457 Mass. 248 | Mass. | 2010
This case comes to us on appeal from an order of a single justice of the Appeals Court vacating a preliminary injunction issued by a judge in the Superior Court against the town of Hanover (town) and Callahan, Inc. (Callahan), a general contractor with whom the town has entered into a contract for the construction of a new high school. The injunction ordered the town and Callahan to cease further work on the school pending a trial on the merits of the plaintiffs’ claim that the contract had been entered into in violation of the public bidding statutes, G. L. c. 149, §§ 44A-44H, because Callahan had made intentional misrepresentations to the town’s prequalification committee regarding its experience in school building projects. We affirm the order of the single justice, though on different grounds from those expressed in his order. Although a con
1. Background. Under G. L. c. 149, § 44A (2) (D), contracts for the construction of public buildings that are estimated to cost more than $100,000 may only be awarded to “the lowest responsible and eligible general bidder” on the basis of competitive bids and in conformity with procedures set forth in §§ 44A-44H. Where, as here, a public construction project has an estimated cost in excess of $10 million, a general contracting firm must satisfy two requirements to be deemed a “[Responsible” and “[ejligible” bidder. G. L. c. 149, § 44A (1). First, the contractor must hold a certificate of eligibility, issued by the commissioner of the division of capital asset management and maintenance (DCAM), showing that the firm has the expertise and financial capacity to perform the work required. G. L. c. 149, §§ 44A (2) (D), 44D (1) (a). Second, the contractor must be pre-qualified to bid on the project by a four-member committee of the awarding authority, that is, the agency, municipality, or other governmental authority awarding the contract,
While the questions that must be asked in the RFQ and the potential points to be awarded in each category of questions are
In conformity with these statutory requirements, in May, 2009, the town issued a RFQ inviting interested general contractors to submit statements of qualification (SOQs) to prequalify to bid on the construction of a new high school. Eleven general contractors submitted SOQs by the June 5 deadline, and on July 6, the town reported the results of the committee’s evaluation in a public register. Callahan was one of nine applicants prequali-fied by the committee to submit formal bids on the project.
On September 17, 2009, N.B. Kenney Company, Inc., a heating and air conditioning subcontractor whose subbid had not been adopted in Callahan’s winning general bid, filed a bid protest with the Attorney General, who is charged with enforcement of the competitive bidding statutes. See G. L. c. 149, § 44H. The Attorney General also received bid protests from J & J Contractors, Inc., the second lowest bidder among the general contractors, and from the Laborers’ New England Region Organizing Fund. The protesters alleged that the committee’s decision to prequalify Callahan was obtained through fraud because Callahan’s SOQ contained misrepresentations of the firm’s prior construction experience that were intended to mislead the committee. Consequently, they argued, Callahan should have been disqualified as an eligible bidder, and the town should be prohibited from entering into a contract with Callahan. Following the filing of the protests, the town requested and received additional information from Callahan about the representations made in its SOQ concerning the company’s prior construction experience.
In response to the bid protests, the Attorney General undertook an investigation and asked the town to refrain from awarding the contract or commencing work on the project while her investigation was ongoing. On September 24, however, the town issued Callahan a notice to proceed. At the bid protest hearing later that month, the Attorney General requested that the town suspend further work on the project pending her determination of the bid protests on the merits. Notwithstanding these requests, the town entered into a general contract with Callahan on or about October 15 and proceeded with construction. Two weeks later, on October 30, the Attorney General issued a decision which essentially confirmed the allegations of the bid protestors.
The Attorney General concluded that Callahan had committed “fraud” within the meaning of G. L. c. 149, § 44DV2 (h), by knowingly misrepresenting material facts in its SOQ with
Based on these findings, the Attorney General concluded that
After a nonevidentiary hearing on November 16, 2009, the motion judge allowed the plaintiffs’ motion for a preliminary injunction and ordered the town and Callahan to cease further construction of the school pending a trial on the merits. In reaching his decision, the judge held that, in contrast to common-law fraud, there is no requirement of detrimental reliance to prove fraud under G. L. c. 149, § 44DV2 (h). Relying principally on the reasoning of earlier bid protest decisions issued by the Attorney General, the judge concluded that, to succeed on the merits in their effort to overturn the decision of the prequalifying committee under § 44DV2 (h), the plaintiffs need only establish that “(1) Callahan made statements or omissions relating to a material fact, (2) that had the tendency to be relied upon by or to influence the average person, (3) that were knowingly false or misleading, and (4) were intended to mislead the prequalification committee or awarding authority.” After setting forth this standard for fraud under the statute, the judge found that the plaintiffs had
Presumably because he deemed it irrelevant under his interpretation of the meaning of fraud under G. L. c. 149, § 44DV2 (h), the judge did not address unrefuted evidence in the record that the prequalification committee had not been misled by the misrepresentations in Callahan’s SOQ and had not relied on them to its detriment. Affidavits submitted by two members of the four-person committee stated that, before the committee prequali-fied Callahan to bid, the committee members knew and had discussed the true nature of the relationship between Callahan and JTC, and were aware that JTC, not Callahan, had done the great majority of the work on North Andover High School. The committee’s consideration of this information is reflected in the fact that it awarded Callahan two out of a possible ten points for similar project experience.
