Ford Motor Co. v. Wayne Circuit Judge

226 N.W. 218 | Mich. | 1929

Ford Motor Company, a corporation, as owner, entered into several contracts with John M. Blair as Blair Construction Company, as contractor for erecting certain structures. Before the work was completed the contract relation was terminated. The owner filed a bill for accounting. It was found on an arbitration by and between the owner and the contractor that the owner was to be debited for labor and materials on the several jobs the total sum of $2,020,962.80 and credited for payments the total sum $1,583,668.03, and that there was due the contractor the sum of $437,294.77, which sum was computed upon the construction jobs as follows:

"Memphis Building ............................ $ 4,930 66 Contract No. 600, Steel Mill ................ 30,259 12 Purchase Order B-30248 ...................... 25,162 31 Purchase Order B-43097 ...................... 2,073 44 Contract No. 791, Motors Extension Bldg ...................................... 69,539 37 Contract No. 755, Somerville Bldg ........... 96,777 75 Contract No. 831, Eagle Avenue Underpass ................................. 208,552 12 ----------- Total ........................... $437,294 77"

Nearly 20 statements of mechanic's lien were filed, some on motors extension building, some on Eagle avenue underpass, some on steel mill building, and perhaps against other of the buildings. Bills to foreclose certain of these liens were filed, and other lienors came in by their several cross-bills also, *540 praying foreclosure. In the main, these foreclosure bills divide into three groups and as against the three structures just above named. The contractor assigned to certain third persons, by several assignments, a part, at least, of his claimed interest in the funds in the hands of the owner. Persons claiming to have furnished material or labor or both to the contractor brought suits against him and caused writs of garnishment to be served on the owner, who disclosed fully respecting all claimants to the funds in its hands.

Suit or suits were instituted against the owner by persons claimed to have furnished labor or material or both for part or all of the said structures, in which a primary liability of the owner is asserted. The owner sought to file an amended bill in the original cause first mentioned, a bill in the nature of a bill of interpleader, praying to be relieved of the liens, to have confirmation of the award on arbitration, and to bring in all aforesaid litigants and claimants, and offering to pay the said amount found to be due into court, and also seeking consolidation of all the suits both at law and in equity, and, being refused, here seeks to compel favorable action by mandamus.

The writ must be denied. Those who assert primary liability against the owner and no interest in the funds in its hands due the contractor may not be impleaded as claimants to the fund.Lanning v. Stiles, 176 Mich. 275. As between the owner and the contractor, the owner is entitled to credit for all payments made, but as between the owner and the lienors, the owner is entitled to credit for payments to the contractor when made in accordance with the provisions of the mechanic's lien law. 3 Comp. Laws 1915, § 14796. Whether there will be dispute *541 in this regard the record does not disclose, but the arbitration, to which the lienors were not parties, does not conclude them in this respect, and it may be therefore that some of the lien claimants will assert liability beyond the fund remaining due upon the particular structure.

Moreover it is essential to the relief here sought that "all adverse claims or titles must be dependent or derived from a common source," quoting from Lanning v. Stiles, supra. See 33 C. J. p. 433; Detroit Trust Co. v. Hunrath, 168 Mich. 180.

The liens here claimed do not have a common source. There are as many sources as there are structures upon which liens are claimed, for the source of a lien, conferred by statute, is the furnishing of labor or material or both for the particular structure upon which lien is claimed. Orderly procedure will require separate hearings on the separate groups of bills to enforce the liens. See Maxim v. Shotwell, 209 Mich. 79; SchoolDistrict v. Weston, 31 Mich. 85.

We will not pursue the subject further, having the opinion that the amendment seeking interpleader was properly refused. The question of consolidation is fully discussed inWellock v. Cowan, 221 Mich. 58, and under such holding the conclusions of the trial court on this question may not be disturbed. There is ample power in the court to adjudicate upon the lien cases, and to dispose of the matters in garnishment, and to permit the owner to pay what it owes, which it seeks to do, and to determine to whom payments will be made, and to relieve the owner speedily of its embarrassment in respect hereof.

Writ denied, with costs to defendant.

NORTH, C.J., and FEAD, FELLOWS, WIEST, McDONALD, POTTER, and SHARPE, JJ., concurred. *542