Ford Contracting, Inc. appeals the February 21, 2012 order of the Franklin Circuit Court reversing in part and affirming in part the 2010 Final Order of the Kentucky Transportation Cabinet. Having carefully reviewed the record and the arguments of the parties, we affirm in part, reverse in part, and remand for additional proceedings.
I. Facts and Procedure
In 2004, the Department of Highways, Kentucky Transportation Cabinet, began planning for a replacement bridge on KY 1742 in Casey County, Kentucky (the Project). Initially, the Department elected to close the road and reroute traffic on a thirteen-mile detour rather than construct a temporary diversion bridge near the existing bridge.
Two years later, the Department advertised the Project and requested bids from contractors. Ford submitted a bid of $294,000.00, which was below the engineer’s estimate of $364,668.39, and also the lowest bid on the Project. The Department awarded the contract to Ford on March 3, 2006.
When the public learned of the Project, opposition arose. Residents were unhappy with the thirteen-mile detour, and expressed their dissatisfaction to both the Lieutenant Governor’s office and the Department’s Chief Engineer. Additionally, 170 Casey County residents delivered a petition to the Department opposing the road closure and requesting a diversion bridge. After receiving the petition, the Department’s State Highway Engineer again reviewed the Project, but concluded that the use of a detour and road closure was still the best course.
The Department and Ford executed a formal contract on March 31, 2006. The contract called for the Project to be completed within sixty-five (65) working days after the Department’s notice to commence work and incorporated by reference the Department’s 2004 Standard Specifications for Road and Bridge Construction.
On April 10, 2006, the Department notified Ford that it was to commence the Project no later than May 10, 2006. Prior to that date, Ford initiated preparatory steps to perform the Project, ordering steel and other materials, gathering and readying equipment, installing traffic signs, and performing other preparatory work.
In early May 2006, a local newspaper reported that, despite local objections, the Project would proceed as originally planned. This ignited a fresh wave of public opposition. One resident threatened to contact an attorney and to protest the project site.
On May 9, 2006, the Project Engineer notified Ford that the Project was on indefinite hold, and instructed Ford not to close the road, effectively halting the Project. The Project Engineer also advised Ford that the Department was considering a temporary diversion to appease disgruntled citizens unhappy with the thirteen-mile detour. The Department then developed a diversion plan which called for a temporary bridge structure, able to withstand a twenty-five-year flood, to be constructed immediately adjacent to the existing bridge. The Department instructed Ford to submit a price estimate for the diversion plan.
Ford obtained diversion estimates from two other contractors: one for $346,667.00 and the other for $328,016.00. On May 31, 2006, Ford submitted these two bids along with its own diversion bid of $317,000.00 to the Department. Ford also advised the Department that it could begin work within three weeks of receiving notice to resume work. Had the Department accept
Department officials discussed Ford’s diversion estimate and decided this total cost was too high. Accordingly, the Department chose to terminate Ford’s contract and re-let the Project to include a diversion.
In September 2006, Ford submitted a claim of $553,100.60 in costs to the Department. The Department denied Ford’s claim. The Department offered to pay $16,507.42 as compensable costs. Ford rejected the Department’s offer. Following failed negotiations, Ford requested an administrative hearing.
An eight-day administrative hearing was held on nonconsecutive days in December 2007, and January and February 2008. At the hearing, Ford presented its case claiming $518,993.55 in damages resulting from the contract’s cancellation. Ford divided its damages into 15 categories:
$ 4,610.61 1. Steel (with $900 credit for scrap)
$ 0.00 2. Bonding
$ 15,907.65 3. Labor
$ 8,590.59 4. Overhead
$ 1,600.00 5. Superintendent Living Accommodations
$ 22,290.57 6. Direct, Distributed Costs
$ 4,550.00 7. Materia] Storage
$ 5,366.06 8. Prejudgment Interest3
$ 12,395.00 9. Unabsorbed Overhead
$ 43,541.64 10. Equipment Depreciation
$ 4,753.49 11. Stockpiled Materials
$ 6,126.75 12. Attorney and Expert Witness Fees4
$ 3,043.62 13. Pre-Stress Services
$ 33,075.00 14. Lost Profit
$353,142.57 15. Idle Equipment
$518,993.55 Total:
Cammle Ford, president and owner of Ford, testified in support of Ford’s damages claim. Mike Spears, a certified pub-lie accountant, also testified to the results of an annual audit of Ford he performed in 2006 and discussed that audit.
