234 A.D. 166 | N.Y. App. Div. | 1931
Claimants have appealed from a decision of the Court of Claims and the judgment entered thereon dated May 28, 1931, awarding them $260,750.64, with interest from August 15, 1924, to March 21, 1927, as compensation for 1,777.076 acres of land located on Montauk peninsula appropriated on August 15, 1924, by the Long Island State Park Commission. Prior to the appropriation, claimants owned two parcels of land, one of about 1,500 acres at the easterly point of the peninsula and Long Island; the other of over 4,000 acres a few miles westerly from the first, occupying the entire width of the peninsula. Its western boundary was along the easterly shore of Napeague harbor and thence southerly across a narrow neck of land to the ocean. The easterly boundary was from the ocean to the sound through about the center of Fort pond. The Commission appropriated 76 acres from the first parcel at the extreme easterly point, having about 3,700 feet of water front and a depth of 800 feet from the ocean. This was substantially all of the water frontage owned by the claimant at the extreme point of the island. The unappropriated part of this parcel was cut off from the water front to a considerable extent by lands previously sold. From the map presented on the argument, it, appears that this parcel still retained about 6,000 feet of water front, about two-thirds on Block Island sound and one-third on the ocean. The westerly 1,701 acres was. appropriated from the second parcel. It had a total water frontage of about 35,950 feet.
The argument by claimants that the land appropriated by the State had a greater value per acre than the remainder is borne out by the evidence, particularly because water frontage is desirable in connection with land of this character. The number of witnesses a:s to value was limited to three on each side, The award was at
“ The owner is not entitled to swell the damages beyond the fair market value of the land at the time it is taken by any consideration of the chances or probability that some time in the future it may be used for some purpose to which it is adapted unless it appears that the market value of the property is enhanced by the chances or probability. As was stated in Moulton v. Newburyport Water Co. (137 Mass. 163): ‘If there were different customers who were ready to give more for the land on account of this chance, or if there were any other circumstances affecting the price which it would bring upon a fair sale in the market, these elements would necessarily be considered by the jury, or by a witness, in forming an opinion of the market value.’ But the mere hopes of an owner that his property may at some future time be required for a reservoir or storage basin for supplying the city of New York or any other city with water cannot be considered unless the probability of such an event in the public mind had in fact affected the fair market value at the time it was taken.” (Matter of Simmons
Interest was-allowed only to March 21, 1927, because of a stipulation made by claimants’ attorneys in connection with an application for an order staying the Attorney-General from proceeding in this matter before the Court of Claims. An action had been commenced by these claimants to prevent the State from making the appropriation of this land. The complaint was dismissed at the Trial Term. This decision was reversed in the Appellate Division (Flagg v. Moses, 222 App. Div. 762). The decision of the Appellate Division was affirmed by the Court of Appeals (248 N. Y. 509). Upon the trial after the two appeals, the plaintiffs were unsuccessful, and the judgment dismissing their complaint was unanimously affirmed by the Appellate Division (225 App. Div. 887). During the continuance and pendency of this action and the appeals, the application for a stay was made and, as is recited in the stipulation, the judge at Special Term required as a condition for the granting of the stay that the claimants stipulate that interest should not accrue after the date mentioned. The order granting the stay at the Special Term upon that stipulation was reversed by the Appellate Division (Fowler v. Ottinger, 221 App. Div. 677). The stipulation was made on condition that there be a stay. The stay having been denied on appeal, the effect of the stipulation should terminate. The award should carry interest to the date of the judgment.
The decision of the Court of Claims should be modified by increasing the award to $300 an acre, with interest computed from the date of the appropriation August 15, 1924, until the entry of the judgment hereon.
All concur, except Van Kirk, P. J., and Hinman, J., who dissent and vote for reversal and a new trial.
The judgment of the Court of Claims is modified to direct that claimants shall recover against the State of New York $533,122.80, together with interest thereon from the 15th day of August, 1924, to the date of the entry of the judgment hereon.
Findings of fact numbered 8, 9 and 10 contained in the decision, and findings numbered 10 contained in the State’s requests to find, together with all findings of fact in the conclusions of law