Forster, Waterbury Co. v. F. MacKinnon Manufacturing Co.

130 Wis. 281 | Wis. | 1907

Marshall, J.

Appellant makes the following claims: (1) The court should not have allowed respondent the $98.86 for 1,883 pounds of castings shipped August 6, 1900. (2) There should have been allowed appellant an additional credit on its counterclaim of $255.38 for extra cost of putting in tie plates, occasioned by defective dove-tailed slots and brittleness of malleables. (3) An additional amount of $411.38 should have been allowed on the counterclaim for defective quality of the unused castings on account of their not being properly annealed and not manufactured so as to avoid the defects called cold-shuts. (4)' An additional amount of $169.65 should have been allowed on the counterclaim on account of expense of working off defective stock, at reduced prices. (5) A further sum of $156.80 should have been allowed on the counterclaim on account of hub cores that would be destroyed in using the balance of the castings.

At the outset it is suggested that some improper evidence was received from a witness produced by respondent, but as it is not claimed that such evidence affected the result and counsel fail to do more than merely make the suggestion that such evidence can be found in the record, we pass the subject without further notice.

As to the $98.86 claimed to have been erroneously allowed respondent, we cannot agree with appellant. It appears, as the referee found, that the item was included by appellant in a statement rendered in the usual way; not as a matter of compromise and settlement, so far as we can see. Moreover, the statement and a check accompanying it covering the balance therein admitted to be due was not thereafter treated as a settlement by either party.

The effect of the decision in the court helow as to imper*287fections in the castings, as regards the dove-tailed slots, is that they were not sufficiently serious to render the castings not good and suitable for hub hands, within the meaning of the contract, and further, that seasonable complaint was not made in regard thereto as to castings shipped after defects in appellant’s patterns were remedied. Reference to the correspondence between the parties fails to convince us that any such complaint was made after Eebruary 16, 1900, which accords with the court’s findings. Counsel for appellant suggest that there was evidence of such complaints, made verbally, in April, July, and September. By far the greater part of the shipments were made after Eebruary 16th. There was no shipment after June 29th, except the small amount covered by the item of $98.96. Eurthermore, we do not find that any definite verbal complaint as to this branch of the subject was made in April, 1900. On the whole it is considered that the evidence fairly hears out the finding. It tends to prove that the patterns furnished by respondent at first, were defective in respect to the feature designed to make perfect dovetailed slots; that such defect was removed by respondent at the latter’s request and expense; that no verbal complaint was thereafter made informing respondent that eastings would not be accepted as satisfying the contract because of defective dove-tailed slots till a considerable length of time after substantially all the shipments were made, and that no such complaint was made thereafter by letter, though complaints were made as to the castings being too brittle. In the letter written June 13, 1900, in which appellant finally rescinded the contract because the malleables were unsatisfactory, no mention was made of defective dove-tailed slots. The complaint was confined to the castings being too brittle and weak.

The rule is familiar that when an article required by contract to he of particular character is shipped to the executory vendee as of the proper kind and is received by the latter without notice being given to the" vendor within reasonable *288time thereafter that the article will not be accepted as satisfying the contract, all defects discoverable by reasonable attention to the matter are waived. Locke v. Williamson, 40 Wis. 377; Northern S. Co. v. Wangard, 117 Wis. 624, 94 N. W. 785; H. McCormick L. Co. v. Winans, 126 Wis. 649, 105 N. W. 945; Waupaca E. L. & R. Co. v. Milwaukee E. R. & L. Co. 112 Wis. 469, 88 N. W. 308. The rule in that regard was stated in the last case cited, thus:

“If a person sells another property to be delivered, accompanying the sale with a warranty, and when delivery takes place there are defects-in the property which are discoverable by a person of ordinary intelligence in the circumstances of the purchaser, by the exercise of ordinary care, and such other nevertheless accepts the property, neither objecting thereto then nor within a reasonable time thereafter, he thereby waives the defects so that he can neither rescind the same, counterclaim for damages when sxied for the purchase price, nor sue for damages for breach of warranty after paying for the property.”

