OPINION OF THE COURT
We are asked to decide, among other things, if a seaman’s failure to disclose a prior injury on a job application causes the seaman to forfeit his entitlement to maintenance and cure. We hold that, under the circumstances presented here, no such forfeiture has occurred and we will thus affirm the district court’s judgment.
I. FACTUAL BACKGROUND
McCormack Aggregates, Co. operates various dredging vessels in connection with its business of mining sand from the bottom of the sea. Francis Deisler is a seaman who is a member of International Union of Operating Engineers, Local 25-Marine Division. That union periodically refers workers to employers who operate dredging vessels and equipment. In 1982, Deisler injured his back while he was working on a dredge and he was disabled for about six months. Thereafter, he returned to jobs involving heavy physical labor including construction work, dockbuilding and dredging.
On August 3, 1988, while Deisler was working as a dredgeman for another boating company, his union referred him to McCor-mack where he filled out an application for a position as a boatman. That application included the following question: “Do you have any physical limitations which would hinder your performance in the position applied for?” Deisler did not answer the question. 1 *1078 On June 12, 1989, some 10$ months after he filled out the application, Deisler’s union told him to report for work with McCormack on June 13. 2 Deisler’s application apparently was never reviewed. The sections on the bottom portion of the application labelled “Reviewed By” and “Approved By,” which were for “office use only,” were left blank.
Deisler was injured almost immediately after he began working for McCormack. The district court described the incident which caused his injury as follows:
On June 15, 1989, ... plaintiff suffered an injury while moving a wheelbarrow loaded with supplies along a path on McCor-mack’s property. This job had been assigned to him by his supervisors, Messrs. Ellis and Melendez, who were, respectively, the tugboat’s Captain, and the dredge’s Dragtender.... The accident occurred when he [Deisler] rolled the wheelbarrow off the vessel side of the ramp, and the wheelbarrow’s wheel went onto the sandy path. The wheelbarrow became unstable, stopped short, and fell onto its side, spilling its contents. Plaintiffs forward momentum caused him to tumble and fall over the stopped wheelbarrow. Immediately after his fall he felt a sharp pain in his back.
April 26, 1994, Findings of Fact, ¶ 5.
The district court found that Melendez and Ellis saw this incident. 3 Both were in the dredge’s dragtender’s cabin which was a raised work platform which overlooked the location where Deisler fell. Melendez testified that Ellis ducked down when Deisler fell so that Deisler would not know that Ellis had witnessed the accident, and that Ellis told him (Melendez) that he had seen Deisler fall.
The following morning Ellis asked Deisler to move some heavy cables, but Deisler complained that his back was hurting. Deisler then left the vessel, went to the company’s offices, and began filling out an accident report of his fall and the resulting back injury. Deisler then went to the office next door where he was given a dismissal notice which stated that he was being fired for unsatisfactory work performance.
Before Deisler left McCormack’s offices, he took a New Jersey Disability Benefits claim form that he sent to his physician. Deisler’s physician completed that form and returned it to McCormack after June 27, 1989. Thereafter, Deisler made a claim for maintenance and cure, and McCormack hired the maritime investigative firm of Lamorte and Burns, Inc. to investigate that claim. Lamorte was succeeded by American Maritime Consultants. 4 Following the investigation of Deisler’s claim, both Lamorte and American Maritime recommended that McCormack pay Deisler the requested maintenance and cure, but McCormack refused and Deisler filed suit against McCormack and its dredge under the Jones Act, 5 and under the general maritime law.
Those two causes of action were tried simultaneously with the jury sitting as the finder of fact on the Jones Act claim and the court sitting as finder of fact on the general maritime claim. The jury found the defendants were not negligent and returned a verdict in their favor under the Jones Act. However, the district court granted plaintiffs motion for a new trial on the Jones Act claim *1079 but plaintiff elected to discontinue that cause of action in favor of his claim for maintenance and cure, and also for c.ompensatory damages, under the general maritime law. The court ruled that plaintiff was entitled to maintenance and cure under general maritime law, and also awarded plaintiff compensatory damages based upon defendants’ arbitrary and capricious denial of plaintiffs claim. The defendants 6 appeal from this judgment of the district court.
