*1 n willissue appeals the court of fails to
vacate its writ of mandamus.
FORMOSA PLASTICS CORPORATION Corporation,
USA and Formosa Plastic
Texas, Petitioners,
PRESIDIO ENGINEERS AND
CONTRACTORS, INC.,
Respondent.
No. 95-1291.
Supreme Court of Texas.
Argued Oct. 1996.
Decided Jan. 1998. Opinion
Dissenting Original 9,1997.
Opinion July
Rehearing Overruled March 1998.
package representa- also contained certain job. repre- tions about the foundation These (1) sentations included that Presidio would arrange responsible and be for the schedul- delivery materials, ing, ordering, and of all *3 (2) Formosa; paid by including those for Hatchell, Navarro, Molly Andy H. Mi- G. progress continually com- work was to from Hatchell, Greenhill, Tyler, chael A. Joe R. (3) completion; job mencement to and Shannon, Austin, Joseph Knight, Bob E. R. 16,1990, July on was scheduled to commence petitioners. for later, completed days and on be October Houston, Cynthia Sheppard, Robert P. T. 15,1990. Griffin, Jr., Victoria, Powers, John William Burnette, president, Bob testi- Jr., respondent. for representations fied that he relied on these preparing Presidio’s bid. Because the bid ABBOTT, Justice, opinion delivered the of package provided that the contractor would Court, PHILLIPS, in which Chief responsible be for all weather and other un- Justice, GONZALEZ, HECHT, ENOCH, delays, days HANKINSON, known he added another 30 to Justices, join. OWEN and job’s comple- his estimate of the scheduled Respondent’s We overrule motion for re- tion date. He submitted a bid on behalf of hearing voluntary and motion for remittitur. $600,000. Presidio in the amount of Because 9,1997, opinion July We withdraw our and bid, Presidio submitted the lowest Formosa following place. substitute the in its awarded Presidio the contract. Telephone In Southwestern Bell Co. v. De Lanney, (Tex.1991), 494-95 job completed days. was not this Court held that a cause of action for Rather, job eight took over months to negligence allega could not be complete, more than twice Burnette’s esti- tion that a negligently had to failed almost mate and three times the scheduled perform a contract because such a claim provided package. time in the bid The de- contract, Today sounded not in tort. lays caused Presidio to incur substantial ad- requested apply are to analysis a similar to ditional anticipated costs that were not when preclude recovery in tort for a fraudulent Presidio submitted its bid. inducement of contract claim. We decline to Presidio asserted a claim paragraph under so, holding do DeLcmney instead our contract, parties’ provided of the which analysis applicable is not to such a claim. delay Formosa was liable for all dam- probative because there is no evi ages within the “control of the owner.” dence to the entire amount of dam may Formosa countered while it ages by court, awarded the trial we reverse delays, been liable for some of the it was appeals the court of and responsible delays not for all of the remand the case to the trial court for a new losses asserted Presidio. Because the trial. parties were not able resolve their dis- I pute, Presidio sued Formosa for breach of duty good contract and breach of a faith Corporation Formosa Plastics be- dealing. brought and fair Presidio also gan large “expansion project” construction fraudulent inducement of contract facility Comfort, at its in Point Texas. Presi- performance fraudulent of contract claims Contractors, Engineers dio Inc. received representations based on made Formosa an “Invitation to Bid” from Formosa on that that Presidio discovered were false after part project requiring the construction commencing performance of the contract. of 300 concrete foundations. The invitation accompanied by Formosa counterclaimed breach of con- package bid contain- tract, ing drawings, specifications, urging properly technical not general Presidio had information, sample completed and a contract. The bid some of its work. jury duty good faith and fair presented and breach of
Presidio intentional, premedi- wantonly, inten- dealing willfully, that Formosa had an were done the contractors tated scheme defraud tionally, or with conscious indifference to expansion working project. Presidio, on its Under jury awarded rights of further scheme, Formosa enticed contractors damages. exemplary million Presidio $10 by making misrepresenta- make low bids jury Formosa Additionally, the found that package regarding tions in the bid schedul- Presidio, causing its contract with breached materials, delivery responsibility ing, $1,267 million in the other damages. On Lin, damages. delay the director Jack hand, jury also concluded that department, Formosa’s civil admitted that comply caus- fully with the did representing deceptively