In sum, McGaughey concluded Ford’s costs were between $10,933.00 and $14,848.00. Accounting for lost profits, and reimbursement for purchased steel ($4,610.61) and pre-stress services ($3,044.00), McGaughey testified Ford was entitled to recover from the Department between $21,111.61 and $25,522.61.
After hearing the conflicting evidence, the hearing officer found that the Department had not properly terminated the contract for convenience under KRS 45A.200(2).
In sum, the hearing officer recommended payment of $52,001.26.
Following an exhaustive analysis, the hearing officer denied recovery for the remainder of Ford’s claimed damages. The hearing officer made three important findings relevant to this appeal.
First, the hearing officer found the testimony of Cammle Ford, and Ford’s overall damages claim, to lack credibility. The hearing officer explained:
If the hearing officer were to accept Ford’s arguments as to its “costs” ..., Ford would have lost $224,993.50 to perform the contract if no breach occurred. Ford would only have received $294,000.00 under the contract but has allegedly incurred $518,993.50 in “costs” to partially perform the contract. This result demonstrates the absurdity of Ford’s damages claim for $518,993.50.
[[Image here]]
Unfortunately, Ford has so exaggerated its costs and expenses, included impermissible expenses, had to exclude expenses when rightfully questioned by file Department, submitted amended damage claims, failed to produce necessary proof, and so convoluted [its] claim, that the Hearing Officer has had difficulty determining what costs and expenses were actually incurred by Ford on the project. To put it more bluntly, the Hearing Officer does not know where the truth ends and the fiction begins.
Second, the hearing officer reasoned that Ford had the burden to prove by a preponderance of the evidence that it was entitled to a “just and equitable” award of damages that would return Ford to the same position it would have been in had the contract been performed. The hearing officer rejected Ford’s remaining costs on the ground that such an award would put Ford in a better position than it would have been had the contract been completed.
Third, the hearing officer rejected Ford’s claim that its damages should be assessed under the federal cost principles set forth in 48 Code of Federal Regulations (C.F.R.) Part 31. The hearing officer concluded that the federal cost principles were nothing more than “guidelines” to be used under certain circumstances, including settlements of terminated contracts.
Ford and the Department filed timely exceptions. The Cabinet issued a final order on December 18, 2008, which accepted the Department’s exceptions, rejected the hearing officer’s improper-termination finding, denied Ford’s exceptions, and reduced Ford’s damages award from $52,001.26 to $46,490.65 (2008 Final Order).
Ford appealed to the Franklin Circuit Court which, on November 17, 2009, en
(1). Whether the price of Ford’s diversion bid or the additional delay costs constituted a substantial change in circumstances that warranted a proper termination of the contract for convenience; and
(2). A determination of a just and equitable award pursuant to the above finding. The fact finder is not precluded from using the C.F.R. cost principles, but Ford must prove his claims by a preponderance of the evidence, and the resultant award must be “just and equitable.”
(R. at 307). In response to Ford’s timely Kentucky Rules of Civil Procedure (CR) 59.05 motion, the circuit court issued a subsequent order on May 24, 2010, disqualifying the Cabinet Secretary from deciding the remanded issues because he testified adversely to Ford during the administrative hearing. The Cabinet designated a substitute to serve in the Secretary’s place (Secretary’s Designee).
On remand, by order entered September 27, 2010, the Secretary’s Designee again found Ford’s diversion bid and the need to acquire temporary easements, collectively, constituted a substantial change in circumstances justifying termination of the contract (2010 Final Order). The Secretary’s Designee further found the hearing officer’s damages award of $52,001.26 to be just and equitable, and found it unnecessary to apply the federal cost principles.
Ford took the matter back to the circuit court. By order entered February 21, 2012, the circuit court reversed the 2010 Final Order in part and affirmed in part. The circuit court reversed the Secretary’s Designee’s conclusion that the Department properly terminated the contract for convenience. The Cabinet has not appealed this portion of the circuit court’s order, and it stands. However, the circuit court upheld the Cabinet’s damages award of $52,001.26. Ford promptly appealed.
II. Standard of Review
Ford is correct that judicial review of an administrative decision focuses on arbitrariness. Kaelin v. City of Louisville,
Our review, however, is altered when the agency denies relief to the party saddled with the burden of proof. Bourbon County Bd. of Adjustment v. Currans,
Not infrequently, contestants appear at the judicial level arguing that the administrative decision is not supported by substantial evidence when the board has offered no relief in the first instance. In other words, the board has ruled that the one having the burden of proof— usually the applicant — has failed. In such cases, attention should be directed to the administrative record in search of compelling evidence demonstrating that the denial of the relief sought was arbitrary. The argument should be that the record compels relief. The argument that there is no substantial evidence to support nonrelief is an anomaly.