Defects of the character under consideration would be visible upon the most casual inspection, and from the circumstance that such defects had been noticed from the start and the patterns were perfected after the first shipments to avoid the difficulty, appellant had good reason to pay attention to that particular matter as subsequent shipments arrived and to seasonably notify respondent if the castings made from the improved pattern were not satisfactory in that regard. Two shipments were made prior to February 10, 1900. On that day respondent was by letter notified that the dove-tailed slots, were imperfect. The next shipment was made February 12, 1900; plainly of castings prepared before the letter of February 10th. Shipments were made thereafter, from time to time, up to August 6, 1900, all except the 1,883 pounds aforesaid being, as indicated, sent by June 29, 1900, and by far the greater part before June 1, 1900. Such being the case, in the absence of evidence of any definite notice having-been given to respondent as to defective dove-tailed slots *289after February 16, 1900, till a considerable length of time after the shipments were substantially completed, the court was warranted in holding as matter of law that such defects, as to the castings made after the patterns were improved, were waived. On that ground as well as on the ground that the dove-tailed slots were not so seriously defective as to render the castings not good and suitable for hub bands, within the meaning of the contract, the disallowance of this branch of the case should not be disturbed.

The remaining question to be considered is: Were the castings not used and not obviously defective upon inspection, amounting to about 42,412 pounds, shown to be worth less than such as were contracted for because of -their not being strong enough to stand the strain required to place them on the wooden hub cores, with sufficient certainty to entitle appellant to an allowance on its counterclaim on that account ? The decision in the court below is that the evidence in that respect is not sufficiently convincing to remove the truth of the matter beyond mere conjecture. The items of appellant’s claim for damages involved in this question are (a) the contract price, being $411.38, of the same percentage of the unused castings, not defective on their face, as proved wholly worthless as to those that were*, attempted to be put to use, less the value for scrap iron; (b) the value of the small percentage of. wooden hub cores required in using the balance of the castings as past experience shows would probably be destroyed, being $156.80; and (c) cost of working off the stock, estimated at $169.65, making a total of $737.83. These claims should be considered as one, since the proper measure of damages, in case of a recovery, is the difference between the actual value of the castings and the value if they had been according to the requirements of the contract. Aultman & T. Co. v. Hetherington, 42 Wis. 622; J. I. Case P. Works v. Niles & S. Co. 90 Wis. 590, 63 N. W. 1013; Park v. Richardson & B. Co. 91 Wis. 189, 64 N. W. 859.

The evidence is undisputed that the castings were neces*290sarily subjected to great pressure in placing them on the wooden bub cores, and that in order for them to withstand it proper annealing and absence of defects called cold-shuts were necessary. Failure to so anneal the castings would leave them brittle and liable to break under the pressure, and cold-shuts would cause them to part at the sides because of the imperfect uniting of the iron on the lines of contact of the molten metal as the streams thereof flowing into the several gates, or openings, in the mould came to the blending points.

The court having found, partly as matter of fact and partly by way of construction, that the contract as understood by both parties was made with reference to a sale and purchase of castings of sufficient strength to withstand the pressure required in placing them on the wooden hub cores, such pressure being for ordinary hubs about thirty tons, as shown by the evidence, and found as matter of fact in appellant’s favor on its defense and counterclaim as to all castings shown by actual test not to be up to the requirement, and respondent having failed to except to any of the conclusions in that regard, it stands as a verity in the case that appellant is entitled to recover on its counterclaim for the diminished value of the unused castings on account of their not being up to such requirement, if such diminished value be established by the evidence with sufficient certainty to permit of an assessment of damages being made.

By reason of the state of the case referred to, unexeepted to by respondent, there is no question of implied warranty nor any as to whether allowances were improperly made by the trial court, for failure of castings actually tested to come up to the required strength, that we need consider. Some such questions are discussed in respondent’s brief, but may well be passed without further mention.