by acted $107,000 damages. ing Formosa package contractors in the bid re- suggested The trial court a remittitur *4 ability the deliv- have the to schedule would $700,000 ducing the tort to and the ery of concrete when in truth Formosa had $467,000, damages to Presidio which delivery secretly up to its own decided set to accepted. Based on Presidio’s election money. in to Formosa schedule order save damages, recover tort rather than contract contractors, doing multiple also scheduled in judgment trial court a favor the rendered work, in same mutually exclusive to be the $700,000 damages, in actual of Presidio instance, For- area at the same time. For punitive prejudgment in million $10 to install mosa scheduled another contractor ' interest, fees, attorney’s The and costs. pipe in area at underground Presidio’s work of con- damages caused Presidio’s breach supposed to the same time Presidio was against judgment. tract were offset the Pena, For- pouring be foundations. Thomas inspector, that Formosa mosa’s admitted appealed to the the Formosa working be knew contractors would judg- appeals, of which affirmed the court other, top of each this informa- right on but court. 138. We of the trial ment passed the tion was not on to contractors. granted application Formosa’s for writ course, once the were on Of contractors consider, things, among to other error that, job, they would realize due to such has fraud claim Presidio a viable whether Formosa, unexpected delays their caused only losses related when it suffered economic inadequate. the con- were But when bids of the performance subject matter and delay damages under the requested tractors contract, legally there was párties’ whether superior rely on its Formosa would fraud, whether sufficient evidence of and position offer the contractors economic sup- to there was sufficient less than the full and fair value far damages awarded. port the entire amount of Robiehaux, fact, damages. delay In Ron that, a viable We conclude while Presidio of Formosa’s contract administration head claim, suffi- present legally it failed fraud to division, Formosa, in an effort testified that amount to entire cient evidence costs, utilize its economic to lower would Accordingly, we re- damages awarded. along and superiority string to contractors appeals judgment of the court verse the added that force them to settle. Robiehaux cause trial. remand the for a new complain then contractor] “if continued to [a from him would take the contract [Formosa] II money.” he his Under and make sure loses scheme, to allegedly stood Formosa this fraud asserts Formosa on its billion ex- save millions dollars $1.5 “Presi- be claim cannot maintained project. pansion losses re- purely were economic dio’s losses subject matter performance and the lated jury found Formosa defrauded The that our Formosa contends of the contract.” million. Presidio and awarded Presidio $1.5 Telephone Co. in Bell a decision Southwestern breached jury also found that Formosa (Tex.1991), DeLanney, 809 dealing and duty good faith fair of Pre- compels us to examine the substance as a result. Presidio million $1.5 awarded tort claim to whether fraud sidio’s determine findings on its that Formosa’s Based is, in reality, re-packaged negligence, accordingly judg- claim breach of rendered urges provided contract claim. in of Bell. mak- ment favor We determination, ing analyze following guidelines distinguishing we con- should alleged injury, tract and tort causes of action: nature the source of the duty, breached and whether the loss or risk negli- If the defendant’s conduct—such as contractually contemplated by of loss is gently burning give down house—would parties. DeLanney- counters that liability independent rise of the fact that type analysis apply does not to fraud claims. parties, contract exists between the below, agree For the reasons discussed we plaintiff’s may claim also in tort. sound with Presidio. Conversely, if the conduct— defendant’s failing publish such as an advertise-
A
give
liability only
ment —would
rise to
be-
fifty years,
last
Over the
this Court has
parties’ agreement,
cause it breaches the
analyzed the distinction between torts and
plaintiff’s
ordinarily
only
claim
sounds
contracts from
perspectives.
two different
determining
contract.
whether the
first,
merely analyzed
At
the source of
plaintiff may
theory,
recover on a tort
it is
duty
determining
whether an action
also instructive to examine the nature of
instance,
sounded in tort or contract. For
plaintiff’s
loss.
loss or
When
Printing
International
Pressmen & Assis
subject
is to the
matter of the
*5
Smith,
399,
tants’
v.
contract,
Union
145 Tex.
198
plaintiff’s
ordinarily
the
action is
729,
(1946),
S.W.2d
735
this Court held that
on the contract.
