139 S.E. 708 | W. Va. | 1927
The decree appealed from sustained a demurrer to plaintiff's bill and dismissed the cause.
The controlling question to be determined is upon the sufficiency of the notice of a subcontractor to the owner of the building required by the statute in order to perfect and preserve his lien.
The bill charges in substance that the plaintiff, Forman, entered into a subcontract with Glenn Sheets, who was the general contractor employed by defendant Kelly, in the erection of a certain dwelling house on Kelly's land; that his contract was to furnish the labor and material for the plastering of the house at the price of 75c per yard; that he performed his contract, and the amount of labor and material at the contract price amounted to $446.25, and that the same had not been paid by any one. The bill further charges that plaintiff theretofore had perfected and preserved a lien for said sum against said property; and the notice which he gave *213 to the owner within 60 days after he had ceased to labor and furnish materials, and required by the statute under sub-section (c) of section 3, chapter 75, of the Code, is exhibited with the bill. It is upon the sufficiency of this notice, that is, whether it is a substantial compliance with the statute, upon which the main question turns. The bill further sets up the recordation of the notice within the time prescribed by the statute, and no question is raised upon the sufficiency of the recorded notice. The bill further charges that defendant lived near the building during the construction thereof, and that he knew plaintiff was doing the plastering in the house and was working therein before he paid the contract price of the house to Sheets. The bill further avers that defendant Kelly is estopped to deny the validity of plaintiff's claimed mechanic's lien for the reason that by a petition theretofore filed in another suit pending against Sheets, he, the defendant Kelly, claimed that certain mechanics' liens, including that of plaintiff, had been taken against his (Kelly's) property by reason of the failure of Sheets to perform his contract as general contractor; and that defendant Kelly sought in that suit to recover the amount of those liens against Sheets. The prayer of the bill is for the enforcement of plaintiff's lien against the real estate of the defendant by the sale thereof.
Under subsection (c) of section 3, chapter 75, of the Code, a subcontractor in order to perfect and preserve his lien, is required within 60 days after the completion of his subcontract to give to the owner a notice of his lien in which he is required to state that he was a subcontractor under the general contractor, naming him, describing the nature of thesubcontract, designating therein the property on which the lien is claimed and a description of the real estate on which the claim is situate, the contract price and value of the work and material furnished; that he has not been paid therefor, and that he claims and will claim a lien upon the said building, and the interest of the owner thereof in the land for the payment thereof. The notice served by plaintiff on defendant under this section complies with the requirements of the statute, except that it does not in any way refer to the *214 nature of the subcontract. It simply says that he was subcontractor with Glen Sheets, the general contractor, "for the furnishing of material and doing of the work and labor necessary to the completion of that certain building, to-wit", (describing it and the land on which it was located), and that the contract price and value of the work and material is $446.25, which has not been paid, and that he claims and will claim a lien upon the building and the interest of defendant in the land on which it is situated. Plaintiff, and appellant here, admits that no reference whatever is made in the notice to the nature of the subcontract, whether for excavation, foundation, carpenter work, plumbing, roofing, or any other of the various kinds of work which might be subcontracted in the erection of the building, but he argues that the notice given is a substantial compliance with the statute, and that the statute should be liberally construed.
Liens of mechanics and material-men are purely statutory, and it is quite generally held they must show upon their face all of the statutory requisites to their validity. 18 Rawle C. L., p. 926, sec. 57. The procedure for perfecting and preserving the lien is in the hands of the mechanic or material-man. The land owner has no control over the procedure. The statute entitles the latter to full information, so that he can protect his property from sale; and although the result of the statutory procedure is a lien of as much dignity as that of a judgment of a court, it is generally held that the facts stated in the notice need not be stated with the exactness and definiteness as is required in a declaration, or other pleading at law. A substantial compliance is all that is necessary. HarrisonConstruction Co. v. Greystone Hotel Co.,
Under statutes which required the person claiming the lien to state in the notice a statement of the materials furnished, it has been held that a general statement of the material furnished was sufficient. Chandler Lumber Co. v. Fehlau,
On the estoppel set up it is apparent that Kelly was seeking to compel Sheets to pay the liens asserted against the former's property for which the latter was primarily responsible, and cannot be construed to be an admission that said asserted liens were valid and binding. The averment and argument is that Kelley by asserting a claim in the suit against Sheets to which Forman was not a party, thereby prevented the latter from attempting in that suit to make recovery from Sheets on his subcontract, and therefore having lulled plaintiff into security, Kelley should now be made to pay the debt against Sheets. He charges in the bill that he was damaged by Kelly's act; but this is a conclusion only. It is not charged that Kelly was successful in collecting from Sheets, or that plaintiff would have been more *217 successful if he had asserted his claim against Sheets. It is apparent that Kelly was not successful, for if Sheets had been made to pay the debt, there would have been little necessity for the present suit. No charge of want of diligent prosecution of the suit against Sheets is made. There are no facts alleged on which the conclusion of resultant damages can be founded.
The decree is
Affirmed.