Lead Opinion
GRIFFIN, J., delivered the opinion of the court in which STAFFORD, D.J., joined. SUHRHEINRICH, J. (pp. 1010-19), delivered a separate dissenting opinion.
OPINION
Almost seventy years ago, plaintiffs predecessor in interest owned and operated two coal gasification plants in Florida. In 1998 and 2003, plaintiff entered into Administrative Orders by Consent (“AOCs”) with the U.S. Environmental Protection Agency to assess the feasibility of remediation of environmental contamination at those sites. At issue in this case is the narrow legal question of whether those AOCs constitute “administrative settlements” for purposes of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“CERCLA”), 42 U.S.C § 9601 et seq. We hold that they do not. We therefore reverse the district court’s dismissal of plaintiffs contribution action based on the statute of limitations and remand for further proceedings.
I.
This case involves two Florida plants, one in Sanford and the other in Orlando. After discovering hazardous contaminants
Under the terms of the AOCs, plaintiff agreed to conduct and implement a remedial investigation and feasibility study for each site. The remedial investigation was intended to determine the nature and extent of the public safety threat. The feasibility study was designed to identify and evaluate options for remedial action. The AOCs established a plan for implementation and set monetary penalties for violating the plan. Plaintiff also agreed to pay the EPA $429,731.23 for past response costs it had incurred at the Sanford site and $104,751.46 for such costs at the Orlando site. Following completion of the investigation and study at the Sanford site, the EPA entered three Records of Decision — in 2000, 2001, and 2006. On January 16, 2009, the U.S. District Court for the Middle District of Florida approved a consent decree between plaintiff and the EPA for actual performance of remediation at the Sanford site. Regarding the Orlando site, plaintiff submitted a draft Remedial Investigation Report, Risk Assessment, and Remedial Alternative Technical Memorandum that was under review by the EPA at the time of this litigation.
On December 30, 2011, plaintiff filed this cost recovery and contribution CERCLA action in the Middle District of Florida for costs related to both sites. It also sought a declaratory judgment that defendant, as a successor in interest to a former owner-operator of the sites, was liable for future response costs that plaintiff would incur. Upon defendant’s motion, the case was transferred to the Northern District of Ohio. Defendant moved for judgment on the pleadings under Federal Rule of Civil Procedure 12(c) on the basis that the 1998 and 2003 AOCs had triggered CERCLA’s three-year statute of limitations and plaintiffs claims were therefore barred. Initially, the district court denied the motion on the grounds that the Sanford AOC was not a settlement agreement because it did not release any party from any liability and preserved the EPA’s right to sue plaintiff for CERCLA violations. Regarding the Orlando AOC, the court ruled that plaintiff could only bring a cost recovery action because the AOC “by its own terms, was not a settlement agreement.”
However, on reconsideration, following our decision in Hobart Corp. v. Waste Management of Ohio, Inc.,
II.
A.
“The district court’s decision regarding a motion for judgment on the pleadings pursuant to Federal Rule of Civil Procedure 12(c) is analyzed using the same de novo standard of review employed for a motion to dismiss under Rule 12(b)(6).” Tucker v. Middleburg-Legacy Place,
Broadly speaking, CERCLA “facilitates cleanup and remediation of contaminated lands, and shifts the financial burden of such environmental response actions to the parties responsible for releasing hazardous substances.” ITT Indus., Inc. v. BorgWarner, Inc.,
CERCLA provides two express cost-shifting actions for costs incurred in remediating a site. Under the “cost recovery” provision of CERCLA § 107(a)(4), the EPA may bring an action against PRPs to recover “all costs of removal or remedial action incurred by the United States Government.” 42 U.S.C. § 9607(a)(4)(A). A PRP that cleans up a site may likewise bring a cost recovery action against other PRPs. See id. § 9607(a)(4)(B); ITT Indus.,
To proceed with a contribution action, a plaintiff must satisfy one of two statutory conditions. Cooper Indus., Inc. v. Aviall Servs., Inc.,
The effective date of a settlement agreement under CERCLA § 113(f)(3)(B) triggers the running of a three-year statute of limitations for a contribution action. Hobart,
To determine whether the agreement resolves a PRP’s liability, we look to the specific terms of the agreement. Id. at 770. “Whether or not liability is resolved through a settlement simply is not the sort of question which can or should be decided by a universal rule. Instead, it requires a look at the terms of the settlement on a case-by-case basis.” Bernstein,
B.