Id. Evidence is compelling if it is so overwhelming that no reasonable person could fail to reach the same conclusion. Greene v. Paschall Truck Lines,
Furthermore, it is basic horn-book law that the “trier of facts is afforded great latitude in its evaluation of the evidence heard and the credibility of witnesses appearing before it.” Bowling v. Natural Resources and Environmental Protection Cabinet,
Finally, statutory interpretation is an issue of law and, accordingly, we review the circuit court’s statutory construction de novo. See Cumberland Valley Contractors, Inc. v. Bell County Coal Corp.,
III. Analysis
Ford raises three issues: (1) whether the circuit court improperly upheld the hearing officer’s damages award; (2) whether the circuit court erroneously denied Ford’s request for prejudgment interest; and (3) whether the circuit court improperly rejected Ford’s argument that the 2010 Final Order is untimely, null, and void.
A. Damages
Contract damages serve to compensate the injured party. In Kentucky, the general “measure of damages for breach of contract is ‘that sum which will put the injured party into the same position he would have been in had the contract been performed.’ ” Hogan v. Long,
Contract damages must always be proven with reasonable certainty. Pauline’s Chicken Villa, Inc. v. KFC Corp.,
With these principles in mind, we turn to Ford’s claims of error.
(i). Applicability of the Federal Cost Principles
Ford asserts that KRS 45A.215 mandates use of the federal cost principles contained in 48 C.F.R. Part 31 to calculate
This argument is premised almost entirely on this Court first finding that the federal cost principles are, in fact, mandatory and, therefore, must be used to calculate Ford’s damages. For the reasons set forth below, we decline to so rule.
KRS 45A.215 directed the secretary of the Finance and Administration Cabinet to issue regulations “setting forth cost principles which shall be used:”
(1) As guidelines in the negotiation of:
(a) Estimated costs or fixed prices when the absence of open market competition precludes the use of competitive sealed bidding;
(b) Adjustments for state-directed changes or modifications in contract performance; and
(c) Settlements of contracts which have been terminated.
(2) To determine the allowability of incurred costs for the purpose of reimbursing costs under contract provisions which provide for the reimbursement of costs; and
(3) As appropriate in any other situation where the determination of the estimated or the incurred costs of performing contracts may be required.
KRS 45A.215. Pursuant to KRS 45A.215, the Finance and Administration Cabinet promulgated 200 Kentucky Administrative Regulations (KAR) 5:317, which adopted the cost principles set forth in 48 C.F.R. Part 31 to satisfy “the purposes stated in KRS 45A.215.” 200 KAR 5:317 Section 3. Notably, Section 1 of that regulation directs that only “[c]ost reimbursement contracts shall conform to the cost principles set forth in 48 C.F.R. Part 31[.]” 200 KAR 5:317, Section 1.
“All statutes ... shall be liberally construed with a view to promote their objects and carry out the intent of the legislature[.]” KRS 446.080. In construing a statutory provision, we must “look to the letter and spirit of the statute, viewing it as a whole.” Lewis v. Jackson Energy Coop. Corp.,
The Cabinet and, in turn, the circuit court, relied on KRS 45A.215(l)(c) to conclude that the federal cost principles were only to be used as guidelines. Ford claims this was error. We are in technical agreement with Ford.
KRS 45A.215(l)(c) authorizes the discretionary use of the federal cost principles as mere “guidelines” in the settlement of terminated contracts. Here, Ford sought administrative intervention because settlement negotiations had failed. The pursuit of administrative relief under KRS Chapter 13B is unquestionably adversarial, not mediatorial. See KRS 13B.080.
