123 A.D.2d 374 | N.Y. App. Div. | 1986
In an action, inter alia, to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Kings County (Aronin, J.), dated September 12, 1985, which denied its motion for summary judgment dismissing the complaint.
Order affirmed, with costs.
The plaintiff, a mail-order company dependent upon telephone service for its sales, entered into an equipment purchase agreement with the defendant, wherein the defendant agreed to deliver and install new telephone equipment on the plaintiff’s premises for the total purchase price of $90,038. The contract imposed an affirmative duty upon the defendant to "use its best efforts to complete the installation by May 18, 1984, which is the intended Cutover Date” (emphasis supplied). The latter term is defined as "the date on which the customer [the plaintiff] is notified in writing by Rolm that the equipment is installed and is functioning so as to be substantially providing the basic service for which the equipment is intended” (emphasis supplied). According to the verified complaint, the connection of the new equipment to incoming or tie-in telephone lines was to occur over "the weekend of May 18-20, 1984” in order to minimize the risk of a disruption of telephone service during this aspect of the installation. American Telephone and Telegraph Company and New York Telephone are assertedly responsible for providing service on the incoming telephone lines. The defendant’s representative allegedly assured the plaintiff that the new equipment would be operational by Monday morning, May 21, 1984. However, the equipment was not operational on that date and service was not restored until June 25, 1984. Thereafter, the plaintiff commenced this action against the defendant to recover damages due to the deprivation of telephone service under several theories, including breach of contract, negligence, breach of warranty, and fraud.
The defendant alleges that the delay in the cutover (the date the equipment is installed and functioning), which resulted in a disruption of service, was due to circumstances
The defendant contends that regardless of the reason for the delay in cutover, it cannot be held liable for damages due to a no-damage-for-delay clause in paragraph 7 of the contract which provides: "It is also understood that all delivery and installation dates, and the intended Cutover Date are approximate, and [the defendant] shall under no circumstances be liable for damages—special, consequential, or otherwise—resulting from delays in delivery, installation or cutover.” This no-damage-for-delay provision is printed as the last sentence in a paragraph captioned "Uncontrollable Circumstances”. Aside from the last sentence, the paragraph is devoted to addressing matters pertaining to the paragraph heading. It excuses the defendant from performance of any part of the contract to the extent the defendant’s performance "is prevented, hindered, delayed, or otherwise made impractical by reason of any flood, riot, strike, explosion, war or other cause beyond the control of [the defendant]”. It also contains a provision imposing a duty upon the defendant to notify the plaintiff of any such condition.
Aside from exceptions not applicable herein, exculpatory clauses intended to insulate one of the parties from liability resulting from his own negligence are enforceable, provided the intention of the parties is expressed in clear and unequivocal language (Gross v Sweet, 49 NY2d 102, 107) and the exculpatory clause is not so obscured as to make it probable that it would escape the reader’s attention, such as by print
A no-damage-for-delay clause must be construed strictly against the drafter of the provision, in this case the defendant (see, Ippolito-Lutz, Inc. v Cohoes Hous. Auth., 22 AD2d 990) and the cause or reason for the delay must be within the contemplation of the parties at the time the contract was executed before it will bar a claim for damages (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297; Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377).
The no-damage-for-delay clause cannot be read out of context. The first portion of the "Uncontrollable Circumstance” paragraph excuses delays in performance "by reason of flood, riot, strike, war or other cause beyond the control of [the defendant].” Applying the rule of ejusdem generis, the comprehensive words "other cause beyond the control” of the defendant are restricted to some extraordinary cause analogous to the specifically named contingencies and not to problems which must naturally be anticipated as to performance (see, Traylor v Crucible Steel Co., 192 App Div 445, affd 232 NY 583). Since a definite date for the cutover (May 18, 1984) was fixed in paragraph 1 of the agreement, so much of the no-damage-for-delay clause which stated "[i]t is also understood that all delivery and installation dates, and the intended cutover date are approximate,” indicate that the parties intended that the defendant would have a reasonable time after May 18, 1984, to install a functioning telephone system. Since the first portion of paragraph 7 excuses the defendant from delays it may sustain by reason of extraordinary and unanticipated causes, the parties must have intended the no-damage-for-delay clause to apply to delay sustained by the defendant due to causes within the contemplation of the parties at the time the contract was entered into, which would preclude the defendant from completing performance by May 18 or a reasonable time thereafter. Any other construction would render the no-damage-for-delay clause repetitious and meaningless. However, it cannot be assumed from such a general no-damage-for-delay clause that it was intended to bar a claim for damages for delay caused by the defendant’s breach of an essential or fundamental obligation of its contract. Such an intent requires explicit language (see, Johnson v City of New
As to paragraph 4 of the contract, entitled "Warranty,” the obvious purpose was to provide a limited warranty with respect to the equipment sold by the defendant to the repair and replacement of defective parts and to preclude recovery for incidental and consequential damages. This is a plausible allocation of the risk of defective equipment which the parties could reasonably have had in mind (see, Cayuga Harvester v Allis-Chalmers Corp., 95 AD2d 5, 14-15). Similarly, the allocation of risks for delay sustained by the defendant, which precluded it from installing a functional telephone system by May 18 or a reasonable time thereafter, despite its good-faith efforts, would also logically be placed upon the plaintiff. However, it defies reason to suppose that the plaintiff, highly dependent on telephone service to remain in business, could have intended to assume the risks of delay caused by the defendant’s negligence or breach of its affirmative duty to use its best efforts to install an operational system by May 18 or within a reasonable period thereafter. A contrary construction regarding the allocation of risk for delay would leave the plaintiff without any fair remedy for the defendant’s breach of a fundamental obligation of its contract.
Accordingly, so much of the paragraph 7 captioned "Uncontrollable Circumstances”, as stated that the defendant "shall under no circumstances be liable for damages—special, consequential, or otherwise—resulting from delays in delivery, installation or cutover” is strictly construed to bar only claims by the plaintiff to recover damages for delays sustained by the