Plaintiff maintains that the district court erred in concluding that the statute of limitations barred its contribution action because the Sanford and Orlando AOCs do not resolve plaintiffs liability to the EPA. Plaintiff argues that the AOCs closely resemble the agreement in ITT Industries, Inc. v. BorgWarner, Inc.,
In ITT, the plaintiff voluntarily entered into a 2002 “Administrative Order by Consent” with the EPA to perform a remedial investigation and feasibility study on a contaminated site in Michigan.
The Seventh Circuit case, Bernstein, is especially illuminating because it involved two distinct AOCs at different stages of performance. There, the plaintiffs entered into an “Administrative Order by Consent” in 1999 to study removal alternatives at a contaminated site in Indiana and established a trust to reimburse the EPA for past response and oversight costs, as well as future oversight costs.
On appeal, the plaintiffs argued that their claims were correctly pleaded as cost recovery actions. The Seventh Circuit agreed with respect to the 2002 AOC, but not the 1999 AOC: first, it held that the plaintiffs had a time-barred contribution action based on the 1999 AOC because the AOC resolved at least some of the plaintiffs’ liability upon complete performance in 2000 (the date of the EPA’s approval), thereby triggering the statute of limitations. Id. at 978-81. Second, regarding the 2002 AOC, the court held that the statute of limitations had not yet begun to run. Specifically, the court observed that “there can be no meaningful argument” that the 2002 AOC resolved the plaintiffs’ liability because performance was ongoing at the time of litigation and the EPA expressly conditioned its covenants not to sue or take administrative action “upon the complete and satisfactory performance by [plaintiffs] of their obligations under [the AOC].” Id. at 977, 983.
At the defendants’ request, the Bernstein court granted panel rehearing to clarify issues raised by the EPA as amicus curiae with respect to whether parties may structure an administrative settlement with the EPA to immediately resolve liability.
Applying these principles, the Seventh Circuit again held that the 2002 AOC did not resolve the plaintiffs’ liability for two reasons. First, the court observed that the plaintiffs refused to consider the AOC to be an admission of liability, citing a provision of the AOC stating that it “shall not constitute any admission of liability by any (or all) of [the plaintiffs].” Id. at 203-04, 212. Second, “the EPA only conditionally promised to release [the plaintiffs] from liability” upon complete performance of the AOC and certification of such promise. Id. at 212 (emphasis in original). The court reasoned that this conditionality meant that if resolution of liability was intended, it “would not occur until performance was complete, which is the first time at which the covenant would have any effect.” Id. In support of its reading, the court observed that the EPA “expressly reserved its right to seek legal or equitable relief to enforce the terms of the Order at any time before those covenants went into effect.” Id. at 212-13 (internal quotation marks and alterations omitted). In making this observation, the court clarified that, “if the EPA had included an immediately effective promise not to sue as consideration for entering into the agreement, the situation would be different.” Id. at 213. But, in Bernstein, that was not the case. In summary, the Seventh Circuit observed: “The parties to a settlement may choose to structure their contract so that liability is resolved immediately upon execution of the contract. Or, the parties may choose to leave the question of liability open through the inclusion of reservations of rights, conditional covenants, and express disclaimers of liability. In this case, the parties clearly chose to do the latter — a choice which the EPA typically has great weight to influence.” Id. at 213-14 (internal citations omitted).
C.
Like the agreements in ITT and Bernstein, the Sanford and Orlando AOCs do not resolve plaintiffs liability because resolution of liability is conditioned on plaintiffs performance and does not take immediate effect. In both the Sanford and Orlando AOCs, the EPA broadly reserved its “right to take any enforcement action pursuant to CERCLA or any other available legal authority ... for any violation of law or this Consent Order.” This language resembles that of the ITT AOC, which reserved the EPA’s “right to take any other legal or equitable action as it deems appropriate and necessary.” ITT AOC, at 20. It also reflects the AOC in Bernstein, in which the EPA conditionally “covenanted] not to sue [the plaintiffs] for judicial imposition of damages or civil penalties or to take administrative action against [the plaintiffs] for any failure to perform actions agreed to in this Order,” and further, “in consideration and upon [the plaintiffs’] payment of the EPA’s response costs, ... covenanted] not to sue or take administrative action against [the plaintiffs] under Section 107(a) of CERC-LA.”
