28 S.W. 714 | Tex. App. | 1894
The appellee, plaintiff below, claimed in its petition that appellant violated its contract in failing to deliver certain machinery which it had purchased from appellant, defendant below, for the purpose of erecting a smelter, in consequence of which it was delayed two months in the construction of such plant; and that it lost the profits it might have made by operating the smelter during the time, and the wages of certain of its employes. That the profits *212 lost were $10,000, and the hire of its employes amounted in the aggregate to $1652, all of which was prayed for as damages.
The petition was excepted to, and the execution of the contract as well as the alleged damages denied by the appellant.
As the result of the trial, judgment was rendered upon a verdict in appellee's favor for $2,722.83 1/3. This appeal is from the judgment.
If the execution of the contract could be made an issue by pleadings not sworn to by defendant, as was sought to be done in this case, such issue was fully and fairly submitted to the jury, upon the evidence, by the charge of the court. And as the finding of the jury upon it in appellee's favor is supported by the evidence, the assignments of error going to matters relating to the execution of the contract require no further consideration.
It is claimed by appellant, that the loss of profits claimed by appellee is too uncertain, remote, and speculative to be recovered as damages. This contention is raised by assignments of error complaining of the rulings of the court upon exceptions to the petition, of its admission of testimony over appellant's objections, of its charge to the jury, and of the sufficiency of the evidence to support the verdict. These assignments will all be considered together.
It is aptly said by the Supreme Court of Oregon: "The difficulty in the determination of the question thus presented lies not so much in the ascertainment of the law of the subject as in its application to the facts of the particular case. The broad general rule in such cases is, that the plaintiff may recover such damages, including gains prevented, as well as losses sustained, as may reasonably be supposed to have been within the contemplation of both parties at the time of making the contract, as the proximate and natural consequence of a breach by defendant; and in determining what may reasonably be supposed to have been within the contemplation of the parties as a natural consequence of a breach, all the facts surrounding the execution of the contract known to both parties may be considered, even if these be such as would not necessarily enter into it, if known to the defendant. It is on this principle that an injured party is allowed to charge the loss on collateral contracts on proving notice, which in the absence of such notice, would not be considered within the contemplation of the parties." Blagen v. Thompson, 31 Pac. Rep., 647, citing 1 Suth. on Dam., 79; 1 Sedg. on Dam., sec. 149; Hadley v. Baxendale, 9 Exch., 341; Griffon v. Colver,
As said by the Supreme Court of Maryland, in Lanahan v. Heaver, 29 Atlantic Reporter, 1038: "The profits claimed must be free from speculation, and must be sufficiently certain to be capable of adequate proof. They must not depend on the chances of trade, but upon the market value and other facts which are susceptible of definite proof (Griffin v. Colver, 16 New York, 494; Masterson v. Brooklyn, 7 Hill, *213
61); and the plaintiff must establish the quantum of his loss by evidence from which the jury will be able to estimate the extent of his injury, excluding all such elements of injury as are incapable of being ascertained to a reasonable degree of certainty by the usual rules of evidence. Wolcott v. Mount, 36 N.J. Law, 271. To furnish ground of recovery as damages, profits must be proved. United States v. Behan,
The principles thus enunciated are followed by our courts (Jones v. George,
The appellee's employes, the loss of whose hire and wages are sued for, were not employed until after the contract was made, and such loss, if any, could not have been contemplated by the parties when the contract was made, and the trial court properly withheld such issue from the jury in its charge.
On account of the errors indicated, the judgment of the District Court is reversed and the cause remanded.
Reversed and remanded.