In an action, inter alia, to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Kings County (Aronin, J.), dated September 12, 1985, which denied its motion for summary judgment dismissing the complaint.
Order affirmed, with costs.
The plaintiff, a mail-order company dependent upon telephone service for its sales, entered into an equipment purchase agreement with the defendant, wherein the defendant agreed to deliver and install new telephone equipment on the plaintiff’s premises for the total purchase price of $90,038. The contract imposed an affirmative duty upon the defendant to "use its best efforts to complete the installation by May 18, 1984, which is the intended Cutover Date” (emphasis supplied). The latter term is defined as "the date on which the customer [the plaintiff] is notified in writing by Rolm that the equipment is installed and is functioning so as to be substantially providing the basic service for which the equipment is intended” (emphasis supplied). According to the verified complaint, the connection of the new equipment to incoming or tie-in telephone lines was to occur over "the weekend of May 18-20, 1984” in order to minimize the risk of a disruption of telephone service during this aspect of the installation. American Telephone and Telegraph Company and New York Telephone are assertedly responsible for providing service on the incoming telephone lines. The defendant’s representative allegedly assured the plaintiff that the new equipment would be operational by Monday morning, May 21, 1984. However, the equipment was not operational on that date and service was not restored until June 25, 1984. Thereafter, the plaintiff commenced this action against the defendant to recover damages due to the deprivation of telephone service under several theories, including breach of contract, negligence, breach of warranty, and fraud.
The defendant alleges that the delay in the cutover (the date the equipment is installed and functioning), which resulted in a disruption of service, was due to circumstances
The defendant contends that regardless of the reason for the delay in cutover, it cannot be held liable for damages due to a no-damage-for-delay clause in paragraph 7 of the contract which provides: "It is also understood that all delivery and installation dates, and the intended Cutover Date are approximate, and [the defendant] shall under no circumstances be liable for damages—special, consequential, or otherwise—resulting from delays in delivery, installation or cutover.” This no-damage-for-delay provision is printed as the last sentence in a paragraph captioned "Uncontrollable Circumstances”. Aside from the last sentence, the paragraph is devoted to addressing matters pertaining to the paragraph heading. It excuses the defendant from performance of any part of the contract to the extent the defendant’s performance "is prevented, hindered, delayed, or otherwise made impractical by reason of any flood, riot, strike, explosion, war or other cause beyond the control of [the defendant]”. It also contains a provision imposing a duty upon the defendant to notify the plaintiff of any such condition.
Aside from exceptions not applicable herein, exculpatory clauses intended to insulate one of the parties from liability resulting from his own negligence are enforceable, provided the intention of the parties is expressed in clear and unequivocal language (Gross v Sweet,
A no-damage-for-delay clause must be construed strictly against the drafter of the provision, in this case the defendant (see, Ippolito-Lutz, Inc. v Cohoes Hous. Auth.,
The no-damage-for-delay clause cannot be read out of context. The first portion of the "Uncontrollable Circumstance” paragraph excuses delays in performance "by reason of flood, riot, strike, war or other cause beyond the control of [the defendant].” Applying the rule of ejusdem generis, the comprehensive words "other cause beyond the control” of the defendant are restricted to some extraordinary cause analogous to the specifically named contingencies and not to problems which must naturally be anticipated as to performance (see, Traylor v Crucible Steel Co.,
As to paragraph 4 of the contract, entitled "Warranty,” the obvious purpose was to provide a limited warranty with respect to the equipment sold by the defendant to the repair and replacement of defective parts and to preclude recovery for incidental and consequential damages. This is a plausible allocation of the risk of defective equipment which the parties could reasonably have had in mind (see, Cayuga Harvester v Allis-Chalmers Corp.,
Accordingly, so much of the paragraph 7 captioned "Uncontrollable Circumstances”, as stated that the defendant "shall under no circumstances be liable for damages—special, consequential, or otherwise—resulting from delays in delivery, installation or cutover” is strictly construed to bar only claims by the plaintiff to recover damages for delays sustained by the