“ ‘an action in contract is for the breach of a DeLanney,
applying
relationship
pursuant
DTPA
with
and contract
vacated
to settlement
merits,
concluding
allegation
an
mere breach
out
47 Inc., 432, (Tex.1986), plain- damages sounding only 708 S.W.2d 434 we held in tort when a maintained, injury that a claim from fraud could be under tiff suffers an that is distinct case, particular facts of that for the economic losses recoverable under a breach agreement pay breach of an oral bonus of contract claim is inconsistent with this law, “promise ignores to do an act in the future well-established and also the fact independent legal duty, separate is actionable fraud when made the in with that an tention, itself, design purpose deceiving, pre- from the existence of with no performing binding intention of the act.” cludes the use of fraud to induce a Stanley agreement. disapprove Accord T.O. Boot Co. v. Bank El We therefore Paso, 218, (Tex.1992); 222 following appellate opinions 847 S.W.2d Stan court to the ex- (Tex. 270, O’Boyle, they v. 462 S.W.2d 272 tent that that tort cannot hold field 1971). for a be recovered fraudulent inducement injury claim absent an that is distinct from prior clearly Our decisions also establish any permissible damages: contractual Grace precluded that tort simply are not Williamson, Corp. Petroleum 906 S.W.2d representation because a fraudulent causes 66, 1995, writ); (Tex.App. Tyler 68-69 no - only years an economic loss. Almost 150 Parker, 918, Parker 897 S.W.2d 924 Roder, ago, this Court held in Graham v. 1995, denied); App. Worth writ Bar — Fort 141, (1849), Tex. that tort were Munden, 288, bouti v. 293-94 plaintiff’s recoverable based on the claim that 1993, (Tex.App. [14th Dist.] writ — Houston fraudulently he was exchange induced to denied); Sullivan, Consulting, River promissory note a tract of land. Al- 165,170 (Tex.App [1st . -Houston though plain- sustained 1992, denied); Dist.] writ C & C Partners v. economic, purely tiff were held tort Co., Exploration Sun & Prod. including exemplary damages, 707, 1989, (Tex.App 719-20 writ de . —Dallas Graham, were recoverable. Since this Court nied); Co., Hebisen v. Nassau Dev. recognize continued to propriety 345, (Tex.App [14th . -Houston sounding despite fraud claims in tort the fact 1988, denied); Allen, Dist.] writ Allen v. aggrieved party’s that the losses were (Tex.App 574-75 . -Houston See, economic e.g., Spoljaric, losses. denied). [14th Dist.] writ We instead 436; S.W.2d at International Bankers Life plaintiff presents legally conclude if a Holloway, Ins. Co. v. sufficient evidence on each of the elements of (Tex.1963); Tex.Civ.PRAc. & Rem.Code cf. *7 claim, any fraudulent inducement 41.003(a)(1) § (expressly authorizing exem- suffered as a result of the fraud sound in plary damages for making any fraud without tort. exception type based on the of loss sustained injured Moreover, party). the we have We thus that conclude Presidio has via- held a similar context that tort against ble fraud claim that it can assert precluded were not for a tortious interfer- However, Formosa. this conclusion not does claim, ence with contract notwithstanding the inquiry. our end We must also determine fact that the for the tort claim supports whether sufficient evidence compensated for the same economic losses jury’s findings. fraud and that were recoverable under a breach of con-
tract claim. American Nat’l Petroleum Co. Ill Pipe Corp., Transcontinental Gas Line requires A fraud cause of action “a 274, (Tex.1990). 798 S.W.2d 278 false, misrepresentation, material which was
Accordingly, tort are re and which was either known to be false when coverable for a knowledge fraudulent inducement claim or made was asserted without irrespective truth, repre of whether the fraudulent its which was intended to be acted are upon, upon, sentations later subsumed in a contract which was relied and which Sears, plaintiff only or whether the injury.” suffers an eco caused Roebuck & Co. v. Meadows, 281, (Tex.1994); nomic loss related to subject matter of 877 282 S.W.2d Allowing recovery the contract. Corp., fraud DeSantis v. 793 S.W.2d Wackenhut 48 (Tex. (Tex.1990), 925, denied, ris,