The defendants sought relief from a single justice of the Appeals Court under G. L. c. 231, § 118, first par. In reviewing the motion judge’s grant of the preliminary injunction, the single justice adopted the judge’s factual findings as well as his interpretation of the meaning of fraud under G. L. c. 149, § 44DV2 (h). The single justice agreed that the plaintiffs had demonstrated a likelihood of success on the merits, but he determined that the
The plaintiffs appealed from the single justice’s order to the full Appeals Court, Mass. R. A. R 3 (a), as amended, 378 Mass. 927 (1979),
2. Standard of review. In reviewing the allowance of a preliminary injunction, whether that review is conducted by a single justice of the Appeals Court pursuant to G. L. c. 231, § 118, first par., or by an appellate court reviewing a decision of the single justice, the standard is whether the motion judge abused his discretion in issuing the preliminary injunction. See Planned Parenthood League of Mass., Inc. v. Operation Rescue, 406 Mass. 701, 709 & n.7, 717 (1990) (vacating suspension of preliminary injunction ordered by single justice); Packaging Indus. Group, Inc. v. Cheney, 380 Mass. 609, 615 (1980) (standard of review framed in terms of abuse of discretion). In conducting our review, we decide “whether the judge applied proper legal standards and whether there was reasonable support for his evaluation of factual questions.” Commonwealth v. Fremont Inv. & Loan, 452 Mass. 733, 741 (2008). See Packaging Indus. Group, Inc. v. Cheney, supra. On review, the motion judge’s “conclusions of law are subject to broad review and will be reversed if incorrect.” Id. at 616, quoting Buchanan v. United States Postal Serv., 508 F.2d 259, 267 n.24 (5th Cir. 1975).
3. Discussion. The motion judge did not abuse his discretion in finding from the circumstantial evidence that Callahan knowingly made false or misleading statements of material fact in the
Fraud is not a defined term under G. L. c. 149, § 44DV2 (h), and no appellate court of the Commonwealth has previously decided any claim involving this statute. Under the common law, fraud is a knowing false representation of a material fact intended to induce a plaintiff to act in reliance, where the plaintiff did, in fact, rely on the misrepresentation to his detriment. See Masingill v. EMC Corp., 449 Mass. 532, 540 (2007); Barrett Assocs. v. Aronson, 346 Mass. 150, 152 (1963). As earlier noted, in bid protest decisions issued pursuant to her authority under G. L. c. 149, § 44H, to enforce compliance with the competitive bidding statutes, the Attorney General has asserted that proof of fraud under G. L. c. 149, § 44DV2 (h), does not require the element of detrimental reliance. See, e.g., Matter of Everett High Sch. Elec. Subcontract, Att’y Gen. Bid Protest Decision (Nov. 2, 2006); Matter of Police Headquarters and East Fire Station, Att’y Gen. Bid Protest Decision (Aug. 10, 2006). However, these bid protest decisions, because they arise from the Attorney General’s prosecutorial, rather than her adjudicative, function, carry no precedential weight. See Brasi Dev. Corp. v. Attorney Gen., 456 Mass. 684, 694 (2010); Annese Elec. Servs, Inc. v. Newton, 431 Mass. 763, 771 (2000). See also E. Amanti & Sons v. R.C. Griffin, Inc., 53 Mass. App. Ct. 245, 253 (2001); Department of Labor & Indus, v. Boston Water & Sewer Comm’n, 18 Mass. App. Ct. 621, 623-624 n.7 (1984).