II. DISCUSSION
The district court had subject matter jurisdiction over this admiralty action under 28 U.S.C. § 1333. We have appellate jurisdiction over the final judgment of the district court pursuant to 28 U.S.C. § 1291. We review the district court’s findings of fact under a clearly erroneous standard.
See Sheet Metal Workers Local 19 v. 2300 Group, Inc.,
A. Maintenance and Cure
The gravamen of McCormack’s argument is that Deisler forfeited his right to maintenance and cure when he failed to disclose his prior back injury as requested on the employment application.
Maintenance and cure are rights given to seamen who become ill or injured in the service of a vessel.
7
“Maintenance is the living allowance for a seaman while he is ashore recovering from injury or illness.
See Vaughan v. Atkinson,
The origins of the duty to provide maintenance and cure have been traced to Justice Story in
Harden v. Gordon,
Viewing seamen as wards of admiralty, the Court has emphasized that the right to maintenance and cure must be construed liberally and has consistently expanded the scope of the right. Thus, today a shipowner is obliged to pay maintenance and cure regardless of any fault on its part; only wilful misconduct on the part of the seaman will deprive him of its protection.
Id. (citations omitted). Although conditions have clearly changed since this concept was first introduced into law, the right of recovery for maintenance and cure has continued to be a fundamental component of the relationship between employees and employers at admiralty.
“[T]he seaman’s right was firmly established in the maritime law long before recognition of the distinction between tort and contract.”
[It is argued that] the rationale underlying the right of maintenance, which is predicated on the special status of seamen as “wards of the admiralty,” is no longer valid. It is true that almost every case concerning the right to maintenance relies on Justice Story’s description of the seaman as “generally poor and friendless, and acquiring] habits of gross indulgence, carelessness, and improvidence.”
[It is also argued that] today those seamen who are unionized are neither friendless nor improvident.... Furthermore, the adjectives “friendless” and “helpless” were generally used to describe sailors in foreign ports
The changed circumstances of the unionized seaman may undercut the rationale supporting the traditional right to maintenance and cure, at least for unionized seamen. However, the Supreme Court has shown no. inclination to depart from its long established solicitude for seamen. Until it does so, we see no basis to assume that the emergence of powerful seamen’s unions, ... justifies our ignoring the Court’s clear and frequent pronouncements that seamen remain wards of the admiralty.
Id. at 636-37 (citations omitted).
A shipowner’s responsibility for maintenance and cure “extends beyond injuries sustained on board ship or during working hours to any injuries incurred in any place while the seaman is subject to the call of duty.”
Id.
at 633;
see also Aguilar v. Standard Oil Co.,
1. Deisler’s Failure to Disclose His Prior Injury
McCormack contends that Deisler’s failure to disclose his prior back injury is the kind of misbehavior which relieves it of the duty it would otherwise have to provide maintenance and cure. However, nondisclosure of a pre-existing injury, without more, will not result in a seaman’s loss of maintenance and cure. Such a forfeiture will not occur unless Deisler
intentionally
misrepresented or concealed medical facts that were
material
to the decision to hire Deisler. In addition, there must be a nexus between the improperly concealed material information and the disputed injury.
See McCorpen v. Central Gulf Steamship Corp.,
The district court concluded that Deisler should have disclosed his prior injury in response to the inquiry on the employment application. The court ruled that McCor-mack’s inquiry into prior injuries created an inference that the information was material to McCormack. The court went on to conclude, however, that this “inference” of materiality was destroyed by the fact that McCor-mack’s decision to deny maintenance and cure was not predicated on the concealment but rather on McCormack’s contention that an accident never happened. Suppl.App. at 107-08. In Deisler’s view, the district court found that the concealment was not material to McCormack’s decision to -hire Deisler. But that clearly is not what the district court found. We thus view Deisler’s materiality argument as an alternative argument for affirming the judgment.
