OPINION OF THE COURT
The primary question to be resolved on these appeals is whether plaintiff, Fourth Ocean, was the third-party beneficiary of a demolition contract entered into between the defendant village and defendant Intеrstate. In our view, the question must be answered in the negative.
Prior to 1977, Fourth Ocean conducted a hotel and beach club on its property in the Village of Atlantic Beach. After it ceased
Fourth Ocean defaulted in complying with the court’s order and judgment directing it to demolish the unsafe buildings and structures. Thereafter, in April 1978, after public bidding, a contract was entered into between the village and Interstate whereby Interstate agreed to demolish the subject buildings and structures. The demolition contract, which did not mention Fourth Ocean by name, provided, inter alia:
“The Contractor agrees to demolish the buildings, cabanas, improvements, structures and boardwalk located on the South side of Ocean Boulevard between Putnam and Vernon Boulevards, known as the Atlаntic Beach Hotel and Cabana Club * * *
“5. * * * All walls and foundations shall be removed one (1) foot below the elevation of the existing grade of the sidewalk adjacent to it. The slab will be crushed for drainage and all large piеces removed”.
In or about January 1979, Fourth Ocean commenced an action against the village seeking (1) to еnjoin the village from assessing it with additional taxes in the amount of $86,372.63, representing the cost of the demolition, on the ground that the work “has not been completed” and (2) a declaration that the “awarding of the contraсt” to Interstate was “void and improper” due to improprieties in the bidding procedure. In accordance with this action, Fourth Ocean moved for a preliminary injunction. This motion was denied pursuant to an order of Special Term dated April 23, 1979 and the additional tax assessment, representing the cost of the demolition, was eventually paid by Fourth Ocean.
In or about September 1982, Fourth Ocean commenced the instant action against the village and Interstate to recover damages for their alleged breach of the demolition contract. The complaint alleged that (1) “in and around March 1, 1982”, Fourth Ocean commenced constructiоn of townhouses on the subject site and (2) during the course of the construction, Fourth Ocean discovered, contrary to the provisions of the demolition contract between the village and Interstate, that the foundation of the old hotel, the damaged boardwalks, and the large pieces of slab had not been removed. The complaint further alleged that (1) the village “breached its obligation” in failing to properly supervise the demolition work and (2) Interstate “breached the contract * * * in failing to remove the concrete foundation, crush the slab and * * * remove the boardwalk.”
After joinder of issue, Interstate moved and the village cross-moved fоr summary judgment on the ground that Fourth Ocean was not a third-party beneficiary of the demolition contract between the village and Interstate. In addition, the village argued that (1) Fourth Ocean’s action was one to recоver damages for breach of contract, (2) pursuant to CPLR 9802, a written notice of claim had to be filed within one year after accrual of the cause of action and an action had to be commenced within 18 months after accrual of the cause of action, (3) the demolition work was completed in July 1978 and any alleged breach of the contract accrued at that time, and (4) Fourth Ocean’s notice of claim, сoncededly served on or about July 22, 1982, and its action, commenced on or about September 1982, were untimely.
In opposition to the motions for summary judgment, Fourth Ocean argued, inter alia, that (1) whether the village and Interstate intended to benefit it was, at the very least, a question of fact to be resolved at trial and (2) the cause of action
Special Term denied Interstate’s motion for summary judgment holding:
“The Court of Appeals in Port Chester Electrical Construction Corp. v Atlas (
“ ‘It is old law that a third party may sue as a beneficiary on a contract made for his benefit. (Lawrence v Fox,
“Further, the Court of Appeals has stated that ‘the mere absence of any provision either excluding or including such coverage does not necessarily preclude proof that unnamed third party beneficiaries were intendеd to be benefited * * *’ Newin Corp. v Hartford Accident & Indem.,
Special Term, however, granted the village’s cross motion for summary judgment based on the defense of the Statute of Limitations, holding:
“The complaint herein alleges a breach of contract. Pursuant to CPLR §9802, a written notice of claim is a condition precedent to an action against the Village and has to be filed within one year after accrual of the cause of action. Salesian Society, Inc. v Village of Ellenville,
In determining whether Fourth Ocean may maintain an action as a third-party beneficiary, for breaсh of the demolition contract entered into by the village and Interstate, it is necessary to determine the intent of the parties (Lawrence v Fox,
Viewing the undisputed facts within the framework of these principles, Fourth Ocean, as a matter of law, cannot bе considered a third-party beneficiary.
The record indicates that Fourth Ocean did not request or even welcome the demolition of the buildings on its property. Thus, Fourth Ocean (1) refused to accede to the village’s initial request to demolish the buildings, (2) argued in the subsequent court proceeding that the buildings were not unsafe, (3) failed to comply with an order of the court that it demolish the buildings which were adjudicated to be unsafe, and (4) compellеd the village to enter into a contract with Interstate to accomplish that task. Moreover, it is clear that in entering into a contract
Wе have reviewed the remaining contentions raised by plaintiff on appeal and find them to be without merit.
Lazer, J. P., Bracken and Niehoff, JJ., concur.
Order modified, on the law, by deleting therefrom the provision denying defendant Interstate’s motion for summary judgment and by substituting therefor a provision granting said motion and dismissing the complaint in its entirety. As so modified, order affirmed, with one bill of costs payable by plaintiff.
