176 Pa. 14 | Pa. | 1896
Opinion by
The real and only question raised on this appeal is whether the learned court below erred in refusing to instruct the jury that the defendant was entitled to a deduction for the clelay caused by the change of the girder. That the defendant suggested to his architect and on consultation with him directed that the change should be made is undisputed, and that the delay for which he seeks compensation was caused by this change is a fact established by the verdict of the jury based on competent and sufficient evidence. The sole ground on which he rests his claim for a deduction for the delay caused by the change is that the order or direction under which the change was made was not in writing. It seems that his contention is that, although he gave the order which caused the delay in the completion of tire building, he is entitled to compensation for
We think the learned court below correctly construed the provision in the contract in reference to compensation for delay in the completion of the building. It was that provision which gave the damages for delay which the defendant claimed he was entitled to recover by way of set-off in this action.
The last sentence in the excerpt from the charge which is the subject of complaint in the second specification of error must be considered in connection with what precedes and follows it, and so considered it furnishes no ground for reversing the judgment.
The specifications of error are overruled and the judgment is affirmed.