However, we do not agree with Ford that use of federal cost principles is mandatory. KRS 45A.215 directs the compulsory application of federal cost principles in two instances only under subsections (2) and (3). In the first, federal cost principles are to be used “[t]o determine the allowability of incurred costs for the purpose of reimbursing costs under contract provisions which provide for the reimbursement of costs[.]” KRS 45A.215(2). This section of the statute refers to a specific type of contract: cost-reimbursement contracts. See 200 KAR 5:317 Sec
In the second instance, federal cost principles are to be applied “in any other situation where the determination of the estimated or the incurred costs of performing contracts may be required.” KRS 45A.215(3). However, the legislature qualifies this application by stating that the regulations issued by the Cabinet, incorporating the federal cost principles, “shall be used [in these other situations, a]s appropriate[.]” KRS 45A.215(3). Again, construing the statute so that no one part is rendered meaningless, Hardin County Fiscal Court,
The question, then, is when is it appropriate for our courts to deviate from our long-developed jurisprudence for determining breach-of-contract damages by applying federal cost principles. We have been directed to no authority, and offered no rationale for jettisoning this jurisprudence, in favor of federal guidelines designed, initially at least, for a different purpose. Application of the federal cost principles is only appropriate when these time-tested measures, when properly applied, fail to make the non-breaching party whole. That is not this case.
Notably, the hearing officer found that Ford’s estimated costs for fully performing the contract were $224,993.50, yet application of the federal costs principles would have yielded an award of $518,993.50. Considering Ford only partially performed the contract, such an award could only be considered punitive of the Cabinet or a windfall to Ford. We agree with the hearing officer that application of the federal costs principles is neither mandatory nor appropriate in this ease.
The hearing officer found that Ford was entitled to a “just and equitable” award that would put Ford in the same position it would have been had the contract been performed. Hogan,
(ii). Equipment-Related Damages
Ford next argues its idle equipment costs are compensable, and that the circuit court erred in upholding the Cabinet’s order concluding that they were not. We agree with Ford.
Ford alleges that the Department’s indefinite hold on the Project left Ford in limbo, and forced its equipment into a varied and indefinite standstill from May 9, 2006, until receipt of the Department’s cancellation order on July 7, 2006. Ford claims it is entitled to .compensation of $314,109.90 as damages caused by the delay and the need for Ford to keep its equipment idle but on-site, prepared to begin performance upon the Department’s notification.
Ford has not identified, and we have not found, Kentucky law recognizing idle equipment or delay damages as a compen-sable category of damages. It appears to be a matter of first impression. A survey of foreign jurisdictions and relevant secondary literature suggests such damages are often compensable. R.L. Coolsaet
As explained by the Seventh Appellate Circuit, “idle equipment (or equipment which must remain on a job site because the project is delayed) is a real and quantifiable loss to the contractor, whether rent is paid to another or charged to the contractor himself as an accounting expense, and it is recoverable.” R.L. Coolsaet Const. Co.,
It was long the practice in this Commonwealth to include in a contract a “no-damages-for-delay” clause. Kentucky courts adjudged such clauses enforceable. See Humphreys v. J.B. Michael & Co.,
In finding Ford was not entitled to idle equipment damages, the hearing officer noted that, if the contract had been completed, Ford would have used the equipment and not received any compensation relating to that equipment. Thus, “[t]he award for lost profits contemplates that Ford would have used the equipment to earn those profits until at least July 7, 2006, so that an award for any additional use, rent, idleness, etc. of that equipment would improperly place Ford in a better position than if the contract had been completed.” (R. at 75).
The hearing officer found the award of lost profits adequately compensated Ford for its idle equipment costs. We disagree. Had the contract been performed, Ford would have recovered its equipment costs in addition to its profit. Ford should not be burdened with costs it incurred due to the Department’s malfeasance. Again, when a contract is breach
On this issue, we remand. We instruct the circuit court to remit this matter to the Cabinet for additional findings, if needed,
First, Ford is only entitled to compensation for the delay period attributable to the Department. See Cushman, supra, § 219 (explaining idle equipment damages are compensable “for a project delay attributable to the owner”). Here, Ford’s equipment was rendered idle on May 9, 2006, when the Department issued its indefinite hold. On June 10, 2006, the Project Engineer notified Ford that the contract had been cancelled. In our view, the hold was lifted at this time; Ford had sufficient notice that it ho longer needed to dedicate equipment to the Project, and no longer needed to maintain a minimal level of readiness. Accordingly, Ford is only entitled to idle equipment damages for those working days between May 9, 2006, and June 10, 2006.