Cf. Mark v. Borough of Hatboro,
Assuming arguendo that the question on McCormack’s application created a duty to disclose, 12 the record is absolutely clear that Deisler’s omission was not material to McCormack’s hiring decision. Deisler was never questioned about his failure to answer although McCormack had eleven months to review his job application before he was told to report for work. This is evidenced by the fact that the sections on the bottom portion of the application labelled “Reviewed By” and “Approved By” were left blank. One of the investigators working for Lamorte stated:
I met with McCormack Aggregates, Mr. Brad Simek, to discuss the hiring of Mr. Deisler and specifically to find out if there was a policy or practice of questioning prospective employees about medical conditions, or if anyone could testify as to any conversations with Deisler that the back condition predated his employment with McCormack. Unfortunately, McCormack is unable to provide me with any such supporting testimony.
Suppl.App. at 182.
McCormack argues that its failure to investigate Deisler’s omission is irrelevant. Reply Brief of Appellant at 4. However, McCormack had the burden of proving that the omission was material .to its decision to hire Deisler,
see Wactor,
B. Wages, Compensatory Damages, Prejudgment Interest, Attorney’s Fees and Costs
McCormack argues that even if Deisler can recover maintenance and cure, the district court erred in awarding lost wages, damages for pain and suffering, prejudgment interest, costs, and attorney’s fees, as those are not an incident of the seaman’s contract of employment. 14 McCormack asserts that these damages are an incident of negligence under the Jones Act and that since Deisler elected to dismiss his Jones Act claim after the trial, the nature of the two causes of action, and the law of the case precludes recovery for these damages under general maritime law. See Brief of Appellant at 13.
In
Cortes v. Baltimore Insular Line, Inc.,
By the general maritime law, a seaman is without a remedy against the ship or her owners for injuries to his person, suffered in the line of service, with two exceptions only_ A remedy is his also if the injury has been suffered through breach of the duty to provide him with “maintenance and cure.” The duty to make such provision is imposed by the law itself as one annexed to the employment. The Osceola, supra. Contractual it is in the sense that it has its source in a relation which is contractual in origin, but, given the relation, no agreement is competent to abrogate the incident. If the failure to give maintenance or cure has caused or aggravated an illness, the seaman has his right of action for injury thus done to him; the recovery in such circumstances including not only necessary expenses, but also compensation for the hurt. The Iroquois,194 U.S. 240 [24 S.Ct. 640 ,48 L.Ed. 955 (1904)]....
The question then is to what extent the ancient rule has been changed by modern statute ... commonly known as the Jones Act.... We are to determine whether death resulting from the negligent omission to furnish care or cure is death from personal injury within the meaning of the statute.
We think the origin of the duty is consistent with a remedy in tort, since the wrong, if a violation of a contract, is also something more. The duty, as already pointed out, is one annexed by the law to a relation and annexed as an inseparable incident without heed to any expression of the will of the contracting parties. For breach of a duty thus imposed, the remedy upon the contract does not exclude an alternative remedy built upon the tort.
Id.
at 370-72,
In Sims, the district court disallowed a claim for additional damages in an action for maintenance and cure that a seaman brought under the Suits in Admiralty Act, 46 U.S.C.A.App. § 741 et seq. 15 In reversing we stated:
The new question in this ease is whether the respondent is liable for the consequential damages 16 occasioned by the failure to provide for maintenance and cure after termination of the voyage when it was demanded....
We may regal’d it as settled law that if a man is injured or becomes ill while on a voyage, neglect to fulfill the duty to provide maintenance and cure may impose damages beyond mere cost of food and medicines. The Iroquois,194 U.S. 240 ,24 S.Ct. 640 ,48 L.Ed. 955 ... , 17
This Court has held that it is not enough to give a sick man a hospital ticket. If he is ill and penniless transportation to the Place of treatment must be provided....