670, Reyna, 928 498 U.S. rt. S.W.2d ce 1993). 765, (1991); 1048, 111 S.Ct. 112 L.Ed.2d Corp., Lawyers Ins. see also Stone Title presented We conclude that Presidio 183, promise A 554 S.W.2d legally sufficient that Formosa evidence performance an action of future constitutes representations no intention made with misrepresentation promise was able represented as in order to induce performing at the performing made with no intention of at a low to enter into this contract Presidio was made. v. Austwell time it Schindler In the and the con price. package bid bid Coop., Farmers tract, represented that Presidio Formosa 1992). However, perform failure to mere delivery of the have control of the would fraud. See id. a contract is evidence of necessary project. While concrete Rather, present Presidio had to evidence argues general more Formosa that other representations the in made with Formosa refute provisions contained in the contract per and with no intention of tent deceive representation, and the bid this the contract forming represented. Spoljaric, 708 specifically pro package unequivocally 434; 272; Stanfield, at at “arrange Presidio the deliv vide that would Co., Stanley at see also T.O. Boot [Formosa]-supplied material ery schedule of 222; Tractor, at Truck & Crim delivery ... of all responsible for the and be Moreover, presented must 597. Further, Formosa’s own materials.” even at the time be relevant Formosa’s intent plain lan witnesses admitted under representation Spoljaric, was made. control guage of the Presidio had scheduling delivery at 434. of concrete. over Accordingly, clearly there sufficient evi alleges made three Presidio that Formosa representation in fact this was dence representations- intended to never by Formosa. made keep in order to Presidio to enter into induce representation, In contravention of this First, package and the contract. the bid decided, the con- two weeks before represented would “ar- contract that Presidio delivery of signed, to take over the tract was delivery range [Formosa]- schedule of informing Presidio. the concrete without responsible for the supplied material and be Lin, department di- Formosa’s civil Jack (this delivery ... of all materials includes rector, Formosa, in an effort to testified [Formosa]).” Second, supplied by material money, the con- decided to take over save provided package the bid and the contract delivery delivery up its own crete set July job begin on was scheduled to in- was not schedule. 15, 1990, completed and be on October change contract until after the formed of Third, days paragraph 17 of the later. act- signed. Lin admitted' that Formosa represented would be that Formosa deceptively by taking over the concrete ed any delay responsible payment for the pack- delivery scheduling when the bid damages within control. its expressly provided that the contractor age *8 admitted have control. He further would and found jury agreed The with Presidio rely knew that Presidio would that Formosa In our re committed fraud. that Formosa preparing its bid. representation this on finding, all of the record view of Burnette, most favorable light must be considered in a testi- president, Bob Presidio’s party in favor the verdict rely whose on this that Presidio in fact fied did rendered, infer every and reasonable Bur- representation preparing been its bid. from is to be every ence deducible the evidence concrete further that nette testified v. delayed days Harbin Pre- indulged party’s favor. while pour was one-to-two Seale, 591, Any the re- to obtain 592 waited sidio Formosa did not than a of evidence concrete. Because Burnette thing quested more scintilla bid, finding. delays the actual such into his legally support sufficient to the calculate Cazarez, project the 937 cost of the exceeded Prods. Co. v. Continental Coffee 444, (Tex.1996); Browning-Fer price. 450 S.W.2d testimony provides
This
more than a
benefit-of-the-bargain
scin- while the
measure
supporting
tilla of evidence
conten-
computes the difference between the value as
tion
intentionally
repre-
that Formosa
made
represented and the value received. Arthur
keep
sentations
it never intended to
in Andersen,
817; Leyendecker,
945 S.W.2d at
order to induce Presidio to enter into the
at
373.
price
contract at a low bid
and that Presidio
misrepresentations
relied on these
to its det-
out-of-pocket
allows
measure
Thus,
legally
riment.
sufficient evidence
injured party
the
“to
the
in
recover
actual
supports
jury’s
the
finding.
fraud
needWe
jury
by
suffered measured
‘the difference
any
representa-
consider whether
other
part
between the value of that which he has
allegedly
tions Formosa
made were fraudu-
with,
ed
the value of
that which he has
lent.
” Leyendecker,
received.’
the rules. See
IV
(Tex.1996)
cases).