To determine the meaning of “fraud” as used in G. L. c. 149, § 44DV2 (h), we look to the intent of the Legislature “ascertained from all its words construed by the ordinary and approved usage of the language, considered in connection with the cause of its enactment, the mischief or imperfection to be remedied and the main object to be accomplished, to the end that the purpose of its framers may be effectuated.” Industrial Fin. Corp. v.
Notwithstanding these familiar principles of statutory construction, the plaintiffs, the Attorney General, and the two judges who ruled on the injunction concluded that the Legislature intended that a contractor’s intentional misrepresentation would constitute the fraud necessary to vacate a decision of a prequali-fying committee under § 44DV2 (h), even where the contractor’s deception falls short of common-law fraud. The plaintiffs contend that this conclusion is compelled by the objectives of the competitive bidding statutes, G. L. c. 149, §§ 44A-44H. A careful examination of the evolution of these statutes, however, reveals that, in the context of a claim of intentional misrepresentation, defining fraud under § 44DV2 to mean common-law fraud, as the defendants contend, respects the Legislature’s purpose in enacting § 44DV2 and is consistent with the over-all objectives of the competitive bidding statutes.
The basic framework of the Commonwealth’s contemporary
The competitive bidding statutes in effect before 1980, as they do today, required that public construction contracts be awarded to the “lowest responsible and eligible bidder,”
Beginning with the Ward Commission legislation enacted in 1980, the Legislature required bidders to provide specified information regarding their competence and experience to the awarding authority, which the awarding authority was required to evaluate “according to procedures and criteria which the deputy commissioner [of DCAM
It was not until 2004, with the enactment of G. L. c. 149, § 44DV2, inserted by St. 2004, c. 193, § 19, that awarding authorities were required to prequalify general contractors for individual projects; the statutory requirement, however, applies only to projects estimated to cost at least $10 million.
As a result of the 2004 legislation, a general contractor who
The 2004 legislation narrowly limited the grounds for appealing from the committee’s prequalification decision: “A general contractor’s score shall be made available to the general contractor upon request. The decision of the prequalification committee shall be final and shall not be subject to appeal except on grounds of fraud or collusion.” G. L. c. 149, § 44DV2 (h).
In determining the meaning of “fraud” as it appears in § 44DV2 (h), we note that the logical implication of the sequence of these two sentences — with the sentence governing an appeal from a decision of the prequalification committee following immediately after the sentence declaring that a general contractor is entitled to learn the score given to its SOQ by the prequalification committee — is that the Legislature anticipated that a general contractor denied prequalification might seek to challenge the committee’s scoring of the contractor’s SOQ. In such an appeal, “fraud” could not mean an intentional misrepresentation in the SOQ itself, because a general contractor
The Legislature, however, did not foreclose an appeal from a decision of a prequalification committee from third parties. Because G. L. c. 149, § 44DV2 (g), provides that the “register of responders shall be open for public inspection,” and, on completion of the evaluations by the prequalification committee, the “contents of the [SOQs] shall be open to the public,” we infer that the Legislature also recognized the possibility of an appeal from an allowance of prequalification by a fellow bidder or a member of the general public based, at least in part, on the contents of the SOQ. In this context, “fraud” could still mean corrupt conduct by one or more members of the committee, alone or in collusion with another, but we do not so limit its meaning. We conclude that, consistent with its common-law meaning, “fraud” in this context means a fraudulent misrepresentation by a general contractor applying for prequalification that the committee relied on to its detriment in qualifying the general contractor to bid. In the absence of detrimental reliance by the committee, a general contractor’s intentional misrepresentation, even if intended to
We believe that this conclusion is consistent with the comprehensive legislative scheme embodied in the public construction statute for two reasons. First, we do not believe the Legislature, by allowing a prequalification decision to be appealed from on grounds of “fraud,” intended to require an awarding authority to disqualify a general contractor or terminate a construction contract because of an intentional misrepresentation in a SOQ where the committee did not act corruptly or in reliance on the misrepresentation and where, in its discretion, the awarding authority does not wish to disqualify the contractor or terminate the contract. Under G. L. c. 149, § 44D (2), “[a]ny materially false statement” made by a general contractor in its application for DCAM certification or its update statement “may, in the discretion of the awarding authority, result in termination of any contract awarded the applicant by the awarding authority.” As a result, where an awarding authority learns that a general contractor with whom it has contracted has made an intentional misrepresentation in either of these two filings, the awarding authority may terminate the contract, but is not required to do so. The awarding authority retains this discretion even though a certificate of eligibility from DCAM and an update statement are both mandatory elements of a general contractor’s SOQ. G. L. c. 149, § 44DV2 (e) (4).