Second, Ford bears the burden of establishing both: (1) that the equipment claimed was, in fact, actually idle during the delay period; and (2) that the “[equipment was necessary for completion of the contract work[.]” Schwartzkopf, supra, § 3.02. It is certainly conceivable that not all of Ford’s equipment was rendered idle. Likewise, it is possible the equipment rendered idle did not remain so for the duration of the delay period. As a corollary, we note that Ford was also obligated to mitigate its damages. Morgan v. Scott,
Third, we find the'proper measure of damages when equipment is idled to be the equipment’s actual rental value (if rented or leased), or the non-breaching party’s actual cost to own the equipment. See Arcon Const. Co.,
Fourth, Ford’s gross idle equipment damages must be reduced by “50 percent to reflect lack of wear and tear.” White Oak Corp.,
Ford’s equipment-damages claim includes a second component in the claimed amount of $39,032.67. Ford claims it incurred this amount “in operating costs based on Ford’s inability to earn revenue to compensate for equipment usage during the lag between bid time and the hold.” (Appellant’s Brief at 10). Ford is not entitled to reimbursement for these costs. The contract contained no specified start date. Instead, the contract directed the Department to notify Ford, in writing, when it was to commence the contract work. While certainly inconvenient to Ford, Ford was well aware of this contract provision when it signed the contract. We cannot say the “lag” between the bid and start date is a delay attributable to the Cabinet for which Ford should receive idle equipment compensation.
(ii). Substantial Evidence
Ford’s final damages-related argument is simply that its damages were supported by the evidence, and the circuit court erroneously affirmed the Cabinet’s decision not to find in Ford’s favor as to all its claimed damages. This argument is unpersuasive.
First, several categories of Ford’s damages hinged on the testimony of Cammle Ford, which the hearing officer found to be less than credible. In light of this, the hearing officer was certainly permitted to discount or even disregard Cammle Ford’s testimony. Bowling,
Second, Ford’s damages evidence was countered in almost every respect by McGaughey, the Cabinet’s expert witness. Ford attacks McGaughey’s credibility, describing his testimony as inaccurate and the hearing officer’s reliance thereon erroneous. McGaughey was certainly qualified, however, to testify to the costs incurred by Ford. He testified in detail concerning the methods by which he calculated Ford’s supposed damages, and was subject to rigorous cross-examination. The incongruity between Ford’s calculations and McGaughey’s calculations did not render erroneous the hearing officer’s reliance upon McGaughey’s testimony. Ultimately, the hearing officer was faced with conflicting testimony, and had to choose one version as preferable to the other. When the testimony is conflicting, we will not substitute our decision for
Neither Ford nor the Cabinet takes issue with the damages awarded for lost profits, purchased steel, and pre-stress services. Similarly, while Ford initially included bonding costs as a category of damages, it abandoned that claim before the hearing officer. No further discussion of these damages is warranted.
We direct our attention to Ford’s direct, indirect, and labor costs. Cammle Ford testified Ford incurred $22,290.57 in direct and indirect costs,
The hearing officer awarded Ford a total of $2,517.00 for its direct and indirect costs, and labor expenses.
While we certainly sympathize with the hearing officer’s plight in calculating these costs, his $2,517.00 award does not comport with the evidence presented during the hearing, and is therefore not supported by substantial evidence. With respect to these damages, we reverse. On remand, we direct the circuit court to instruct the Cabinet to award Ford direct, indirect, and labor costs in an amount consistent with the evidence presented, taking into consideration the hearing officer’s prior credibility determinations.
With respect to employee living accommodations, material storage, equipment depreciation, stockpiled materials, attorney and expert witness fees, overhead, and unabsorbed overhead, the hearing officer determined Ford failed to provide any rehable evidence as to the appropriate amount of such damages. Simply put, Ford failed to carry its burden of proof. Moreover, McGaughey, for various reasons, assigned a zero damages rating to each of these categories. We have painstakingly reviewed the record, and cannot say it “compels a contrary decision in light of substantial evidence therein.” Currans,
B. Prejudgment Interest
Ford asserts the circuit court’s' erroneous denial of its request for prejudgment interest constitutes reversible error. Ford argues its claim for breach of contract is a liquidated claim, entitling it to prejudgment interest.- In response, the Cabinet argues that the claim is unliquidated.
“[P]rejudgment interest is awarded as a matter of right on a liquidated demand, and is a matter within the discretion of the trial court or jury on unliquidat-ed demands.” 3D Enterprises Contracting Corp. v. Louisville and Jefferson County Metropolitan Sewer District,
A damages claim is liquidated if it is “of such a nature that the amount is capable of ascertainment by mere computation, can be established with reasonable certainty, can be ascertained in accordance with fixed rules of evidence and known standards of value, or can be determined by reference to well-established market values.” 3D Enterprises,
Here, the value of Ford’s underlying breach of contract claim was neither “agreed upon by the parties [nor] fixed by operation of law or the parties.” Nucor Corp.,
Because Ford’s damages are not liquidated, prejudgment interest is a matter of discretion. “When the amount [of damages] is ‘unliquidated,’ the amount of prejudgment interest, if any, is a matter for the trial court weighing the equitable considerations.” University of Louisville
Here, the hearing officer exercised his discretion and found, as a whole, the equities did not warrant an award of prejudgment interest to Ford. The hearing officer reasoned that “[a]ny delay in payment of Ford’s claim is mainly the result of Ford’s unreasonable claim for $553,100.60 which the Department properly refused to pay resulting in this administrative action.” The Cabinet adopted the hearing officer’s findings. On appeal, the circuit court found “that the Cabinet was justified in its denial of a pre-judgment interest award to Ford.” We decline to disturb the circuit court’s decision. On this issue, we find no abuse of discretion.