(listing
argument
Formosa’s
finally consider
We
fair
good faith and
identical
that the submission
were faced with an almost
We
trial
erroneous. The
dealing question was
voluntary
in Redman
offer of
remittitur
jury charge question on
Homes,
court submitted
Ivy,
duty good dealing faith and fair to Presi- I. PROFITS LOST dio, any.” jury found that Formosa A. No Evidence Review comply duty had failed to with this holds, As the Court of common victim awarded Presidio million. $1.5 law in the can fraud inducement recover bargain damages. benefit-of-the This mea Formosa contends that the submis recovery sure of allows for lost question sion of this was erroneous. We profits. reviewing damage In awards for lost agree. general duty good There is no profits, only this Court must conduct a tradi dealing ordinary, faith and fair arms- tional no evidence review. Texas Instru length English commercial transactions. See ments, Energy Management, Inc. v. Teletron Fischer, 521, (Tex.1983); 660 522 S.W.2d (Tex.1994) 276, (holding 877 S.W.2d 281 Assocs., Co., Harrop Electro Constr. prove there no reasonable evidence 21, (Tex.App. 22-23 - Houston certainty profits); of lost Holt Atherton In 1995, denied); Adolph writ [1st Dist.] Coors Heine, (Tex.1992) 80, dus. v. 835 84 S.W.2d 477, Rodriguez, v.Co. 481 (holding that the evidence was insuffi denied). 1989, App. Corpus writ Christi - prove profits); cient to lost Southwest Bat good We find no basis for the submission of a Owen, 423, 115 tery Corp. v. 131 Tex. S.W.2d dealing jury fair question faith and (1938) (court 1097, it determined that Accordingly, jury’s this case. affirmative decide, law, a could not as matter of support question answer to this cannot judgment required against plaintiffs facts remand, judgment. question On this should claim). profits lost not be submitted. weigh sufficiency We cannot the factual jury’s ‡ ‡ supporting verdict. ‡ ‡ ‡ ‡ evidence Stores, Inc., v. E-Z See Havner Mart conclusion, party In a we hold when (Tex.1992). only It is S.W.2d when fraudulently procures by making a contract reasonable minds cannot that evidence differ promise any keeping without intent of probative lacks force that it is “no evidence.” promise order to induce another into exe- Con/Chem, Inc., See Kindred v. cuting for a tort cause of action all Like cases where Accordingly, that fraud exists. Presidio has sufficiency legal Court considers the against a viable fraud claim Formosa even evidence, only must consider the evidence though seeks economic support that tend to the lost and inferences subject per- losses related to the matter and profits finding, disregard all parties. contrary. formance of the contract between the Holt Ather and inferences ton, 835 at 84. appeals’ judg- cannot affirm the court of We ment, however, because there is no evidence B. The NatuRE of Lost Profits Evidence award. the entire We therefore reverse the of the court profits Recovery of lost is allowed where a appeals and remand this ease for a new relationship business is established on the
trial. strength adversely effect- of a contract but by contracting party’s misconduct
ed under Jackson, Corp. Pace contract. See BAKER, J., dissenting opinion filed (1955). 179, 284 We Tex. SPECTOR, J., joins. which profits “recovery for lost does have held susceptible of require the loss be SPECTOR, BAKER, Justice, joined by Atherton, 835 exact calculation.” Holt Justice, dissenting. fact, nature, their “[i]n S.W.2d at 84. improper Because the Court conducts an profits conjectural specu- or or are more less sufficiency factual review of the evidence Corp., Pace at 348. lative.” Nevertheless, profits supporting prove Presidio’s actual must lost fraud, competent I some evidence with “reason- Formosa’s dissent. *12 Atherton, with Formosa about project, Burnette dealt certainty.” able Holt 84; contract Battery, at terms and handled the contract’s at Southwest trial, review, tes- for At Burnette disputes To no Presidio. “[a]t 1098. withstand evidence expert. minimum, an lost tified as opinions or estimates of facts, profits objective must be based lost
figures,
[r]ecovery
or
...
[and]
data
Evidence
B.Presidio’s
complete
profits
predicated on
must be
one
personal knowl-
expertise
on his
and
Based
Szczepanik
calculation.”
v. First S.
calcu-
edge, Burnette testified about how he
Co.,
Trust
by Formo-
profits caused
lated Presidio’s lost
Specifically,
testified
fraud.