Second, giving the word “fraud” its common-law meaning under § 44DV2 (h) does not conflict with the “transparent” legislative intent that the competitive bidding statutes “establish an open and honest procedure for competition for public contracts.” John T. Callahan & Sons v. Malden, 430 Mass. 124, 128 (1999), quoting Modem Cont. Constr. Co. v. Lowell, 391 Mass. 829, 840 (1984). In formulating the provisions of § 44DV2 in 2004, the Legislature had no need to, and did not, concern itself with remedying intentional misrepresentations that do not infect a prequalification committee’s decision-making process because sufficient means to remedy this kind of misconduct — and thereby to ensure the integrity of the public bidding process — were already provided by statute. A general contractor who makes an intentional misrepresentation in a SOQ with the intention of deceiving the prequalification committee risks grave
4. Conclusion. In view of our interpretation of the meaning of fraud under G. L. c. 149, § 44DV2 (h), we conclude that the motion judge committed an error of law in determining that the plaintiffs would not need to prove detrimental reliance by the prequalification committee to prevail on their claim for injunc-tive relief. As a result of this error, because there is no allegation that any member of the prequalification committee acted corruptly in deciding to prequalify Callahan, and because there is unrefuted evidence that the committee did not act in reliance on any of the alleged misrepresentations, the motion judge abused his discretion in concluding that the plaintiffs were likely to succeed on the merits at trial. Having so found, we need not reach the issue whether a preliminary injunction would promote or adversely affect the public interest, because the
We affirm the single justice’s order vacating the allowance of the plaintiff’s motion for a preliminary injunction.
So ordered.
We acknowledge amicus briefs filed by the Attorney General; Associated Builders and Contractors, Inc.; the Associated General Contractors of Massachusetts; the City Solicitors and Town Counsel Association; Construction Industries of Massachusetts, Inc., and Utility Contractors Association of New England, Inc.; Foundation for Fair Contracting of Massachusetts and Brockton & Vicinity Building Trades Council; and TFT Construction Corp.
“The prequalification committee shall be comprised of 1 representative of the designer and 3 representatives of the awarding authority.” G. F. c. 149, § 44DV2 (c).
The statute instructs each awarding authority issuing a request for qualifications (RFQ) to solicit information in four specified categories and to assign points among the first three categories according to a fixed formula: (1) management experience (fifty points); (2) references (thirty points); (3) capacity to complete projects (twenty points). G. L. c. 149, § 44DV2 (e). The awarding authority is instructed to use its own discretion in allocating points within each of these categories and in evaluating and scoring contractor responses. G. L. c. 149, § 44DV2 (e), (h). The fourth category, for which no points are awarded, requires applicants to submit: (1) a commitment letter for payment, and performance bonds in the full estimated value of the contract from a surety company licensed to do business in the Commonwealth and approved by the United States Treasury Department; and (2) a certificate of eligibility from the division of capital asset management and maintenance (DCAM) demonstrating that the contractor has a capacity rating commensurate with the size and scope of the project, as well as an update statement with the information required under G. L. c. 149, § 44D (1) (a). G. L. c. 149, § 44DV2 (e).
The project specifications allowed for certain alternate design elements above the base plan. Callahan was also the winning bidder when estimates were considered with the alternate design elements included.
CaIlahan also included five residential projects and one project on a university campus, none of which fell within the definition of “Similar Project Experience” specified by the statement of qualification (SOQ).
General Laws c. 40, § 53, provides that ten taxable inhabitants of a municipality may bring suit to enforce laws relating to the expenditure of public funds by local officials. See Edwards v. Boston, 408 Mass. 643, 646 (1990), and cases cited.
N.B. Kenney Company, Inc. (Kenney), one of the parties who had filed a bid protest with the Attorney General following Callahan’s selection as the winning bidder, filed a separate suit and was a party to the proceedings in the Superior Court and before the single justice.
Where, as here, a suit is brought by citizens acting as private attorneys general to enforce a statute or a declared policy of the Legislature, a showing of irreparable harm is not required for the issuance of a preliminary injunction. LeClair v. Norwell, 430 Mass. 328, 331-332 (1999). In these circumstances, a judge instead must first determine whether the plaintiffs have shown a likelihood of success on the merits of the asserted claim and then determine whether “the requested order promotes the public interest, or, alternatively, that the equitable relief will not adversely affect the public.” Id., quoting Commonwealth v. Mass. CRINC, 392 Mass. 79, 89 (1984).
