177 Iowa 51 | Iowa | 1916
There are three main points relied upon by appellant for a reversal, and these are set up in the answer and covered by the assignments of error. They are, substantially, that plaintiff failed to perform the conditions of its contract and the requirements of the bond, in that it paid to the contractor money before it was earned, when the contract required that he be paid only for work actually done, and that 10 per cent of that amount be retained; and that plaintiff engaged the contractor to perform work outside the contract, using the same men and commingling the accounts, when, as appellant claims, the contract and bond prohibited any such arrangement; and that this breach of the contract and change in the contractual relations of the parties operated as a release of the surety. There is a claim, also, that the contractor was not in court and no effort was made to serve him, and that, by reason of that fact, the appellant could not know what the real arrangements were as to advance payments and extras.
So much of the agreed statements of facts as appears to be necessary to a determination of the questions presented, in addition to parts already referred to, is as follows: After conceding that plaintiffs and defendants are officers and corporations, as alleged, and the execution of the contract and the bond, it was agreed:
“ (5) The specifications and the blue prints referred to in the contract and the bond are herewith submitted, marked Exhibit 2, and are identified by the signatures of counsel.
“(7) The work contemplated by said contract covered 30.2 miles, approximately.
"(8) On August 24, 25, and 26, 1912, the plaintiff engaged Burns to replace certain poles blown down on the main line between Boxholm and Hope, same being work not covered by the written contract of July 26, 1912. For this work, Burns used his regular gang of men, and the plaintiff-paid to Burns, on August 31, 1912, the sum of $178.96, which amount was the amount of time presented by Bums for his men on said date. The said poles were blown down by a storm, and it was impossible to operate trains for purpose of stringing wires or for Bums to go to and from his work, with the poles blown down. The poles blown down was work that Burns had nothing to do with, but were poles that carried the trolley wires.
“ (9) August 31, 1912, Burns had dug 220 holes for the poles, framed 250 poles, raised and fitted 175 poles and placed 40 ground wires, and had completed 80% of 7 miles of work which, at $120 per mile (80% of $840), would be $672. An estimate on that basis was made by plaintiff and 10% deducted ($672 less $67.20), and $604.80 was on that day paid J. F. Burns by plaintiff, the voucher or check paying said $604.80 being made payable to J. F. Bums & Company and endorsed by J. F. Burns & Company and J. F. Burns, same being paid August 31, 1912.
“ (10) On September 30, 1912, Bums had dug 565 holes for poles, framed 530 poles, set 350 poles, strung 9 miles wired (not tied in), and anchored 9 miles, and the plaintiff estimated said work as worth $1,433. Plaintiffs deducted from same the first estimate of (of August 31, 1912) $672, making $761. Deducted from this amount $76 and made the amount due Bums on this estimate $685. On September 30, 1912, the plaintiff paid Burns $1,000. No notice was given the South
" (11) Certain changes were made in the location of poles on Frazer Hill, and Burns and plaintiff agreed that Burns should be paid $72.20 for that extra labor, and same was included in the next payment. Certain changes were made in the poles at Lundgren, for which the plaintiff and Burns agreed he should have extra pay to the amount of $18.72, and same was included in the next payment.
"(12) On October 14, 1912, the said Burns being in need of funds, the plaintiff advanced to Burns the sum of $100, saíne being made prior to the making of the estimate for that month, Burns needing the money on account of men leaving him. It was a payment on work done, it being the agreement with Bums that said $100 was to be taken into account and deducted at the next estimate. The Southern Surety Company had no knowledge of this transaction.
"(13) October 31, 1912, Burns had dug 845 holes for poles, framed 830 poles, raised 531 poles, set 532 poles, set 375 guard arms and anchored 14 miles, and completed 2 miles up hill. Had wire from Wolf to Niles and had 9 miles strung in not tied. This work the plaintiff estimated at $2,561.35, and from that amount deducted first estimate ($604.80), second payment of $1,000, deducted $100 paid Bums October 14, 1912, (referred to in paragraph 12), leaving due Burns in this estimate $866.55, from which plaintiff deducted 10%, or $86.65, leaving $779.90 due on the contract. To this was added the $72.20 and $18.72 referred to in paragraph 11 above, and voucher was issued to Burns for $870.82, which, on November 1, 1912, was paid by the plaintiff. The figures on this transaction then being:
Paid on contract $ 604.80
“ “ “ 1,000.00
“ “ 100.00
1,704.80.
$ 866.55
10% retained 86.65
$ 779.90
Changes $72.20 Frazer Hill
18.72 Lundgren 90.92
Paid Nov. 1, 1912. $ 870.82
“ (14) November 8, 1912, the said Burns being in need of funds, the plaintiff paid to Burns the sum of $100, same being made prior to any estimate, with the understanding that same should be taken into account and to be deducted at the fourth estimate. Of this payment, the Southern Surety Company had no knowledge.
“ (15) It was decided between Burns and plaintiff that through a certain swamp that the poles should be anchored with screw anchors, four on each pole, instead of being fastened with rock. It was further agreed that $105 would be paid to cover the extra labor in this regard. Of this arrangement, the Southern Surety Company had no knowledge. It was impossible to construct the work as provided in the contract, and under the arrangement made, the work was facilitated. To have used rock would have been more expensive and delayed the work.