Sims,
This obligation for maintenance and cure is ... “imposed by the law itself as one annexed to the employment.... The duty ... is one annexed by law to a relation, and annexed as an inseparable incident without heed to any expression of the will of the contracting parties.” Cortes v. Baltimore Insular Line,287 U.S. 367 , 371-72 [53 S.Ct. 173 , 174,77 L.Ed. 368 ] (1932). It is no more a contract than the obligation of a husband to support his wife is one of contract. Each arises out of a relationship voluntarily entered into. But these duties *1084 are imposed by the law as an incident to the relationship, not a matter of con-tract_ [Therefore, ... the usual rules of damages for breach of contract to pay money are [not] applicable, (emphasis added). 18
Id.
at 974. Although the court’s analogy to the marital relationship cannot withstand the social evolution that has occurred since the court spoke, the court’s pronouncement of the permissible recovery for failure to promptly provide maintenance and cure remains valid.
See also Neville v. American Barge Line Co.,
In
Vaughan,
plaintiff seaman had worked as a taxi driver after becoming ill while in defendant’s employ. The employer refused to pay maintenance and cure because it doubted that plaintiff had really been ill. “Ultimately [the employee] was required to hire an attorney and sue in the courts to recover maintenance and cure, agreeing to pay the lawyer a 50% contingent fee.”
Vaughan,
The Supreme Court disagreed on both points. The Court reasoned that “[w]hile failure to give maintenance and cure may give rise to a claim for damages for the suffering and for the physical handicap which follows
(The Iroquois,
It would be a sorry day for seamen if shipowners, knowing of the claim for maintenance and cure, could disregard it, force the disabled seaman to work, and then evade part or all of their legal obligation by having it reduced by the amount of the sick man’s earnings.... This result is at war with the liberal attitude that heretofore has obtained and with admiralty’s tender regard for seamen.
Id.
at 533,
We therefore disagree with McCormack’s assertion that the additional damages that Deisler seeks are limited to the Jones Act. Brief of Appellant at 13-14. We believe that the district court properly awarded Deisler lost wages, damages for pain and suffering, and prejudgment interest arising from McCormack’s failure to pay him maintenance and cure.
McCormack further asserts that even where such additional damages and expenses are awarded on a maintenance and cure claim, they are allowed only where there is a willful and wrongful refusal to pay maintenance and cure and that the record here does not support the district court’s conclusion that McCormack’s refusal to pay maintenance and cure was arbitrary or capricious. As noted above, in
Sims
we held that consequential damages are allowed in a claim for maintenance and cure in order to make the injured seaman whole, and they are not dependent upon a showing of bad faith.
See Sims,
One man hurts another in an accident. The actor fails to provide medical care or alleviate the harm suffered by the victim honestly thinking that he was not (1) himself negligent or (2) the victim was contrib-utorily negligent. If the trier of fact disagrees with the actor on these conclusions, defendant is liable for full damages suffered, although some of them could have been mitigated by prompt action on his part.
Id. at 974-75.
In
Morales v. Garijak,
From the outset, the only reason offered for McCormack’s failure to pay maintenance and cure was the assertion that no accident had occurred. During the trial, the district court questioned Bernard Lillis, McCor-mack’s Chief Financial Officer, about McCor-mack’s reason for denying Deisler’s claim:
Lillis: If one person had come along and said that they saw Mr. Deisler fall over the wheelbarrow I would have changed my decision.
The Court: Mr. Lillis has made it very clear that the reason maintenance and cure was denied was because he didn’t think the accident ever happened. Isn’t that right, Mr. Lillis?
Mr. Lillis: That’s right, your honor.
The Court: Let me pursue this. Is it your position that the only reason that maintenance and cure was denied was because your company felt that an accident never happened?
Mr. Lillis: That is true, your honor.
The Court: An accident of Mr. Deisler falling over a wheelbarrow on June 15, 1989?
Mr. Lillis:' That’s correct.
The Court: That is it?
*1086 Mr. Lillis: That is it.
(emphasis added). Findings of Fact, ¶ 49 n. 5, SuppLApp. at 45-46.