Moreover, to the extent the Sanford and Orlando AOCs expressly address the resolution of plaintiffs liability, they provide:
*1004 Following satisfaction of the requirements of this Consent Order, [plaintiff] shall have resolved [its] liability to EPA for the performance of the [remedial investigation/feasibility study] that is the subject of this Order. [Plaintiff is] not released from liability, if any, for any actions taken beyond the terms of this Order regarding removals, other operable units, remedial design/remedial action (RD/RA), or activities arising pursuant to section 121(c) of CERCLA.
This language goes a step beyond the conditional covenants not to sue and reservation of rights in ITT and Bernstein to explicitly condition the resolution of liability on performance.
The dissenting opinion suggests that because the parties included any reference to the resolution of liability, wé should infer that they intended to resolve plaintiffs liability. That interpretation, however, ignores the context in which the reference is made. The AOCs do not provide that plaintiff has “resolved its liability to the EPA as of the effective date of this agreement,” but rather state, “Hollowing satisfaction of the requirements of this Consent Order, [plaintiff] shall have resolved [its] liability to the EPA____” The phrase is better interpreted as conditioning the resolution of plaintiffs liability on plaintiffs performance. To conflate these phrases would compromise the meaning of the parties’ chosen language.
As to the admission of liability by plaintiff, the Sanford AOC is silent. The Orlando AOC, however, provides that “participation of [plaintiff] in this Order shall not be considered' an admission of liability.” This provision parallels the non-admission of liability provisions in the ITT and Bernstein AOCs. See ITT,
Our recent case of Hobart Corp. v. Waste Management of Ohio, Inc.,
In Hobart, we went on to identify four “material differences” between the AS-AOC in Hobart and AOC in the ITT case. Id. at 770. First, the title of the agreement in Hobart included the phrase “administrative settlement,” while the ITT agreement did not, which we considered probative of intent. Id. Second, and more substantively, the ASAOC explicitly stated that the plaintiffs’ liability was resolved while the ITT AOC’s analogous paragraph contained “no explicit statement that ITT Industries had resolved its liability.” Id. Third, regarding that same paragraph, the ASAOC contained a reference to the relevant contribution statute, § 113(f)(3)(B), while the analogous paragraph in the ITT AOC did not. Id. Fourth and finally, the government’s covenant not to sue was much broader in the ASAOC than the ITT AOC and took effect immediately, and, at the same time, the government’s reservation of rights and ability to withdraw from the ASAOC was narrower than the ITT AOC. Id. With respect to the Seventh Circuit’s Bernstein case, we observed that it was distinguishable from Hobart because resolution of liability was contingent on performance and was therefore not “definitively settled” upon signing of the AOC in Bernstein. Id. at 771.
Our analysis in Hobart supports our conclusion that the Sanford and Orlando AOCs do not resolve plaintiffs liability and are therefore not administrative settlements. Most compelling is that the “material differences” between the Hobart ASAOC and the ITT AOC likewise separate the Sanford and Orlando AOCs from the Hobart ASAOC. With respect to the title of the agreements, neither the Sanford nor Orlando AOC is titled “administrative settlement” — a phrase that is not found anywhere in either AOC. Regarding the resolution of liability, the instant AOCs expressly condition the resolution of liability on performance of the contract, as opposed to resolving liability on the contract’s effective date. Specifically, the AOCs provide: “[F]ollowing satisfaction of the requirements of this Consent Order, [plaintiff] shall have resolved its liability.” This language is distinguishable from that of the Hobart ASAOC and is more like the conditional language of the Bernstein agreement, which Hobart distinguished for failure to “definitively settle[]” the plaintiffs’ liability.