“(16) November 30, 1912, Burns had constructed 31 miles of holes framing, setting of poles and raising, 14 miles of anchors, 21 miles of copper complete, 10 miles of static complete, 17 miles of static strung, 24 miles of storm guys, 11 miles of ground rods complete, 16 miles of ground rods driven, 19 miles copper strung out, 2 miles of completed line,
“Estimate of work $3,086.00
10% 308.60
$2,777.40
Less Payments 2,484.70
292.70
Extra Labor 238.25
Amount paid to Burns Nov. 30,1912. $530.95
“(17) On November 30, 1912, the plaintiff had paid Burns the sum of $3,385.53, same being as follows:
$ 604.80 “Paid on Contract
1,000.00 cc a a
100.00 act <c
. 779.90
100.00
292.70
$2,877.40 Total "
Extra work $178.96
“ “ 72.20
“ “ 18.72
“ “ 238.25
508.13
$3,385.53,
“(23) During December, 1912, the plaintiff, in accordance with the authorization of the Southern Surety Company heretofore referred to, paid to laborers claiming liens against the plaintiff’s property for this work, the sum of $661.28, and also paid to laborers for labor performed for Burns on work additional to the contract, extras, the sum of $238'.25, making a total paid to said laborers in all of $899.53.
“(24) Plaintiff then proceeded to complete the unfinished portion of said contract with Burns, Exhibit 1, and paid out in order to do so the sum of $2,134.36, all of which was for labor.
“ (26) Plaintiff admits the limit of recovery in this case is the sum of $2,000, the amount named in the bond, interest and costs.
“(27) The reason the two vouchers above -named were made to J. F. Burns & Company was that Burns presented certain bills or estimates on letterheads of J. F. Burns & Company, and vouchers accordingly were issued by the plaintiff in that name. The name of J. F. Burns & Company was used only through inadvertence, and no other person had any interest in the contract save J. F. Burns, who alone secured and receipted for all the money paid by the plaintiffs prior to the time Burns defaulted.”
The specifications which were made a part of the contract provided, among other things:
“These specifications with the attached prints are presumed to give the full information necessary for the proper construction of said line, but the omission from either or both of any requirement, such as is essential to the construction of a first class power line of the character proposed, will not relieve the contractor of fulfilling any such requirement.”
1. The provision of tlie specifications and contract just referred to contemplates some deviation from the strict letter of the contract, although appellant contends that no departure
We have examined the record, and are of opinion that there were no changes or alterations made not contemplated and covered by the contract.
The stipulated facts show that, on September 30, 1912, the contractor, Burns, had earned $685, and that on that date he was paid $1,000. On October 14, 1912, he was paid $100, and on November 8, 1912, he again received the sum of $100. From the agreed statement of facts, it appears that:
“It was agreed at this time between plaintiff and Burns that this voucher for $1,000 was in the nature of a $315 loan on account of Burns’ lack of funds, and that same should be taken into account in the next estimate and to be deducted from the amount due Burns in the next estimate. ’ ’
From this it appears that it was expressly agreed that this
Appellant cites eases to the effect that advance payments upon a contract will release the surety upon the contractor’s bond. Other courts hold that a premature payment will not release the surety, where the security is not impaired or where the risks of the surety are not increased. Appellee cites, in support of this proposition, St. John’s College v. Ætna Indemnity Co. (N. Y.), 94 N. E. 994; Stephens v. Elver (Wis.), 77 N. W. 737; Robinson v. Hagenkamp (Minn.), 53 N. W. 813; Leghorn v. Nydell, 39 Wash. 17 (80 Pac. 833); Bateman Bros. v. Mapel, 145 Cal. 241 (78 Pac. 734); Hand Mfg. Co. v. Marks, 36 Ore. 523 (59 Pac. 549).
But we think it is unnecessary to pursue this subject of advance payments further, because, as stated, the stipulation as to the facts shows that it was a personal loan. As we understand counsel for appellant, they concede in argument that, if it was an independent loan, the surety is not discharged; because they say:
“An advance by the principal to the contractor may be construed as an independent loan, in which event the surety is not discharged.”
But they contend that, if the so-called loan is to be repaid in labor or materials, or other performance of the contract for which the bond is given, or if the loan is carried with and as a part of the one transaction, the advancement discharges the surety, and they cite to this point, among other cases, First Nat. Bank v. Fidelity Co. (Ala.), 5 L. R. A. (N. S.) 418. But in that case, it was stated that the contract was not complied with in the manner of payment or in the reservation of 10 per cent and that the transaction bears none of the earmarks of a separate, independent loan. In the instant case, it was conceded in the agreed statement that these advances were loans, and, as already stated, they were deducted at the end of the month in which the loans were made, and the 10 per cent reserved. Further cases cited by appellant on the proposition that there is a distinction between an advancement which is in fact a loan and an advancement which is an overpayment on the contract, are Museum of Fine Arts v. American Bonding Co. (Mass.), 97 N. E. 633; Fidelity & Deposit Co. v. Agnew, 152 Fed. 955.
Another item was allowed which was a necessity in the proper construction of a first class transmission line, as pro
Appellant also contends at this point that the accounts for the additional work were commingled with the accounts fob the contract work. But the stipulation shows that a separate and distinct account of all additional work was kept, and the figures are set out in detail in the stipulation, as are also the figures for the contract work. Aside from this, it is shown that the amount expended by the railroad company to finish the work which Burns contracted to do was $2,795.64. Appellees retained from money due Burns and held in their possession the required 10 per cent, which amounts to $308.60. Deducting this leaves $2,487.04, which is the net amount the appellees were damaged by the default of the contractor. This is in excess of the penalty of the bond. Under the record, we think it quite clear that the company is liable for the amount of the bond, and such was the judgment of the court.
Our conclusion is that the court rightly determined the matter, and the judgment is therefore — Affirmed.