730 F.2d 778 | D.C. Cir. | 1984
Lead Opinion
Opinion for the Court filed by Circuit Judge WALD.
Opinion concurring in part and dissenting in part filed by Senior Circuit Judge MacKINNON.
In this case, several Florida municipal electric utilities
I. Background
FP & L, the largest electric utility in Florida, sells power and transmission services to retail and wholesale customers. Its retail service area, over which its transmission lines extend, covers virtually the entire Atlantic coast area from the Georgia border to Miami and the Gulf coast from Sarasota southward. FP & L, together with FPC, serve practically the entire Florida peninsula; the Tampa area is served by another investor-owned utility, Tampa Electric. Within the service areas of the two largest privately-owned utilities lie numerous small municipal and cooperatively-owned electric utilities, including Florida Cities, which serve their own customers.
The transmission system of each utility is directly connected with that of one or more adjoining utilities, and thus indirectly connected with every other utility in peninsular Florida, enabling FP & L, FPC, Florida Cities and others to create a regional market for the exchange of excess generating capacity. Under a set of “interchange agreements,” each utility can buy electricity generated by any other utility for periods ranging from one hour to three years to supplement power during generator emergencies, equipment maintenance or any time when the buyer’s incremental generation costs are, for whatever reason, higher than the seller’s.
When one utility buys power under an interchange agreement from a utility with which its transmission lines are directly connected, it pays no transmission charge.
FP & L filed with FERC a set of transmission service agreements (TSAs) setting out the terms under which it would offer wheeling service to a utility purchasing power under an interchange agreement from another utility, delivery of which required the use of FP & L’s transmission network.
Cities argued in addition that at least as to transmission rates for emergency service for periods no longer than 72 hours (TA service) and “energy exchanges” for periods of one hour (TC service), the applicable rates should not include “capacity” or “demand-related” costs. They argued that because the transmitting utility could simply decline to enter into TSAs of such short duration whenever it did not anticipate having enough excess transmitting capacity, transmission under TA and TC service agreements did not require the planning, construction and maintenance of any additional capacity and should not be assigned any of the associated capacity costs. FERC rejected both arguments and, with minor modifications, approved FP & L’s rates as just and reasonable, as required by the Federal Power Act. Cities appeal from both the refusal to impose joint rates and the inclusion of capacity costs.
II. Joint Rates
In Richmond Power & Light v. FERC, 574 F.2d 610 (D.C.Cir.1978), we upheld FERC’s rejection of a municipal electric utility’s proposal of joint rates — or “through rates” — for wheeling transactions crossing two or more electrical systems. We held that “the Commission’s failure to establish through rates can be deemed arbitrary only if the individual rates were unjustly or unreasonably high and, as well, the utilities had a duty to wheel.” Id. at 619. Florida Cities do not claim that these conditions are met here. Unlike Richmond Power, they do not contend that FP & L and FPC are obligated to wheel.
A. The Problem: “Double Rates”
Florida Cities illustrates their argument for joint transmission rates with the case of New Smyrna Beach, Florida.
Under the pricing system approved here by FERC, a utility determines its transmission costs per unit of electricity by dividing the total annual costs of constructing and maintaining its entire transmission network by the load, or the amount of power on the network, at certain peak periods.
In the case of New Smyrna, FPC and FP & L each charges a “postage stamp” rate for the use of its transmission network.
Cities claim that these individual rates combine to yield an excessive and discriminatory total rate. They argue that because FP & L and FPC pay no transmission charge for a “functionally similar” transmission of electricity across each other’s boundaries,
B. The Proposed Solution: Joint Rates
Cities concede that because they, unlike FP & L and FPC, have not invested in their own transmission networks it is proper to impose on them a portion of FP & L’s and FPC’s transmission costs. They also concede that, except for the inclusion of capacity costs discussed below, the individual
The crux of Cities’ argument to this court is that FERC has applied the right methodology to the wrong transmission network. Cities claim that because of the very high degree of integration among utilities in peninsular Florida, and especially between FP & L and FPC, the appropriate transmission network is not defined by the corporate boundaries of FP & L and FPC. In the case of service like that offered New Smyrna, which requires the use of both FP & L and FPC transmission facilities, Cities argue that FP & L and FPC should each be viewed as performing only part of the full transaction. In their view, transmission rates should be based on the combined transmission costs of both FP & L and FPC over the functionally integrated network covering most of peninsular Florida. Cities would divide those combined costs by the total peak load on the combined network to arrive at the cost per unit on the network as a whole. This method would result in a single postage stamp rate that is roughly the average rather than the sum of the two utilities’ individual rates.