To enable appellant to recover for failure of the unused castings to come up to the contract requirements as to strength, it was not necessary to prove the amount of the de-*291fcctivcs nor the diminished value of the castings by reason thereof, with the certainty of a demonstration. All that was required was to establish' such matters to a reasonable certainty. If more was required in judicially assessing damages many wrongs would go unrighted. It is familiar law that even loss of opportunity to make profits in a business is a proper subject for compensation in damages by the person producing such loss, and that proof of profits derived from such business covering a considerable period of operations furnishes a legitimate basis for determining the compensation recoverable for profits prevented through a discontinuance thereof produced by. breach of contract. Shepard v. Milwaukee G. L. Co. 15 Wis. 318; Treat v. Hiles, 81 Wis. 280, 50 N. W. 896; Kelley, M. & Co. v. La Crosse C. Co. 120 Wis. 84, 90, 97 N. W. 674.

In the last case cited the court said:

“Only when the estimation of prospective profits involves such degree of speculation and uncertainty that it is likely to work injustice, rather than justice, should courts reject it if loss of profits is the result of the breach of the contract. . . . Past experience may establish with sufficient certainty what would have been the course and results of that business during a certain period of interruption” for the recovery of damages.

Applying the foregoing principle to the situation before us it would seem that if the evidence in this case shows that the 30,000 pounds of castings used, or attempted to be used, were fairly representative of the character of those that remained, then a legitimate basis was established for estimating damages as to the latter. As we read the record that was shown. The evidence quite satisfactorily proves that from the time appellant commenced using the castings till the last of the 30,000 pounds was handled a large percentage proved to be not up to the contract strength by reason of improper annealing and cold-shuts; that about twenty per cent, of the castings had latent defects causing them to break under the *292pressure required to be put upon them and were wholly useless except for scrap iron. It does not seem necessary to refer to the evidence in detail on this subject. Since tbe defective character of the castings as to so large a quantity, including a number of invoices, was demonstrated by actual test, in the absence of any affirmative evidence to the contrary it is inferable, with sufficient certainty to sustain a finding as to the character of-those that were not used, that they were likewise defective. To so conclude would not be indulging in mere guesswork, but in a fairly logical process of reasoning, similar to that by which past experience as to profits in a business forms a legitimate basis for determining prospective profits. In any case of the accumulation of a large quantity of manufactured articles, all of the same general kind, made at the same factory and from the same patterns or designs and a large proportion thereof proving defective in certain particulars, one would naturally conclude, in the absence of evidence to the contrary, that the balance of the lot is likewise defective. We are constrained to hold that a mistake was made on this branch of the case; that too high a standard of certainty as to the establishment of facts was held to be necessary in order to enable a finding to be made on the subject of damages. In many situations compensation for loss, wrongfully produced, is recoverable where neither the loss generally nor the amount of it can be established except to a reasonable certainty.

The quantity of the unused castings, as before indicated, as appears without substantial dispute, if any, was 42,212 pounds. The only-direct evidence in the record as to the diminished value of such castings from the contract requirements on account of their being brittle and defective because-of cold-shuts, places such diminished value at one and one-half cents per pound. That was corroborated by evidence as-to the percentage that would probably break in placing the castings on hub cores, and extra cost of using them because of" *293tlieir weakness. It seems that from the whole evidence the difference between, the value of such castings as were contracted for and such as were furnished because of the contract requirements as to strength not being satisfied, is fairly measured by one and one-half cents per pound, or $638.18 for the unused stock. That entitles appellant to judgment against the plaintiff for $628.32 and interest from the time the counterclaim was interposed, to wit, January 10, 1903.

By the Gourt. — The judgment is reversed, and the cause remanded with directions to render judgment in favor of the defendant for $628.32 and interest from January 10, 1903, with costs.

midpage