However, McCormack never interviewed Deisler, and although Melendez denied seeing Deisler fall he told Lamorte’s investigator that he saw Deisler “dusting himself off’ after the wheelbarrow incident. Suppl.App. at 169. In addition, Ellis told Lamorte’s investigator that he saw “the wheel barrow lying on its side, the bags on the ground, and Deisler standing there kicking his feet.” Id. Rather than accept that testimony as corroboration that Deisler had been injured, McCormack tenaciously used it to support the rather dubious position that no accident could have occurred because no one saw it. Finally, McCormack disregarded their own investigators’ recommendations that they pay Deisler maintenance and cure. Although McCormack was under no obligation to accept the recommendations of Lamorte or American Maritime, the district court did not have to ignore McCormack’s rejection of its own expert’s recommendation.
Similarly, the district court properly noted that McCormack’s reason for denying Deis-ler’s claim shifted from pillar to post as the case progressed.
Defendant’s primary defense to the maintenance and cure claim was that plaintiff lied about an accident occurring. Second, defendant contended that no injury occurred even if the incident did. Third, defendant contended that if plaintiff was suffering from any condition, which it denied, it pre-existed the date of the incident. Next, defendant contended that even if an injury occurred, it was fully resolved, and no further medical care was necessary. Thus, the presentation of plaintiff and Steve Melendez as liability witnesses was necessary. Plaintiff was required to move for a new Jones Act trial because of defendant’s misrepresentations of material facts.
Findings of Fact, ¶ 59. That assessment is supported by the record.
It is now for McCormack, not Deisler, to bear the extra cost occasioned by McCormack’s intransigence. This includes the wages Deisler would have been earning had McCormack met its obligation to finance the corrective back surgery, and damages for the pain and suffering he has endured while awaiting that surgery. See Cortes, supra.
1. The Law of the Case
Nor does the law of the case preclude Deisler from recovering consequential damages under general maritime law despite the jury’s Jones Act verdict in favor of defendants. “The doctrine of the law of the case dictates that “when a court decides upon a rule of law, that rule should continue to govern the same issues in subsequent stages in the litigation.’”
In re Resyn Corp.,
McCormack argues that since Deisler elected to dismiss the Jones Act claim after trial the law of the case precludes recovery of consequential damages under general maritime law. That argument rests upon the mistaken belief that such lost wages and damages for pain and suffering are incidents of negligence under the Jones Act and not *1087 recoverable under the general maritime law. As we explained above, such damages may be recovered for the failure to provide maintenance and cure in the absence of a Jones Act claim. Thus, the law of the case is not a bar to plaintiff’s recovery.
2. Prejudgment Interest
The award of prejudgment interest was also proper. Unlike attorney’s fees and litigation expenses (which were not regarded as part of the merits of judgment at common law) prejudgment interest has traditionally been considered part of the compensation due to a plaintiff.
See Osterneck v. Ernst & Whinney,
3. Attorney’s Fees and Costs
Attorney’s fees and costs differ from interest, lost wages and damages for pain and suffering because attorney’s fees and costs cannot be recovered unless plaintiff can first establish defendant’s bad faith or recalcitrance.
Recognizing the importance of a seaman’s right to be made whole through the recovery of maintenance and cure, the federal courts have fashioned a supplemental remedy for instances in which a ship operator’s unjustified refusal to own up to its responsibilities to furnish maintenance and cure forces a seaman to incur the expense of a lawsuit to collect that which is due. When a ship operator fails to make a prompt, good faith investigation of a seaman’s claim for maintenance and cure or otherwise takes a “callous” or “recalcitrant” view of its obligations, the seaman may recover legal expenses on top of maintenance and cure. See Vaughan,369 U.S. at 530-531 [82 S.Ct. at 999-1000 ]....
Rodriguez Alvarez v. Bahama Cruise Line, Inc.,
However, as stated above, the record here fully supports the district court’s conclusion that McCormack’s refusal to pay Deisler maintenance and cure was arbitrary and capricious. Accordingly, we will affirm the district court’s award of attorney’s fees and costs.