The Commission rejected Cities’ proposal. Under that proposal, it concluded, joint rate customers would pay each utility significantly less than non-joint rate customers for the same use of the transmission network. According to FERC, in the absence of any evidence that each utility’s contribution to joint service is less costly than its ordinary wheeling service, the joint rate would be discriminatory as to the non-joint rate customers, forcing them to subsidize Cities’ rates for no justifiable reason. 21 FERC at 61,241.
C. Analysis
The Commission’s conclusion rests on the premise that wheeling transactions beginning and ending within the service area of a single utility do not use the adjoining utility’s transmission network, while wheeling involving two utilities uses both.
Cities, however, appear to challenge the Commission’s premise that wheeling transactions beginning and ending within a single utility’s territory do not make use of the adjoining utility’s transmission network.
The Commission did not respond directly to Cities’ claim that, contrary to its basic premise, FPC and FP & L had created a unitary system on which all loads used the combined network.
A high degree of coordination involving frequent exchanges of power between adjoining utilities does not indicate that the utilities’ corporate boundaries have no functional significance.
We need not determine whether there will ever be circumstances under which two utilities have gone beyond extensive cooperation and have so completely integrated the operation of their transmission systems that any transmission by either utility makes use of the combined network. In that case, a transaction crossing corporate boundaries, like the transmission of water across a single reservoir, would be functionally identical to a transaction within corporate boundaries. Such unusual circumstances would present a stronger case that individual rates permitted overrecovery of costs and that joint rates were therefore required. But Florida Cities have not persuaded us that FP & L’s corporate boundaries are merely illusory and without functional significance in the wheeling transactions at issue. Under these circumstances we uphold FERC’s refusal to order joint rates.
III. Capacity Costs
FERC permitted FP & L to include in its transmission rates the “rolled-in” costs of the entire transmission network, including so-called “demand” or “capacity” costs associated with constructing and maintaining the transmission capacity necessary for serving its customers’ peak demand.
A. The Transmission Service Agreements and Capacity Costs
Electric utilities often distinguish between “firm” service, under which custom
FP & L provides transmission service in conjunction with four interchange agreements: TA emergency service for periods up to seventy-two hours, TB capacity and energy for up to twelve months, TC energy exchanges for periods of one hour, and TD capacity and energy for twelve to thirty-six months. 12 FERC at 65,056. The wheeling rate applicable to all four agreements includes capacity costs associated with FP & L’s transmission system.
The Commission disagreed with the AU’s nomenclature:
Because all four of the services are offered only on an “if and when available” basis, we cannot conclude that any of them ... can be categorized as a firm service. Unlike the truly firm service customer, the customers here have no assurance they will receive any service from FP & L under the transmission service agreements.
21 FERC at 61,245. Nevertheless, the Commission accepted the gist of FP & L’s argument that “[t]he services do in a sense become firm once they are undertaken. Whether for one hour, one week, or one year, FP & L is committed to using its system to provide transmission for that duration.” Id. The Commission therefore approved as “equitable” the allocation of capacity costs to all four kinds of transmission service. It did so without addressing Cities’ argument that short term service did not actually impose any capacity costs.
In Kentucky Utilities Co., 15 FERC ¶ 61,002 (1981), and the followup opinion denying rehearing, 15 FERC ¶ 61,222 (1981), FERC set out at length its rationale for not allocating capacity costs to transmission service that was “interruptible.” In that case, the transmission service agreement gave Kentucky the limited right to interrupt or curtail service to the city of Paris up to 400 hours during any twelve consecutive months or 1000 hours during any five consecutive years. FERC held that even thpugh service was not always cut off at peak demand, Kentucky could not include its capacity costs in the rate for this service: “because of the right to interrupt, Kentucky can keep Paris from imposing any demand on Kentucky’s system during peak periods and thereby control its capacity costs.” Id. at 61,004.