Burnette
sa’s
today,
“[i]t
Before
this Court had held
truthfully represented the
that had Formosa
impossible
announce with exact certain
to
details,
would have bid
project’s
Presidio
profits.
ty any
measuring”
party’s
rule
lost
million. Burnette calculated
about $1.3
In
Battery, at 1099.
Southwest
comparing
original
by
million bid
his
fact,
$1.3
today,
until
hastened to
Court
to
estimated cost to Presidio’s actual cost
determining
any
“sanction
one method for
ratio,
by
Atherton,
multiplying
then
obtain
and
profits.”
lost
Holt
S.W.2d at
deducting
original bid. After
what Formosa
Nevertheless, today the
85.
conducts
Court
$700,-
Presidio,
figure
in a
paid
this results
improper
sufficiency
factual
review
profits.
per-
lost
which includes
profits
by weighing
Presidio’s lost
profits
centage of lost
in the
million bid
testimony against
$1.3
Presidio’s
what the Court
percentage of
is identical to the
estimated
proper
profits.
calls “the
calculation”
lost
added).
profit
original
in the
that Formosa fraud-
bid
(emphasis
to what relied under the con- tract. II. LOST PRESIDIO’S PROFITS
EVIDENCE
C.Application
Law to The
Evidence
A.Peesidio’s
Witness
course,
opinions
“hypo-
are
Of
Burnette’s
presi-
Bob
has been
Burnette
Presidio’s
“speculative”
thetical” and somewhat
—he
dent since its formation
Burnette
1984.
expect Formosa to commit fraud when
didn’t
degree
degree
has a
and a
job
bachelors
masters
won the
for
he bid
contract
engineering.
profes-
Moreover,
civil
He is a licensed
have recognized,
as we
Presidio.1
engineer
nature,
sional
in Texas.
California and
profits are “more or less
their
lost
negotiated
Burnette
for Presi-
contracts
conjectural
speculative.”
Corp.,
or
Pace
ranged
Indeed,
dio since 1984. The
just
years
contracts
at 348.
over three
quarter
from a
million
to two million
dollars
ago, this Court reaffirmed
rule that
jobs
bidding
dollars.
Presidio he
proof
Before
certainty” requirement for
“reasonable
large
in-
participated in other
contract bids
profits
of lost
“is intended
be flexible
cluding
pipeline
one
over
in Iran for
myriad
circum-
enough to accommodate
profits
million.
$100
in which
of lost
arise.”
stances
claims
Instruments,
at
III. CONCLUSION
today,
To hold as the Court
allows
does
tMs case the
holds that a
Court
Formosa,
feasor,
proven
escape
fraud
may
recover tort
for fraudulent in-
liability2 simply because Presidio cannot
irrespective
ducement
the fraudu-
whether
“prove
perfect
damages.”
measure of
See
representations
lent
are later
in a
subsumed
Battery,
Southwest
115
at 1099.
S.W.2d
Be-
party oMy
contract or whether the
suffers an
improperly weighing
sides
in on the facts and
economic loss related to the contract’s sub-
crunching the numbers to
determine
ject
recovery
To
matter.
allow
of tort fraud
“proper
damages,
calculation” of
the Court
damages oMy
plaintiff
when a
suffers an
ignores
against
also
sanctioning any
its rule
injury distinct from the economic losses re-
one
determining
profits.
method for
lost
coverable under a breach of contract claim is
Atherton,
injured
Holt
Because Presidio
some
objective
complete
based on an
calcula-
acknowledges
recog-
The Court
that Texas
tion with
certainty,
reasonable
I
affirm
would
nizes two measures of direct
for
appeals’ judgment
the court of
for Presidio.
(1)
out-of-pocket
common-law fraud:
(2) benefit-of-the-bargain
measure and the
BAKER, Justice,
SPECTOR,
joined by
measure.
See Arthur Andersen & Co.
Justice, dissenting
Overruling
to Order
Perry
Equip. Corp., 945
S.W.2d
Rehearing
Voluntary
Motions
Nissan,
(Tex.1997); W.O. Bankston
Remittitur.
(Tex.1988).