Defendant’s arguments to the contrary are unconvincing. It is defendant’s position that the AOCs resolved at least some of plaintiffs liability once plaintiff “cut a check” to the EPA for past response costs. We disagree for two simple reasons. First, defendant’s argument does not comport with the language of the AOCs, which conditions the resolution of liability on complete — not partial — performance. The reservation of rights provision, for example, states that plaintiff “shall have resolved [its] liability to EPA” “following satisfaction of the requirements of this Consent Order,” not any single requirement. (Emphasis added.) And the covenants not to sue are “conditioned upon the complete and satisfactory performance [by plaintiff] of [its] obligations under this Order.” Second, we are doubtful that the tendering of a check to the EPA distinguishes this case from the aforementioned cases. In every case, the plaintiffs agreed to reimburse the EPA for past costs incurred. In ITT and Hobart, the parties agreed that “[plaintiffs] shall pay” to the EPA certain specified costs upon receiving a bill from the EPA. ITT AOC, at 15; Hobart ASAOC, ¶ 79. In Bernstein, the AOC included a specific amount: the plaintiff agreed to pay $112,799.53 within 60 days of the effective date of the AOC. Bernstein AOC, at 20. There is no reason to believe that the Bernstein plaintiff failed to tender payment by the deadline or that the ITT plaintiff failed to pay the EPA when it received a bill. And partial performance seems to have made no difference in Bernstein, in which performance of the 2002 AOC was ongoing at the time of litigation. Accordingly, even if defendant’s argument did not contravene the language of the AOCs, we would not conclude that payment of some costs transformed the AOC into an administrative settlement.
Finally, defendant argues that the AOCs are bilateral contracts, characterized by an exchange of mutual promises to do something in the future and enforceable at the time of the exchange, as opposed to the time of performance. The dissenting opinion takes this argument further, arguing that one of our prior cases, RSR Corp. v. Commercial Metals Co.,
In RSR Corp., the plaintiff entered into a judicially approved consent decree in which it agreed to reimburse the EPA for past and future response costs, finance and perform remedial work at a contaminated site, and undertake additional future response actions. Id. at 554. In return, the EPA agreed not to sue or take administrative action against the plaintiff that would impose further liability, and the plaintiff received the right to seek contribution against other PRPs. Id. More than three years later, the plaintiff filed a contribution action against the defendant, which moved to dismiss the action as barred by the statute of limitations. Id. At issue in that case was whether CERCLA’s three-year statute of limitations on contribution actions or six-year limitations period for cost recovery actions governed the judicial consent decree. Id. at 555-56. After a detailed discussion of CERCLA’s statutory framework, we concluded that plaintiffs action was one for contribution governed by a three-year statute of limitations. Id. at 556. Only then did we briefly address RSR’s argument raised in its reply brief that it “could not have resolved its liability to the United States in the consent decree
RSR’s promise of future performance was the very consideration it gave in exchange for the United States’ covenant not to seek further damages. RSR and its co-defendants in other words resolved their liability to the United States by agreeing to assume all liability (vis-a-vis the United States) for future remedial actions. And even if the covenant regarding future response costs did not take effect until the remedial action was complete, the statute of limitations for contribution actions runs from the “entry” of the settlement, 42 U.S.C. § 9613(g)(3)(B), not from the date that each provision of that settlement takes effect.
Id. We thus rejected RSR’s attempt to evade the three-year statute of limitations.
Notably, RSR Corp. did not interpret the various provisions of the consent decree for purposes of determining whether the parties intended to resolve liability by way of the consent decree, as did ITT, Hobart, and Bernstein. In fact, it is far from clear from our opinion that RSR even contested that the parties intended to resolve its liability by way of the consent decree. In RSR Corp., we assumed, “[i]n view of the apportionment of liability for past and future response costs among the United States, RSR and its co-defendants [that] the consent decree was a cost-recovery settlement under § 122(h) as well as a cleanup agreement under § 122(d)(1) [and] [b]ecause the consent decree established RSR’s liability, its contribution action regarding those ‘costs’ accrued on the date of the consent decree (April 12, 1999) and expired three years later.” Id. Only after we observed that the consent decree had resolved liability — without engaging the various provisions of the consent decree— did we reason that “even if the covenant ... did not take effect until the remedial action was complete, the statute of limitations for contribution actions runs from the ‘entry’ of the settlement ..., not from the date that each provision of that settlement takes effect.” Id. To be clear, we do not fault the RSR Corp. court for declining to consider whether the parties intended the consent decree to resolve RSR’s liability, as it appears that the issue was not squarely before the court. Where that leaves us is this:- we have at least two Sixth Circuit cases, ITT and Hobart, and the Seventh Circuit case of Bernstein, that are more applicable than RSR Corp. We thus disagree that RSR Corp. forecloses our resolution of this case.