The Commission further explicated its reasoning in its opinion denying rehearing, 15 FERC ¶ 61,222, in which it distinguished earlier cases permitting the allocation of capacity costs to transmission service. For example, FERC pointed to several critical circumstances justifying the allocation of capacity costs to off-peak wheeling service in New England Power Pool Participants, 52 F.P.C. 410 (1974), rehearing denied, 54 F.P.C. 1375 (1975), aff'd sub nom. Richmond Power & Light v. FERC, 574 F.2d 610 (D.C.Cir.1978). The Commission noted that the service in Richmond Power involved a reservation of capacity for the period service was provided. 15 FERC at 61,506. In addition, however, there was evidence that many of the transmission lines involved were heavily loaded at all times, with the result that the “coal-by-wire” transmission service did impose demands on the systems’ capacity. Id. Furthermore, the Commission had invoked special . emergency powers to deal with the energy crisis; “the need to induce voluntary transfers of energy to forestall an emergency” under these circumstances was an important factor in the Commission’s decision and this court’s affirmance. Id. The Commission in Kentucky Utilities stressed these factors as justifying the assignment of capacity costs: We agree with FERC’s assessment in Kentucky Utilities of the basis for our own proposal of the allocation of capacity costs in Richmond Power.
The clear import of the Commission’s decision in Kentucky Utilities is that the allocation of capacity costs to transmission service must ordinarily be justified on the basis of the transmitting utility’s inability to avoid service at peak demand and its need to plan future capacity based in part on the transmission service at issue. This approach, which comports well with established principles of cost-based ratemaking, does not appear to have been followed in this case. FP & L’s own witnesses conceded that “one hour firm is not very firm.” J.A. 468. They acknowledged that requests for transmission service under an interchange agreement could and would be refused at peak demand periods when the system’s excess capacity was just sufficient to guarantee service to firm customers in case of an emergency. J.A. 473-77. They further admitted that FP & L did not take into account interchange transactions in planning its capacity. J.A. 457. The Commission nevertheless approved the inclusion of capacity costs because the service — even that for only one hour — was “in a sense firm.” It made no attempt to reconcile its decision with the Kentucky Utilities analysis.
The Commission now argues that Kentucky Utilities has no relevance to this case, which involves wheeling services and not ordinary transmission associated with the purchase of power. We are skeptical of this distinction. First, the Commission took note in Kentucky Utilities of the initial decision in the instant case. Although it declined to “opine” on the proper resolution of the capacity cost issue now before us, the Commission described that issue as “the very point discussed by Kentucky.” 15 FERC at 61,508. The Commission is therefore not well situated to deny the relevance of the Kentucky Utilities analysis to this case. Moreover, FERC has not explained the significance of the difference
We do not believe the Commission has adequately explained the reasoning behind its decision to allocate capacity costs to all classes of transmission service under the TSAs, including service for periods of only one hour. It is not enough to state that service is “in a sense firm.” If the utility is reasonably able to predict its peak demand periods within a week,
A more comprehensive analysis may indicate that some fraction of capacity costs must fairly be allocated even to very short term wheeling service.
Conclusion
We are unfortunately unable to bring these lengthy proceedings to a close. FERC’s decision to reject Cities’ joint rate proposal was reasonable and supported by substantial evidence, and we affirm the Commission in that respect. However, the rationale behind the decision to allocate capacity costs is obscure and appears incon
Judgment accordingly.
. The four municipal customers are Fort Pierce Utilities Authority, Lake Worth Utilities Authority and the Cities of Homestead and Starke. They are supported in this action by intervenors Sebring Utilities Commission and the Cities of Clewiston, Green Cove Springs, Jacksonville Beach, Kissimmee and Vero Beach.
. This decision affirmed, with minor changes, initial ALJ decisions in Commission Docket No. ER77-175, 5 FERC ¶ 63,025 (1978), concerning transmission rates for New Smyrna Beach, and Commission Docket No. ER78-19, et al. (Phase II), 12 FERC ¶ 63,014 (1980), which consolidated proceedings concerning rates for numerous transmission customers. New Smyrna Beach is not a party to this appeal. See infra note 9. Docket No. ER78-19, et al., was initiated in October, 1977, with FP & L’s proposal to limit the availability of firm wholesale service and to increase rates for the service. Proceedings were bifurcated into Phase I concerning restrictions on availability, and Phase II concerning rates. Only Phase II proceedings are at issue in this appeal.
. This may occur, for example, when one utility can generate additional power only by starting up a "peaking” unit with high fuel costs, while another has excess capacity on large generating units with low fuel costs. In this case, a computer will match the high-incremental-cost buyer with the low-incremental-cost seller, and the utilities can arrange a purchase at mutually agreeable price — i.e., a price that lies between the seller’s incremental cost and the buyer’s "decremental” cost.
. See generally Gainesville Utilities Dep't v. Florida Power Corp., 402 U.S. 515, 91 S.Ct. 1592, 29 L.Ed.2d 74 (1971) (discussing the benefits of increasing interconnection and coordination among utilities).
