246 P. 786 | Colo. | 1926
BRIGHTON Ditch Company sued Fort for damages to its irrigating ditch, caused by the breakage of a dam in defendant's reservoir, and recovered judgment. Defendant brings error. We shall designate the parties as in the trial court.
Plaintiff owns a ditch taking water from the South Platte river. Todd creek crosses the ditch about seven-tenths of a mile below plaintiff's headgate. Defendant's reservoir is on Todd creek, about 1,000 feet above the intersection of the creek with the ditch.
After a period of heavy rains, the dam of the reservoir broke, the water burst out, carrying part of the dam, with earth, rocks and debris with great force down the creek, upon and across plaintiff's ditch, breaking its banks, filling it up and rendering it unfit for use. Plaintiff had it cleaned out, repaired and restored and obtained judgment for the expense thereof.
1. Defendant claims the benefit of our decision inRyan Gulch Reservoir Co. v. Swartz,
2. Defendant asked the court to instruct the jury that plaintiff must prove that the damage was the proximate result and direct consequence of the construction, maintenance or operation of the reservoir, and that defendant would not be liable if the damage to plaintiff's ditch was the result of some other and independent cause, without which the injury complained of would not have resulted. The instruction was refused and plaintiff assigns error.
We could not well reverse the case for failure to give the above instruction, without discrediting witnesses for both plaintiff and defendant, some of whom were present when the catastrophe occurred, saw it with their own eyes, and testified to the fact. From this and other evidence, there is no question that the breaking of the dam in defendant's reservoir, the consequent sudden rush of a large volume of released water, tearing down the creek, was the direct and proximate cause of the damage to plaintiff's ditch below the reservoir dam. It is only a short distance between the reservoir and ditch, and it took only from one to three hours after the break in the dam to complete the disaster to the ditch. *465
It is true that ordinarily a defendant is entitled to have granted a request for a proper instruction on the question of proximate cause, and the province of the jury should not be invaded except in the clearest of cases, but when the proximate cause is indisputably disclosed, as here, by witnesses for both parties, the question becomes one of law for the court. Rocky MountainFuel Co. v. Tucker,
The refusal to give the instruction requested was not error.
3. Defendant further claims that there was not a sufficient plea or proof of damages, but to this we cannot agree. The complaint as amended was very explicit, showing that by reason of the acts complained of, the ditch was rendered entirely unfit and useless for the purpose of carrying water for irrigation; that it was necessary to clean out the canal and repair the damages so caused, and to place the canal in as good condition as before the commission of the acts complained of; that the amount necessarily expended was $729.70, giving the items; that in addition thereto, it would cost $1,000.00 more to place it in as good condition as before. The amount recovered was $892.20 and costs. We think the pleading and proof were both sufficient to sustain the judgment as to such damage to plaintiff's ditch, at and below the point of intersection of Todd creek with the ditch, where the injury to the ditch occurred. The judgment was for less than the amount shown by the pleading and proof.
There are instances, like this case, when the cost of restoration of the property to its original condition is the proper measure of damages. 17 C. J. page 882;Big Five Mining Co. v. Left Hand Ditch Co.,
The case before us is in many respects like BeaverWater Irrigation Co. v. Emerson,
MR. CHIEF JUSTICE ALLEN and MR. JUSTICE BURKE concur.