136 Iowa 213 | Iowa | 1907
In the year 1905 the defendant city let to the plaintiff the contract to pave, gutter, and curb a certain street or streets of said city for a stated compensation to be paid in cash, or city warrants or in payments or improvement certificates at the city’s option. On the claim that he had performed his contract, and that the city by its authorities refused to accept the same or to settle or pay for the
FINDINGS oe Fact.
(1) The crushed quarry run rock laid by the plaintiff was substantially as required by the contract.
(2) . The crushed rock above,, otherwise called “ macadam,” was laid of the required thickness.
(3) The sand was not flushed into the macadam, as required by contract, but the' court finds that substantially the result required by the contract was attained by the method adopted, that the amount of sand required to fill the voids was used, and that the voids in the macadam were filled*215 substantially as required by tbe contract, although a different means of accomplishing the same result was employed.
(4) That the bricks used by the plaintiff are the very best No. 1 Galesburg block, and that they fully meet the requirements of the contract.
(5) That sand wás used under the curbing wherever the soil itself was not sufficiently sandy to meet the requirements of the contract.
(6) That parts of the curbing were not troweled, but that it was impossible to literally comply with the contract in this respect on account of the cement being too hard, when it was reasonably safe to remove the forms; that the painting of the curbing with cement, where not troweled, accomplished practically the result contemplated by the contract.
(7) That, in respect to the improvement in its entirety, the court finds that, while the contract was not literally complied with in respect to the means of method employed in the points indicated, the results obtained were substantially the same as contemplated by the contract. The court finds that the plaintiff earnestly endeavored to attain these results, and that he has substantially performed his contract; that he has furnished the defendant city with a first-class pavement, which, as completed, is substantially in every respect the pavement and curbing required to be furnished under the terms of the contract.
(8) The court finds that no change in the grade of the streets at either the curb or sidewalk lines or established grades was made, but that the crown of the street surface was slightly raised on both streets above the established grade, in order to meet the grade of the brick paving theretofore laid: that such raising of the surface of the streets was at the crown and center thereof, and that the slopes to the curb on either side were gradual, leaving the curbs sufficiently high above the surface of the pavement at the gutter, and corresponding in all respects to the surface of the gutter of the old pavement ; that the finished work presents a uniform surface and grade in connection with the old pavement, and that the curbs are upon the established grade.
It is therefore ordered, adjudged, and decreed that the plaintiff has fully and fairly and equitably complied with his contract with the defendant city in the construction of two blocks of pavement and curbing, including intersections,*216 on Main street, in said city, and in tbe construction of one block of pavement and curbing, including intersections, on Franklin street in said city, and that he is entitled to payment therefor as against and by the defendant city of Manchester and its officers, according to the terms of his contract, and that he may be compensated and paid according to the terms of his said contract, and in that behalf, and to that end, the defendants the city of Manchester, L. Matthews, mayor of said city, D. F. Hennessy, E. S. Cowles, Jr., W. L. Drew, 33. J. Lawman, C. L. Adams, and A. D. Work, alderman of said city, and their successors in office, are ordered to accept the pavement and curbing on Main and Franklin streets, in the city of Manchester.
In accordance with these findings and conclusions judgment was rendered for plaintiff. for the relief demanded. From this judgment two of the defendant property owners have appealed.
The decisive question- upon which the rights of these parties turned -is one of fact, and, the finding of the trial court thereon being fairly sustained by the evidence, the judgment appealed from must be, and is, affirmed.