. Each utility is, at different times, both a buyer and a seller. Instead of the buyer paying transmission charges to the seller for such transactions, the utilities have a reciprocal arrangement by which each utility bears its own transmission costs when it is the seller. Therefore, as FP & L points out, all customers pay rates that reflect the cost of owning and operating transmission facilities. Brief for Intervenor FP & L at 5.
. Florida Cities initially challenged FP & L’s decision to file over twenty separate agreements rather than a single tariff setting out the terms under which any utility could obtain wheeling services. FERC ordered FP & L to file a single tariff incorporating, and thus making mandato
. Cf. supra note 6. Cities are no longer asking FERC to order wheeling, either directly or indirectly, as the petitioners did in Richmond Power, 574 F.2d at 620. They are merely protesting the rate applicable to any voluntary transactions that are undertaken.
. In Part III of this opinion we discuss Florida Cities’ objection to the inclusion of capacity costs in FP & L’s cost-of-service calculations; that challenge is independent of its argument in favor of joint rates.
. New Smyrna Beach, whose rates were the subject of Docket No. ER77-175, see supra note 2, is not a party to this appeal. However, the New Smyrna Beach example has been used by all parties to this appeal to illustrate their arguments as to the joint rate proposal, and the record before the Commission, as well as its decision, on the joint rate issue in Docket No. ER78-19 was based largely on the record and the analysis of the joint rate issue in the New Smyrna Beach case. See 21 FERC at 61,243.
.FP & L witness Lloyd Williams described in more detail the application of this methodology to FP & L’s transmission rates:
To obtain the appropriate charge, it was necessary for us to determine the total annual cost of transmission service. This figure ($86,982,434) was derived by multiplying FPL’s investment in transmission facilities ($333,030,193) times our cost of capital and income taxes (16.71%). To the resultant figure of $55,649,345, we added 1976 transmission operating expenses other than income taxes of $31,333,089, to arrive at the total annual cost of transmission service of $86,-982,434. This amount was then divided by the average of the twelve monthly peak demands to obtain the transmission cost per KW of demand.
This cost per KW was then converted to a charge by applying an adjustment for revenue taxes____ The necessary charge for transmission service on the basis of 1976 costs, is therefore, $13.46 per KW per year.
J.A. 28.
. The Commission strongly favors the "rolled-in" method of calculating transmission costs. See Otter Tail Power Co., 12 FERC ¶ 61,169 at 61,420 (1980).
. FPC’s "postage stamp" rate of $9.40/KW-year, together with FP Si L’s rate of $13.46/KW-year, results in a cost to New Smyrna or any city requiring wheeling by both utilities of $22.86/KW-year.
. Of course, Cities also do not pay transmission charges for power they purchase directly from an adjoining utility. See supra note 5.
.This can be illustrated by the following simplified example. Suppose that FPC’s total annual costs are $150,000 and its peak load is 15,000 KW, resulting in a rate of $10/KW-year. Suppose further that FP & L’s total annual costs are $240,000 and its peak load is 20,000 KW, resulting in a rate of $12/KW-year. Instead of adding those rates ($22/KW-year), Cities would add the two utilities’ total annual costs ($390,-000/year) and divide by their combined peak load (35,000 KW), resulting in a single rate of $11.14/KW-year, which is the weighted average of the two individual rates. Cities' actual proposed joint rate was $7.75/KW-year, less than either of the utilities' individual rates, because of other differences between Cities and FP & L on the costs that could properly be included.
. Cities’ joint rate of $7.75 would yield $2.88/KW-year to FPC and $4.87/KW-year to FP & L.
. This premise is clearly articulated in the initial ALJ decision in Docket No. ER78-19, 12 FERC at 65,053, expressly adopted by FERC in its own decision, 21 FERC at 61,243 (1982): "The shortfall in revenue [resulting from the joint rate proposal] will come from customers who transmit on only one system and are charged on the basis of costs on one of the two
. Cities argued that if two interconnected utilities (within a regional market) were required in order to complete a transaction, then, as a matter of logic, each performed only part of the full transaction, and the' cost to each utility must therefore be only half the cost of a transaction that a single utility could complete. See, e.g., Brief for Petitioners Florida Cities at 23; Initial Brief of Florida Cities at 69, FERC Docket No. ER78-19, et al. (Phase II) (R. 4872). But the Commission recognized that it is by no means a logically inescapable proposition that when FP & L wheels, taking on power at Point A and giving up power at Point B, the fact that FPC had to deliver power to Point A reduces the use of FP & L's transmission network, and thus its costs, by about half. 21 FERC at 61,241.