Since RSR Corp., both the Seventh Circuit in Bernstein and this circuit in Hobart have distinguished the consent decree in RSR Corp. from the contracts at issue in those cases. In Bernstein, the Seventh Circuit concluded that RSR Corp. was distinguishable based on “obvious and dispos-itive differences in the facts”:
In [RSR Corp.], the consent order contained an immediately effective release from liability. In this case, it did not. In fact, far from immediately resolving all liability, our AOC immediately resolved none. So, the consideration in [RSR Corp.] was an immediate release from liability; the consideration in this case was a conditional promise to release from liability if and when performance was completed. Given the nature of the statutory trigger, that distinction clearly warrants a different result.
Bernstein,
The dissenting opinion maintains that the Bernstein and Hobart courts erred in their interpretation of the consent decree in RSR Corp. Specifically, the dissent unearths the underlying 1999 judicial consent decree, not quoted in the RSR Corp. decision, to show that the consent decree was not immediately effective. As a preliminary matter, it is not clear that the Bernstein or Hobart court erred. The covenant not to sue provision in the RSR Corp. consent decree provides:
In consideration of the actions that will be performed and the payments that will be made by the Settling Defendants under the terms of the Consent Decree ... the United States covenants not to sue or to take administrative action against Settling Defendants.... [T]hese covenants not to sue shall take effect upon the receipt by EPA of the payments required.... With respect to future liability, these covenants not to sue shall take effect upon Certification of Completion of Remediation Action by EPA.
RSR Corp. Consent Decree, at 79.
More importantly, even if we assume that the Bernstein and Hobart courts misread the RSR Corp. consent decree, RSR Corp. does not preclude a distinction between immediate and conditional effectiveness because our more recent published decision in Hobart adopts and ratifies this distinction. Regardless of the actual language of the RSR Corp. consent decree, our court’s 2014 decision draws a bright line between cases in which the resolution of liability is immediately effective and when the resolution of liability is subject to what the dissent calls a “condition precedent.” In Hobart, the court distinguished an agreement reading, “The Parties agree that this Settlement Agreement - constitutes an administrative settlement for purposes of Section 113(f)(3)(B) of CERCLA ... pursuant to which [the plaintiffs] have, as of the Effective Date, resolved their liability to the United States for the Work, and Future Response Costs,”
Finally, we acknowledge the dissent’s concerns about the “inconsistency” in our circuit’s analysis of settlement agreements under CERCLA § 113(f). Some historical background helps to explain the development of our case law. In 2005, the EPA revised its model AOCs. See Susan E. Bromm & Bruce S. Gelber, U.S. EPA & U.S. DOJ, Interim Revisions to CERCLA Removal, RI/FS and RD AOC Models to Clarify Contribution Rights and Protection Under Section 113(f) (Aug. 3, 2005). Although defendant asks us to consider the EPA’s memorandum in interpreting the AOCs in this case, our court has already held that the “EPA memorandum is parol evidence, which can be consulted only in certain limited circumstances [and] [t]his situation does not fall within one of those narrow exceptions.” Hobart,
Among those revisions, the EPA retitled its model “Administrative Order on Consent,” as “Administrative Settlement Agreement and Order on Consent,” and referred to the document as a “settlement agreement.” EPA Mem., passim. It also inserted a provision stating that the parties “agree that this Settlement Agreement constitutes an administrative settlement for purposes of Section 113(f)(3)(B) of CERCLA, 42 U.S.C. § 9613(f)(3)(B), pursuant to which [specified PRPs] have, as of the Effective Date, resolved their liability to the United States for the Work, Past Response Costs, and Future Response Costs.” Id. at 5. In Hobart, a case involving a 2006 ASAOC, our court found this modified language significantly probative of an intent to resolve the PRP’s liability.
III.
For these reasons, we reverse the judgment of the district court and remand for
Notes
. United States v. Shane, 3:89-cv-383 (S.D.Ohio) (record entry 436).