C. Allocation of Fees and Costs
Alternatively, McCormack argues that even if the, award of attorney’s fees and costs was proper, the district court acted arbitrarily in allocating 90% of plaintiffs attorney’s fees to the general maritime claim and refusing to make an allocation of costs between it and the Jones Act claims. The district court candidly acknowledged that “[g]iven the overlapping evidence on the Jones Act claim and the maintenance and cure claim, it is difficult to separate out services attributable solely to the unsuccessful Jones Act claim.” Findings of Fact, ¶ 59. Notwithstanding this caveat, the court held that based on its “review of the record a fair estimate of counsel time expended in attempting to prove defendant’s negligence under the Jones Act is 10%.” Id.
The district court must exercise its informed discretion in awarding attorney’s fees.
Pawlak v. Greenawalt,
McCormack argues only that “[i]t is inconceivable that only 10% of fees are attributable to the Jones Act jury trial, in which plaintiff unsuccessfully tried many issues not implicated in the maintenance and cure claim.” Presented with no more than this assertion of “inconceivability,” we cannot say that the division of attorney’s fees was an abuse of discretion. Although the required *1088 division of fees is difficult, our review of the record does not allow us to conclude that the district court erred in slicing the pie as it did. Accordingly, we will affirm the district court’s allocation of the award of attorney’s fees and costs.
D. The Deposition of Charles Ellis
McCormack argues that it should have been allowed to introduce the deposition of Captain Ellis under Federal Rule of Civil Procedure 32(a)(3) as Ellis was more than 100 miles from the place of trial, was no longer McCormack’s employee, and thus was unavailable within the meaning of that Rule. The district court did not allow McCormack to use Ellis’ deposition because it found that Deisler took the deposition under the misapprehension that Ellis had not witnessed any part of Deisler’s accident. The court reasoned that Deisler was therefore unlikely to have focused upon Ellis’ observations during the deposition.
Plaintiffs counsel’s strategy during the Ellis deposition was to avoid creating a deposition record which could be used against his client at trial in the event of Ellis’s unavailability at trial. This strategy is a plausible response to defendant’s misleading answer to the interrogatory in question.
Findings of Fact, ¶ 12 n. 2.
Even assuming the district court erred in excluding the deposition, we believe that any error in this regard was harmless.
See McQueeney v. Wilmington Trust Co.,
Thus, any error in failing to admit Ellis’ deposition was harmless as the district court considered the same testimony by way of the Lamorte report.
E. Challenges to the District Court’s Findings of Fact
McCormack also challenges a series of factual findings, all of which are supported by the record. We therefore find these challenges to the district court’s findings of fact to be lacking in merit.
First, McCormack claims that the district court erred in finding that plaintiff suffered a job related injury because the finding was based upon an erroneous belief that Ellis had witnessed the accident. There is ample evidence to support the district court’s finding that Ellis witnessed the accident. Melendez testified that Ellis observed the event and exclaimed: “Oh, look, he fell. He busted his a...,” as he watched. In addition, both Deisler and Melendez testified that the accident occurred.
Second, McCormack claims that the district court erred in finding that plaintiffs accident and his reports of it occurred before plaintiff was notified that he had been fired. Deisler testified that he reported the accident to both Melendez and Ellis before he was fired and that he was filling out the accident report when he was given his dismissal notice. Melendez corroborated part of that testimony. There was testimony that Deisler completed the accident report on June 16, and thereafter had his own doctor fill out and return a New Jersey Disability Form.
McCormack also argues that the testimony of Brad Simek and William Daniel contradict *1089 the district court’s findings. Simek inferred no accident had occurred because any accident should have been reported to him, and none was. Daniel testified that Deisler reported the accident to him after Deisler had been terminated. Regardless of when, if ever, Deisler told Simek or Daniel of his accident, the evidence that Deisler told Ellis and Melendez of his injury prior to being terminated supports the district court’s finding.
Third, McCormack argues that the district court erred in finding that the investigation of Deisler’s claim was not conducted in good faith. McCormack claims that the court based this finding upon an equally erroneous finding — namely, that the only reason McCormack did not pay maintenance and cure was that it believed that no accident occurred and that the medical evidence supporting Deisler’s claim was ignored.
