This cause came on to be heard upon the appeal, the transcript of the docket, journal entries and original papers from the Hamilton County Court of Common Pleas, and the briefs and arguments of counsel.
FACTS/PROCEEDINGS
The Thomas J. Dyer Company (“Dyer”) contracted to do construction work on the Convention Center Project in Cincinnati, Ohio. To complete a portion of its duties, Dyer engaged Weldcraft, Inc. as a subcontractor to do sheetmetal ductwork on the project. Weldcraft, in turn, entered into a contract with Ohio Farmers Insurance Company of the Westfield Companies (“Westfield”) for it to act as a surety on the contract with Dyer. Under that contract, Westfield held a bond for $219,000, from which the performance of the Weldcraft/Dyer contract was guaranteed. Seeking to protect itself as surety, Westfield contracted with Weldcraft, Clem Turner, Fred B. DeBra Company, Fred E. DeBra, Donna DeBra, Daniel H. Tarkington, Sandra Tarkington, David A. DeBra, and Diane L. DeBra (“third-party defendants”) to indemnify Westfield for any loss it incurred in its agreement with Weldcraft.
Before its obligations on the convention center were complete, Weldcraft defaulted on its contract with Dyer. To complete Weldcraft’s work, Westfield entered into an additional $24,000 contract with a second subcontractor, Four Seasons Environmental (“Four Seasons”). When it completed the project, Four Seasons sued Westfield for the amount due on the contract. Westfield then impleaded third-party defendants for indemnity. Subsequently, in response to Westfield’s motion, the trial court entered a summary judgment against the third- *159 party defendants for the amount due on the Four Seasons contract. From that judgment, Fred B. DeBra Company, Fred E. DeBra, Donna DeBra, Daniel H. Tarkington, Sandra Tarkington, David A. DeBra, and Diane L. DeBra (“De-Bra/indemnitors”) bring this appeal.
ASSIGNMENT OF ERROR: FAILURE TO MITIGATE
In their single assignment of error, DeBra/indemnitors argue that the trial court incorrectly entered summary judgment because a question of material fact remained, ie., had Westfield mitigated its damages? Specifically, DeBra/indem-nitors claim that Dyer was holding approximately $5,000 for work that Weldcraft had completed, but for which it had not been paid. They argue that if Westfield, as a surety, had mitigated its damages by collecting the $5,000, their liability as indemnitors would have been reduced.
The trial court may enter summary judgment when no genuine issue of material fact remains to be litigated and the moving party is entitled to judgment as a matter of law. Civ.R. 56(C). Indemnity arises from contract, either express or implied, and is the right of a person who has been compelled to pay what another should have paid to require complete reimbursement.
Travelers Indemn. Co. v. Trowbridge
(1975),
The indemnity contract here provides that the DeBra/indemnitors “unconditionally agree to indemnify and reimburse Sureties [Westfield] against any and all loss * * * in connection with the performance of [Weldcraft/Dyer] contract.” DeBra/indemnitors argue, however, that, even though they were obligated to indemnify the sureties, Westfield was required to mitigate its damages by pursuing the $5,000 held by Dyer.
In Ohio, under the mitigation doctrine of avoidable consequences, a party who makes a claim on a contract cannot receive damages that it could have prevented by “reasonable affirmative action.”
F. Enterprises v. Kentucky Fried Chicken Corp.
(1976),
Concerning indemnitee mitigation generally, some courts in other states have held that indemnitees have a duty to take reasonable actions to avoid passing on unnecessary losses to indemnitors. See,
e.g., Internatl. Minerals & Chem. Corp. v. Avon Products, Inc.
(1991),
First, when the terms of a contract are clear, the court will not enlarge on the parties’ duties under the agreement.
Gomolka v. State Auto. Ins. Co.
(1982),
Second, Westfield’s alleged failure to mitigate — not pursuing the $5,000 — is not the type of indemnitee/surety action that other courts have found to be unreasonable. For example, a corporation issued duplicate stock to a shareholder who claimed that she had lost her original certificates.
Fed. Ins. Co.,
Similarly, Avon Products sold the stock of its subsidiary, Mallinckrodt, to International Minerals and Chemical Corporation.
International Minerals, supra,
In both Federal Insurance and International Minerals, summary judgment was not allowed because the record contained evidence of unfair overreaching by the indemnitee. On the facts and circumstances of this case, there is no such overreaching. DeBra/indemnitors presented no evidence that Westfield paid Four Seasons an excessive sum for its work to finish the project. As a result, DeBra/indemnitors’ mitigation argument is without merit. The assignment of error is overruled.
CONCLUSION
The unambiguous terms of the Westfield indemnity contract state that the DeBra/indemnitors must reimburse Westfield for its losses. Furthermore, there is nothing in the indemnity contract that requires Westfield to pursue Weldcraft’s claims against Dyer. Finally, there is no evidence that Westfield failed to mitigate by causing excessive damages to DeBra/indemnitors. Therefore, the trial court did not err by granting summary judgment for Westfield.
The judgment of the trial court is affirmed.
Judgment affirmed.