Dissenting Opinion
dissenting.
The question before this court is whether the Sanford and Orlando Administrative Orders by Consent (“Sanford/Orlando AOCs”) constitute “administrative settlements” within the meaning of CERCLA— that is, whether they “resolved [plaintiff Progress Energy’s] liability to the United States ... for some or all of a response action or for some or all of the costs of such action....” 42 U.S.C. § 9613(f)(3)(B). Although the Sanford/Orlando AOCs contain several provisions ITT Industries, Inc. v. BorgWarner, Inc.,
I further dissent because many of the factors identified in this Circuit’s case law to determine whether an agreement resolves liability are arbitrary and immaterial.
A. The Import of the AOCs’ “Resolved Their Liability” Language and Exchange of Future Promises for Performance
The majority bases its decision primarily on similarities between the Sanford/Orlando AOCs and the AOCs in ITT and Bernstein v. Bankert,
1. “Resolved Their Liability” Language
The Orlando/Sanford AOCs provide: “Following satisfaction of the requirements of this Consent Order, Respondents shall have resolved their liability to EPA for the performance of the RI/FS that is the subject of this' Order.” “[H]ave resolved their liability” mirrors 42 U.S.C. § 9613(f)(3)(B), which entitles a “person who has resolved its liability to the United States ... in an administrative or judicially approved settlement” to a contribution action. This inclusion of 42 U.S.C. § 9613(f)(3)(B)’s language distinguishes the Sanford/Orlando AOCs from the
The AOCs’ reference to the' § 9613(f)(3)(B) language not only separates them from the ITT/Bernstein agreements but also reflects an intent to enter into an administrative settlement with all its attendant statutory consequences. Although the language resolving liability in the Hobart ASAOC differs in verb tense from the language resolving liability in the Sanford/Orlando AOCs, they share a deliberate reference to the statutory language entitling a settling potentially responsible party (“PRP”) to a contribution action. According to Hobart, such a deliberate reference to the statute manifests an intent to form an administrative settlement. See Hobart, 758 F.3d at 768-69. Both the Hobart court and the majority lend weight to the Hobart ASAOC’s inclusion of “administrative settlement” in its title as well as its acknowledgement of itself as “an administrative settlement for purposes of Section 113(f)(3)(B) of CERCLA.” See id. at 768-69; Hobart ASOAC, at 31; Maj. Op. at 1004-05. These aspects of the AS-AOC are significant not because they satisfy any technical requirement but rather because they demonstrate the parties’ awareness of the governing statute and an intent to align their agreement with the statutory framework. See Hobart,
2. RSR Corp.’s Binding Precedent Regarding the Exchange of Promises for Future Performance and a Conditional Covenant Not to Sue
The majority acknowledges that the Sanford/Orlando AOCs contain language indicating Progress Energy “shall have resolved their liability,” but reasons that the language does not in fact resolve Progress Energy’s liability since the resolution is conditioned upon Progress Energy’s performance. Maj. Op. at 1004. As the opinion further points out, the EPA’s covenants not to sue in the Sanford/Orlando AOCs take effect only upon Progress Energy’s payment of past and future response costs and upon issuance of the EPA’s notice of completion verifying Progress Energy’s performance of the work addressed in the consent order. Maj. Op. at 1005-06. The analysis contrasts these conditional provisions with the immediately effective resolution of liability and covenant not to sue in the Hobart ASAOC. Maj. Op. at 1005-06. The problem, however, is that the earlier-decided RSR Corp. precludes this distinction between immediate and conditional effectiveness as a basis for determining whether an agreement has resolved a PRP’s liability. See Darrah v. City of Oak Park,
In RSR Corp., the plaintiff filed a CERCLA contribution suit more than three years after entering into a judicially approved consent decree with the United States. RSR Corp.,
[T]he United States covenants not to sue or to take administrative action against Settling Defendants pursuant to Sections 106 and 107(a) of CERCLA.... Except with respect to future liability, these covenants not to sue shall take effect upon the receipt by EPA of payments required by Paragraph 49 of Section XVI (Reimbursement of Response Costs). With respect to future liability, these covenants not to sue shall take effect upon Certification of Completion of Remedial Action by EPA.
RSR Consent Decree, at 79.