The defendants each filed cross appeals as to specific conclusions reached by the single justice but not as to his decision that the preliminary injunction should be vacated.
Kenney also appealed from the order of the single justice to the full Appeals Court but withdrew its appeal prior to oral argument before this court.
Compare G. L. c. 149, § 44A, as amended through St. 1977, c. 968, with G. L. c. 149, § 44A, as appearing in St. 1980, c. 579, § 55.
The only guidance given in the earlier statute was that a “responsible and eligible bidder” was a bidder “possessing the skill, ability and integrity necessary to the faithful performance of the work and who shall certify that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed on the work.” G. L. c. 149, § 44A, as appearing in St. 1956, c. 679, § 1. See G. L. c. 30, § 39M.
At the time of the 1980 and 1984 legislation, the agency was known as the division of capital planning and operations. In 1990, it was changed to the division of capital asset management and maintenance (DCAM). St. 1998, c. 194, §§ 182-185. For purposes of simplicity, we refer to it as DCAM.
Pursuant to St. 1980, c. 579, § 55, the burden of making this determination remained with the awarding authority, although the statute permitted an awarding authority to request that DCAM perform such an evaluation on its behalf.
Every bid made to an awarding authority for a contract of general construction must also include an “update statement” reflecting changes in the bidder’s financial position or business organization since the date of certification of eligibility. G. L. c. 149, § 44D (1) {a).
For contracts estimated to cost at least $100,000 but not more than $10,000,000, G. L. c. 149, § 44DV2 (a), permits, but does not require, an awarding authority to prequalify general contractors. Therefore, an awarding authority issuing a public contract costing less than $10,000,000 is free to rely on DCAM’s certification alone as a guarantee of a bidder’s capacity and expertise. See id.
The 2004 amendments expanded the range of construction options available to awarding authorities by allowing for the election of “at risk” and “[d]esign build” approaches for projects estimated to cost $5 million or more (G. L. c. 149A, §§ 1, 14), and required awarding authorities to retain an
An awarding authority must select its prequalified bidders before soliciting general bids. By regulation, the deadline for submission of general bids from prequalified general contractors must be at least fourteen days after the awarding authority’s issuance of invitations to bid. 810 Code Mass. Regs. § 9.10 (2005).
In 2008, G. L. c. 149, § 44DV2 (h), was amended to include “arbitrariness” and “capriciousness” as additional grounds for appeal. St. 2008, c. 303, § 23. Because the plaintiffs here allege only fraud, the addition of these grounds for appeal do not affect our analysis.
The inclusion in 2008 of “arbitrariness” and “capriciousness” as additional grounds for appeal allows a disqualified contractor to challenge the denial of his prequalification without needing to make the difficult showing of collusion. St. 2008, c. 303, § 23. Before this amendment, a contractor without direct evidence of collusion had only the argument that collusion should be inferred from the arbitrariness and capriciousness of the committee’s decision.
Because the application for DCAM certification, the update statement, and the SOQ are so interwoven in the statutory scheme to ensure that bidders are qualified, we understand that the awarding authority would have the same discretion to terminate a construction contract based on a materially false statement in a SOQ.
For this reason, we are not persuaded by the plaintiffs’ argument that fraud under G. L. c. 149, § 44DV2 (h), does not require detrimental reliance because a DCAM regulation provides, “Any General Contractor who fails to respond to the RFQ in accordance with the instructions provided in the RFQ in any material way shall be deemed to be disqualified from consideration for prequalification.” 810 Code Mass. Regs. § 9.06(5) (2005). This regulation disqualifies a general contractor from prequalification who has failed to abide by the procedural requirements in the RFQ, such as the deadline for submission, the obligation to sign the SOQ under the pains and penalties of perjury, and the need to include the required commitment letter, performance bonds, and DCAM’s certificate of eligibility. Id. It cannot reasonably be understood to require an awarding authority to disqualify a general contractor and terminate a contract based on an intentional misrepresentation that the authority did not rely on in its prequalification decision, where the statutes cited above do not require an awarding authority to terminate a contract after debarment, or after learning of an intentional misrepresentation in the contractor’s application for DCAM certification or in the update statement submitted with its SOQ. See G. L. c. 29, § 29F (h); G. L. c. 149, § 44D (2).