Walters,
Today
recognizes
out-of-pocket
the Court overrules Presidio’s mo- The Court
that the
rehearing
voluntary
tions for
remittitur. measure is the difference between the value
respectfully
paid
I
dissent to the Court’s order.
and the value received while the benefit
Studying
opinion again
bargain
the Court’s
after it
of the
measure is the difference be-
issued,
.say
I
I
things
represented
write
some
wish I
tween the value as
and the val-
Andersen,
my original
had said in
I
dissent.
also write
ue received. See Arthur
only escapes liability
damage
punishing
2. Formosa not
for actual
verdict
Formosa for its fraud.
punitive
$10
but also avoids a
million
Assocs.,
817;
as
That
Leyendecker
at
Inc.
damental flaws
those
Court.
&
Wechter,
is,
calculation should be based
made,
out-of-pocket
upon
actually
The Court states that the
mea-
than
the contract
rather
injured party to recover the
parties
sure allows the
but
contract the
would
made
injury
actual
suffered measured
the dif-
inducements.
Formosa’s fraudulent
with
ference between
value of that
which
Here,
to show and
Presidio was entitled
with,
parted
he has
value of that
and the
upon
did
the value of its loss based
show
Andersen,
which he received. See Arthur
actually happened
of Formo-
what
also
It is true that
in a fraudulent
Presidio asserts that
damages
damages
computed
inducement case are
as of the time
entitled to a remittitur of
case,
point
Because
at the
of Court found excessive.
the Court
fraud.
However,
essentially
appeal’s judgment,
the court of
contract.
Formosa
did not affirm
therefore,
rationale;
adopts
voluntary
remittitur of the
For-
Presidio offers
Court’s
mosa’s
suffer
fun-
amount of the actual fraud
arguments
from
same
Court found to be excessive. Presidio
may,
re-
Be that as it
the facts here are
quests
appeals judgment
distinguishable
the court of
be re-
from those
in Redman
Here,
Homes.
the Court
formed and affirmed as reformed. Alterna-
could and did con-
clusively ascertain from the
tively,
requests
record the dam-
judgment
Presidio
be
ages
testimony.
untainted
inadmissible
ap-
reformed and remanded to the court of
The substance of the
Court,
Court’s
find-
peals.
argues
Presidio
that the
ing in this case is that Presidio’s evidence
many years,
accepted voluntary
has
remitti-
profits might
about
have earned is inadmis-
Homes,
plaintiffs.
turs from
See Redman
testimony
hypothetical
sible
because it is
Ivy,
speculative. The Court held that Presidio’s
responds
that the Court should
damages testimony
support
does
an out-of-
grant
voluntaiy
Presidio a
remittitur be-
$231,000
pocket damage award of
or a bene-
awarding
cause that relief from error in
dam-
$461,000.
fit-of-the-bargain damage award of
ages unsupported by legally
evi-
sufficient
What the Court concludes amounts to a con-
through'
dence is unavailable
the office of
finding
clusive
under either mea-
voluntary remittitur.
Formosa relies on sure that the
permissible
court holds is
for a
argument.
Redman Homes in
of its
fraud
the inducement claim.
the Gourt declines to render
Homes,
In Redman
a unanimous Court
for a
lesser dollar amount because
recognized
accepted
that the
Court
re-
Formosa contests the
issue.
*15
plaintiffs
past.
mittiturs from
in the
upon
Homes,
finding
specific
Based
the Court’s
Redman
First,
response
in its
request
to Presidio’s
for
remittitur,
voluntary
neglects
Formosa
dissent,
my original
Based on
I still believe
state, but Presidio
out that in
points
Formo
disposes
that the Court
erred
how
application
sa’s
for writ of error
to this
damages issue. The Court should have af-
Court, Formosa asserted: “Presidio’s actual
appeals’ judgment
firmed the court of
damages are excessive as a matter of law to
upon
Presidio.
Court’s
$467,000.
they
the extent
exceed
mini
holding
voluntary
motion for
mum relief to which
entitled for
remittitur, Presidio is at least entitled to
that error is excision of the excess and rendi
grant
have the
that remittitur. The
Court
$467,000.
tion of
Larson
modify
appeals’
Court should
the court of
Co.,
v. Cactus Util.
matter of law to the extent that exceed
$467,000 express is an concession that Presi- proven
dio’s actual are as a matter $467,000.
of law in the amount of
