasonably be found to have caused a person to act differently from the way he otherwise would have' acted.”
Lowell Gas Co.
v.
Attorney Gen.,
We have dealt with all the questions raised below which have been argued here. No other question requires separate discussion.
The judgment is to be modified so as to include therein awards of counsel fees and expenses to the plaintiff in connection with this appeal in such reasonable amounts as may be determined by the Superior Court and, as so modified, is affirmed. 7
So ordered.
Notes
The defendant has abandoned his belated objections to Fraser’s testimony on these subjects, and the case has been argued to us on the footing that the defendant is responsible for whatever consequences may flow from Bettencourt’s silence. See generally
Ruszcyk
v.
Secretary of Pub. Safety,
The agreement between the plaintiff and Denron did not take the form of a subsubcontract of a portion of the work which Homar owed the defendant under the original general contract and which it had subcontracted to Denron, undoubtedly because the agreement between the plaintiff and Denron called for repair and other work not contemplated by the general contract. The agreements between the plaintiff and Denron and between Denron and Homar were both executed on a form recommended by the American Institute of Architects for use in agreements between general contractors and their subcontractors.
There was a $10,000 deductible in the builder’s risk policy which could be avoided if full recovery could be had from Piva’s insurer. The decision to pursue Piva’s insurer was a matter of business judgment which is not questioned by the plaintiff. Correspondingly, the defendant does not seek to avoid responsibility on the ground that he received nothing from his builder’s risk insurer.
The total amount of the claim submitted to Piva’s insurer reflected not only the amount of the plaintiff’s claim, but also claims for flooding damage to the work which had been performed by subcontractors other than Denron.
We need not and do not pass on the validity of any of the supposed defences.
See Patry
v.
Liberty Mobilehome Sales, Inc.,