We previously detailed the abundance of evidence supporting the district court’s finding that McCormack did not rely on Deisler’s pre-existing medical condition either in hiring him or in its decision not to pay maintenance and cure. Moreover, the record supports a finding that all of the evidence which tended to corroborate Deisler’s claim was ignored by McCormack.
Finally, McCormack argues that the district court erred in finding that Deisler will reach maximum medical improvement approximately four months after surgery. McCormack claims that Deisler admitted in his trial testimony that his doctors told him toward the end of 1989 that his medical condition would not improve. Brief of Appellant at 25. McCormack claims that the end of 1989, rather than four months after surgery, is the point of “maximum cure.” However, McCormack’s position is based upon an incomplete recitation of Deisler’s testimony. Deisler testified that his doctors told him his condition would not improve without sur gery. 21
III. CONCLUSION
For the reasons stated above we find that McCormack’s arguments are without merit. Accordingly, the judgment of the district court will be affirmed. 22
Notes
. Although there was some dispute at trial about Deisler’s prior injury, Deisler offered testimony that he had been pain free for three years prior to filling out the job application. It is undisputed that Dr. Edward Taylor, an orthopedic surgeon, treated Deisler for a herniated disk at L3-4 in 1985, and prescribed medication and exercise. Thereafter Deisler's condition improved and he resumed work as a manual laborer.
*1078 Deisler testified that when he filled out the job application, he believed he had no physical limitation which would hinder his job performance with McCormack.
. The district court's Findings of Fact state that Deisler reported for work on June 14, 1989. April 26, 1994, Findings of Fact, ¶ 4. However, that appears to be an error. Deisler's uncontro-verted trial testimony is that he received the call to report to work on Monday, June 12, 1989 and he reported the next day. See Suppl.App. at 4 (Deisler's trial testimony).
. Melendez testified at trial that he saw the aftermath.
. Bernard Lillis, McCormack's Chief Financial Officer also investigated Deisler’s claim. Lillis delegated some of the investigation to Brad Si-mek, McCormack's Dredge Superintendent who oversaw the operations of the dredge and its crew.
. The Jones Act provides in part that "[a]ny seaman who shall suffer personal injury in the course of his employment may, at his election, maintain an action for damages at law, with the right of jury trial,....” 46 U.S.C.App. § 688.
. Hereinafter both defendants will be referenced as "McCormack."
. It is undisputed that Deisler is a maritime employee who would normally be entitled to maintenance and cure.
. For a discussion of the historical underpinnings and evolution of a seaman’s right to maintenance and cure see
Cox v. Dravo Corp.,
. In
The Osceola,
a crew member sued for injuries sustained in carrying out an order given by the master. There was no allegation that the mate or the crew were negligent in their execution of the master's order. Rather, plaintiff claimed that the vessel and its owners should be liable for the negligent order of the captain in the course of the navigation or management of the vessel.
The Court distilled the substance of the questions before it into the sole issue of whether the vessel owner was liable in rem to one of the crew by reason of the improvident and negligent order of the master. The Court began its analysis by noting that for the district court’s conclusion to be correct, the liability must be founded upon the general admiralty law or upon a local statute of the state in which the accident occurred.
Id.
at 168,
That the seaman is not allowed to recover an indemnity for the negligence of the master, or any member of the crew, but is entitled to maintenance and cure, whether the injuries were received by negligence or accident.
*1080
Id.
at 175,
This proposition was undercut with the passing of the Jones Act, which provided that a seaman who is injured in the course of his employment by the negligence of the owner, master, or fellow crew members could recover damages for his injuries. See Grant Gilmore & Charles L. Black, Jr., The Law of Admiralty § 6-2, at 276-277 (2d ed. 1975).
. The duty to provide maintenance and cure is independent of any fault of the employer, and the seaman’s contributory negligence does not affect his right to maintenance and cure.