C. Validity of the 2010 Final Order
Finally, Ford urges us to declare the 2010 Final Order untimely and, therefore, null and void. Ford asserts the Secretary’s Designee was required to issue her order following remand within the 90-day limit fixed by KRS 13B.120(4). We disagree.
KRS 13B.120(4) directs the agency head to “render a final order in an administrative hearing within ninety (90) days after”:
(a) The receipt of the official record of the hearing in which there was no hearing officer submitting a recommended order under KRS 13B.110; or
(b) The hearing officer submits a recommended order to the agency head, unless the matter is remanded to the hearing officer for further proceedings.
KRS 13B.120(4). KRS 13B.120 places no limitation on the agency head to issue a final order within ninety days, or any other designated timeframe, following remand from the circuit court. Regarding this particular situation, KRS Chapter 13B is silent. Of course, nothing prohibits the circuit court from directing an administrative agency to act upon remand within a practical, defined time period to uphold and further the rationale of KRS Chapter 13B. See McKinstry v. Wells,
We agree that an agency head should act as expeditiously as practicable on remand, taking into consideration the complexities of the case and the issues to be decided. See generally United Sign, Ltd. v. Commonwealth,
IV. Conclusion
The February 21, 2012 Opinion and Order of the Franklin Circuit Court is reversed insofar as the court mistakenly upheld the Cabinet’s denial of Ford’s idle equipment damages and direct/indirect/labor costs damages claim. Solely on these issues, we remand for additional proceedings consistent with the guidelines expressed in this opinion. In all other
ALL CONCUR.
Notes
. This is the total cost of $294,000.00 to replace the existing bridge, plus $317,000.00 to construct and remove the temporary diversion bridge.
. Had the Department accepted Ford’s diversion estimate, it would have issued a change order to Ford's existing contract to pay for both the diversion and the original contract.
. Ford labeled this category “Cost of Money.”
. Ford labeled this category "Claims Presentation Costs.”
. McGaughey distinguished between indi-recpoverhead costs which are attributable to a specific contract or project from general administrative/overhead expenses that are not job-specific. Examples of the latter included an office receptionist, office utility bills, paper for the copier, and office supplies.
. While McGaughey did not assign a value to this category, there seems to be no real dispute that Ford is entitled to $4,610.61 for steel purchased for the Project.
. KRS 45A.200(2) requires certain construction contracts to include a clause authorizing the Commonwealth to terminate the contract for convenience.
. KRS 45A.015(2) directs that "[ejvery contract or duty under this code shall impose an obligation of good faith in its performance or enforcement.”
. The hearing officer reached this amount by subtracting Ford's original list costs of performing the contract ($252,174.71) from the total contract price ($294,000.00).
. The other two considerations are: “(1) whether an action was taken in excess of granted powers[; and] (2) whether affected parties were afforded procedural due process[.]” Hilltop,
. Indeed, the hearing officer made a specific factual finding that Ford’s "equipment remained idle and was dedicated to the project while Ford waited for the Cabinet’s decision.” (R. at 64).
. The Cabinet may, at its discretion, again utilize the services of a hearing officer to ascertain any additional needed facts.
. Common rental guidebooks include the Equipment Watch and Rental Rate Blue Book, and the Green Guide published by the Associated Equipment Distributors.
. That particular question is not before this Court. Even if that were an actual controversy requiring our attention, we would necessarily consider all of the circumstances of the case.
. While labeled "direct and distributed costs,” the hearing officer noted in its opinion that this category included direct and "indirect costs allocated to the project” (R. at 60).
. The hearing officer stated its direct-costs award included labor costs. (R. at 80-81).
. Again, the hearing officer pointed out that Ford's $15,907.60 labor claim was almost one-half of the total $30,973.00 labor costs for the entire project.
