22 App. D.C. 253 | D.C. Cir. | 1903
delivered the opinion of the Court:
The plaintiff has assigned three errors, for which he asks the reversal of the judgment:
1. That it was error to take the case from the jury, in view of all the evidence before them.
2. That it was error to hold as matter of law that the architect
3. That the court erred in admitting parol evidence to vary, add to, or modify the terms and provisions of the written contract sued on.
1. With respect to the first assignment of error, we do not perceive that the case is materially changed from what it was when here on the former appeal, so far as the right of the plaintiff to have the case passed upon by the jury is concerned. On the first trial the case was taken from the jury, and that was held by this court to have been error, and the judgment was reversed and the cause remanded for retrial. It is true, the defendant’s evidence contained in the present record was not then before us; but there is nothing in the defendant’s evidence, as now disclosed, that rendered it proper to take the case from the jury on the last trial, any more than on the former trial. On both trials, there was evidence that should have been submitted to the jury.
The learned justice below seems to have been of opinion that the architect had paramount authority over the contract and the work to be done under it, and that he could change and vary the contract and the plans and specifications, of the work as he thought proper; and this appears to have been the opinion of the architect also, as to the extent of his powers. The justice below seems to have thought that because the plaintiff did not proceed with the execution of the work as directed by the architect, before the erection of the exterior walls and putting on the roof, as required by the contract, he can have no right to recover for any delays that may have occurred, in violation of the terms of the contract, no matter how damaging such delays may have been to the plaintiff. That such was the view of the justice. below seems clear from the opinion expressed by him,
Upon such a construction of the contract it would afford the plaintiff, the contractor, little or no protection, and all power would reside in the architect to change and modify the terms of the contract at his will and pleasure. If he can dispense with one provision of the contract, made manifestly for the protection of the contractor, he could dispense with any other material provision, or as many others as he might think proper, and the rights secured by contract would thus become subordinate to the will and pleasure of the architect. This was clearly never contemplated by the contracting parties. Indeed, the very terms of the contract forbid it.
The general or usual powers of an architect are not, by any means, of an unlimited character. Building contracts generally make the architect the agent of the owner in the matter of deciding whether the wmrk done is according to the requirements of the drawings and specifications. But, apart from an agreement to that effect, an architect is not the general agent of the owner, and has no power to change plans of the work, and especially not to the detriment of the contractor. He cannot change the terms of the contract, and either omit or insert provisions that the parties have not agreed to, unless expressly authorized by the parties. The terms of the contract, that the contractor, under the
It follows from what we have said that the judgment appealed from must be reversed, and the cause be remanded that another trial be had; and it is so ordered.
Judgment reversed and cause remanded.