. Cities’ argument for why joint rates would not be discriminatory turns upside down usual notions of what constitutes price discrimination: they argued that transactions requiring wheeling by two utilities were different, and were therefore entitled to pay each utility only part of an average joint rate, because wheeling by two utilities was required in order to complete the transaction. The Commission of course responded that it was precisely that difference which, on the contrary, justified the supposedly discriminatory "double rates.” 21 FERC at 61,241.
. See Brief for Petitioners Florida Cities at 24-28. This argument appears not to have crystalized in the agency proceedings until well after the record was closed, in Cities’ Brief on Exceptions to the 1980 ALJ decision, J.A. 369-75. Cities’ primary arguments to the Commission are summarized supra notes 17, 18. Although we discern a significant shift in Cities' position, its current position was presented to the Commission and we are not foreclosed from considering it.
. As noted, Cities’ argument shifted during the proceedings. The Commission’s decision is responsive to Cities’ argument as framed throughout most of the proceedings, but did not evaluate the more fundamental claim of a unitary system.
. If the degree of coordination demonstrated by Cities between FP & L and FPC were sufficient to require the treatment of two transmission systems as a unitary network, the network would seem to expand indefinitely with increasing regional coordination. FERC therefore shared the concern of FP & L and FPC over the consequences if Cities’ version of joint transmission rates were applied to transactions over an
. For example, a “Contract for Interchange Service between [FP & L] and Tampa Electric Company" contains schedules for interchange transactions during emergencies and equipment maintenance, and for economy exchanges. J.A. 248-274.
. In the case of economy exchanges, which may occur when one utility has excess capacity that it can make available at a low incremental cost to a buyer who could only generate the electricity it needs at a higher incremental cost, the exchanges are made on an hour-by-hour basis. At least in the case of the FP & L/Tampa agreement, supra note 22, the transactions are documented by the buyer within 24 hours after the exchange. J.A. 273.
. For example, the FP & L/Tampa agreement, supra note 22, provides for precise metering and billing of electricity transmitted across interconnections, and in-kind return of energy transmitted inadvertently as a result of human or equipment error. J.A. 237-38. These are only some of the provisions one would not expect to find among functionally merged transmission systems.
. Of course, we express no view as to whether it would be within FERC's authority to order joint rates under the circumstances presented here.
. According to testimony by FP & L witnesses, most of the costs associated with transmission service are "capacity” costs; the incremental cost of transmitting electricity on an existing system with sufficient excess capacity is very small. J.A. 519-20.
. See, e.g., Garfield & Lovejoy, Public Utility Economics 163-64 (1964) (“All utility customers should contribute to capacity costs,” but “a unit of firm demand for service should be allocated a greater share of capacity costs than a unit of demand that cannot pre-empt capacity on an equal basis with firm service.”).
. FP & L points out that the wheeling rates— $1.65/megawatt-hour — are significantly lower than the transmission rates it charges its own firm wholesale customers — about $2.50/mega-watt hour. As we understand it, this is because FP & L, lacking an adequate basis for projecting demand under the agreements, did not "annualize" its costs; that is, it included in its wheeling rates only the capacity allocable to the electricity actually transmitted, whereas it bases its regular transmission rates on a pro rata share of the total capacity, including unused capacity, that it has to maintain throughout the year in order to provide reliable service at peak demand. See Brief for Intervenor FP & L at 25; J.A. 535-37.
. This was the contention of the Commission Staff in Docket No. ER78-19. 12 FERC at 65,-056, and we use this estimate for the purpose of illustration. Its precision is not critical for this discussion; even if the actual period within which peak demand could be predicted was only one day, commitments to wheel for one hour periods would appear to place no unavoidable burden on capacity.
. See, e.g., Garfield & Lovejoy, supra note 27, at 163 ("All utility customers should contribute to capacity costs."). Although FP & L's failure to "annualize" its transmission costs, see supra note 28, appears to reduce the capacity costs charged to customers under the interchange agreements, the Commission did not rely on or even discuss this point. We are not in a position to determine on our own whether the larger part of capacity costs still charged fairly reflect the actual cost of performing the wheeling service, short term as well as long term.
. For example, although it seems unlikely, it may be unduly burdensome to require separate rates for short-term and long-term services.
. The dissent finds FERC's decision to allocate capacity costs not "plainly unreasonable,” and would affirm. Without any attempt by the Commission to reconcile its result here with the well-reasoned and, as we read it, contrary analysis of Kentucky Utilities, we do not see how we can make that judgment.