The Osceola, supra; Aguilar,
. In
Sammon v. Central Gulf Steamship Corp.,
. McCormack argues that Deisler’s failure to cross-appeal means that we must accept the district court’s finding that Deisler should have disclosed that he could not perform the work as readily as others because of his prior back injury. The argument is frivolous. Of course, an appel-lee is entitled to rely on alternative arguments which had been raised in the district court supporting the judgment without filing a cross-appeal, so long as he or she is not seeking to expand his or her rights under the judgment or limit another’s rights.
See Mark v. Borough of Hatboro,
. We reject McCormack's contention that we should, here, presume reliance from the simple fact that it asked the question. But there may be situations where courts should presume such reliance. For instance, if a shipowner requires a prospective applicant to submit to a physical examination and/or to fill out a detailed medical history form, the extent to which the employer will be required to submit affirmative proof of reliance should be diminished. It is not that reliance is no longer required; rather, it is that the employer will there have demonstrated reliance by adopting a particular procedure or form. However, where, as here, a general question about past illnesses and injuries is but a single question in a standard form employment application, the situation is markedly different. The question is simply one of many questions on a variety of topics, and the rather vague inquiry into medical history may not ever be reviewed by anyone at all. The employer’s interest in the information is significantly less than in the prior examples, and it therefore makes sense to require the shipowner to present evidence of reliance.
. Although lost wages are qualitatively different from damages for pain and suffering as the former would certainly be deemed an incident of the seaman's contract of employment, for purposes of our discussion, we will accept McCormack’s conflation of these damages.
. The Suits in Admiralty Act waives the government’s sovereign immunity:
[i]n cases where if [a United States] vessel were privately owned or operated, or if [United States] cargo were privately owned or possessed, or if a private person or property were involved, a proceeding in admiralty could be maintained, any appropriate nonjury proceeding in personam may be brought against the United States....
Gordon
v.
Lykes Bros. Steamship Co., Inc.,
In effect, the Suits in Admiralty Act is a jurisdictional statute providing for maintenance of admiralty suits against the United States which encompasses all maritime torts alleged against the United States.
See id.
at 98;
United States v. Continental Tuna Corp.,
. While the district court correctly classified Deisler’s lost wages and damages for his pain and suffering as compensatory damages, an award of consequential damages would clearly encompass these compensatory damages. Compensatory damages serve to compensate for harm sustained by a party. Restatement (Second) of Torts § 903 (1977). Consequential damages are merely compensatory damages for harm that “does not flow directly and immediately from the act of a party, but only some of the consequences or results of such act.” Black’s Law Dictionary 390 (6th ed. 1990).
.
The Iroquois,
On appeal, the Supreme Court first noted that it had recently recognized the shipowner’s duty to provide proper medical treatment for a seaman who becomes ill or injured in
The Osceola.
The Court ultimately held that the master had breached his duty to the seaman by failing to put into an intermediate port sooner. The Court further held that the fact that the seaman did not request to be taken to an intermediate port was of no significance because the master was his legal guardian and had a duty to look out for the safety and care of his seamen, whether or not such a request was made.
Id.
at 247,
. We have, however, limited the right to recover additional damages when one is not injured on the open sea.
See Graham v. Alcoa S.S. Co., Inc.,
. "Unlike the more precise requirements of res judicata, law of the case is an amorphous concept.”
. The "[l]aw of the case directs a court's discretion, it does not limit the tribunal's power.”
Schultz,
. Defendants failed to include the following testimony in their brief:
Q. Did Dr. Molzen tell you that surgery would improve your condition?
A. That is a tricky question. Dr. Molzen recommended surgery for me, yes. Yes, it would improve my condition. There is also a threat that it will not be successful, but yes it would help.
Q. Dr. Gott, did he tell you that surgery would improve your condition?
A. Yes, he did.
Q. But they also told you that there were risks involved.
A. Absolutely.
Q. Is that why you hesitated?
A. Yes.
Suppl.App. at 20.
. We will also grant Deisler's motion for reimbursement of the costs associated with Deisler’s submission of a Supplemental Appendix. The Appendix filed by McCormack was inadequate and the editing of the testimony of Melendez and Deisler was so selective as to be misleading. Deisler therefore had to file the Supplemental Appendix to clarify the record.