Concurrence in Part
concurring in part and dissenting in part:
I concur in the majority’s determination that the Federal Energy Regulatory Commission (the “Commission”) is not required to order joint wheeling rates among interconnected utilities. I disagree, however, with the majority’s decision that the Commission failed to provide sufficient explanation for its decision to allocate some demand costs to wheeling services.
It must be noted first that in passing upon the reasonableness of rates, the Commission is entitled to a great deal of discretion. The Supreme Court, in the analogous natural gas situation, has admonished us that
Congress has entrusted the regulation of the natural gas industry to the informed judgment of the Commission, and not to the preferences of reviewing courts. A presumption of validity therefore attaches to each exercise of the Commission’s expertise, and those who would overturn the Commission’s judgment undertake “the heavy burden of making a convincing showing that it is invalid because it is unjust and unreasonable in its consequences.” ... We are not obliged to examine each detail of the Commission’s decision; if the “total effect of the rate order cannot be said to be unjust and unreasonable, judicial inquiry under the Act is at an end.”
[The Commission] must be free, within the limitations imposed by pertinent constitutional and statutory commands, to devise methods of regulation capable of equitably reconciling diverse and conflicting interests.
Permian Basin Area Rate Cases, 390 U.S. 747, 767, 88 S.Ct. 1344, 1360, 20 L.Ed.2d 312 (1968) (quoting FPC v. Hope Natural Gas Co., 320 U.S. 591, 602, 64 S.Ct. 281, 287, 88 L.Ed. 333 (1944)).
The Commission in this case found as a matter of fact that essentially non-interruptible service for a particular contract period was not “firm.” But it also found that it was not typical interruptible service such as that involved in Kentucky Utilities Co., 15 FERC ¶ 61,002 (1981), rehearing denied, 15 FERC ¶ 61,222 (1981). The Commission concluded that it was equitable to allocate demand costs to such quasi-firm service.
The Commission, both before and after Kentucky Utilities, has consistently approved allocation of demand costs to wheeling transactions. See New England Power Pool Participants, 52 F.P.C. 410 (1974), aff'd sub nom. Richmond Power & Light v. FERC, 574 F.2d 610 (D.C.Cir.1978); Indiana & Michigan Electric Co., 10 FERC ¶ 61,295 (1980); Cleveland Electric Illuminating Co., 11 FERC ¶ 61,114 (1980); Public Service Co. of New Hampshire, 24 FERC 11 61,007 (1983). This court approved
Kentucky Utilities involved service interruptible at will. This case involves service that is essentially noninterruptible for the length of the contract period — whether one hour or three years.
. Although Permian Basin is a natural gas case, the same standard of discretion "appl[ies] to ... review of an electric rate proceeding under the Federal Power Act.” Ohio Power Co. v. FERC, 668 F.2d 880, 886 (6th Cir.1982).
. The court cited with approval, 574 F.2d at 621 n. 44, such cases as FPC v. Texaco Inc., 417 U.S. 380, 387, 94 S.Ct. 2315, 2321, 41 L.Ed.2d 141 (1974) (“[t]hat every rate of every natural gas company must be just and reasonable does not require that the cost of each company be ascertained and its rates fixed with respect to its own costs"); Colorado Interstate Gas Co. v. FPC, 324 U.S. 581, 615, 65 S.Ct. 829, 845, 89 L.Ed. 1206 (1945) (Jackson, J., concurring) ("I do not think it can be accepted as a principle of public regulation that industrial gas may have a free ride because the pipe line and compressor have to operate anyway"); Consolidated Gas Supply Corp. v. FPC, 520 F.2d 1176, 1185-86 (D.C.Cir. 1975) (actual costs are not the sole valid considerations in setting rates); and State Corporation Commission v. FPC, 206 F.2d 690, 709-10 (8th Cir.1953) (same), cert. denied, 346 U.S. 922, 74 S.Ct. 307, 98 L.Ed. 416 (1954).
. To the majority’s assertion that there is little practical difference between a one-hour contract and purely interruptible service, I would answer that any line between firm and nonfirm service is likely to be fine. The Staff, for example, advocated using one week as the minimum period that would justify allocation of demand costs. But there seems to me to be little difference between service for 7 days, which the Staff would treat as firm, and service for 6 days, 23 hours, which the Staff would treat as nonfirm. Would allocating capacity costs to 7-day service agreements therefore be unreasonable? Line-drawing of this type is best left to the Commission.