RSR argued that the consent decree was not a judicially approved settlement because RSR could not have resolved its liability before completing the remedial action that triggered the EPA’s covenant not to sue for future liability. RSR Corp.,
RSR insists that it could not have resolved its liability to the United States in the consent decree before the completion of the remedial action. But RSR’s promise of future performance was the very consideration it gave in exchange for the United States’ covenant not to seek further damages. RSR and its co-defendants resolved their liability to the United States by agreeing to assume all liability (vis-a-vis the United States) for future remedial actions. And even if the covenant regarding future response costs did not take effect until the remedial action was complete, the statute of limitations for contribution actions runs from the “entry” of the settlement, 42 U.S.C. § 9613(g)(3)(B), not from the date that each provision of that settlement takes effect.
Id. (internal citation omitted). Ultimately, the court held the consent decree consti
The contractual exchange in the RSR Corp. consent decree closely resembles the mutual promises in the Sanford/Orlando AOCs, including the EPA’s conditional covenant not to sue. Like RSR, Progress Energy made several promises under each AOC: to conduct and implement an RI/FS for each site, to pay the EPA for past response costs incurred at each site, and to reimburse the EPA for future response costs incurred in overseeing the RI/FS’s implementation. In return, the EPA promised in both RSR Corp. and this case not to sue the settling PRP for recovery of these costs or to compel further work of the sort described in the agreement, but only once the EPA received the promised funds and certified completion of the agreed-upon work. RSR Corp., 496 F.Bd at 554; RSR Consent Decree, at 79. Because the RSR Corp. court found that the contingent nature of the EPA’s promise did not preclude the resolution of RSR’s liability, neither should this panel decide that the conditional nature of the EPA’s promise not to sue in the Sanford/Orlando AOCs undercuts their status as administrative settlements. Under RSR Corp.’s logic, Progress Energy’s promise to undertake future stages of the clean-up process in exchange for the EPA’s conditional covenant not to sue established a binding contract that immediately resolved Progress Energy’s liability.
The majority rejects this reading of RSR Corp. by implying that the passage addressing the resolution of liability is non-binding, stating, “it is far from clear from our opinion that RSR even contested that the parties intended to resolve liability.” Maj. Op. at 1007. The opinion, in fact, directly recognized the issue as disputed: “RSR insists that is could not have resolved its liability to the United States in the consent decree.... ” RSR Corp.,
In fact, as shown above, the RSR covenant not to sue was not immediately effective, but rather conditioned upon the settling defendants’ payment to the EPA and the EPA’s certification of completion of the work — just like the covenants not to sue in this case. Yet the RSR Corp. court did not view this conditional covenant not to sue as a barrier to resolving liability under 42 U.S.C. § 9613(f)(3)(B). To the contrary, the court addressed the argument presented by Progress Energy — that liability cannot be resolved under a conditional covenant not to sue until complete performance — and rejected it on the grounds that such an interpretation is inconsistent with contractual principles and with setting the statute of limitations from the date of entry of a judicially approved settlement (or, as in this case, from the date of an administrative settlement). See RSR Corp.,
Despite this clear statement of law, the majority clings to the distinction between immediate and conditional effectiveness as a standard for determining the resolution of liability because “our more recent published decision in Hobart adopts and rati-
The law in our Circuit on whether an agreement “resolves liability” under 42 U.S.C. § 9613(f)(3)(B) is so muddled that it is unsurprising this case engendered disagreement among the panel. I agree with the majority that Hobart draws a distinction between immediate and conditional covenants not to sue, but I am persuaded this Court’s earlier decision in RSR Corp. bars that line of reasoning. Therefore, because the Sanford/Orlando AOCs explicitly state that Progress Energy “shall have resolved their liability to the EPA” and include a bilateral exchange of promises for future performance, I would affirm the district court’s holding that the Sanford/Orlando AOCs resolved Progress Energy’s liability and triggered the statute of limitations for its contribution action.
B. Our Case Law’s Contradictory Stance on Provisions in CERCLA Settlement Agreements
Athough I believe the Sanford/Orlando AOCs are administrative settlements because of their key similarities with the Hobart and RSR Corp. agreements, the majority applied several factors consistently with this Circuit’s case law in determining the Sanford/Orlando AOCs did not resolve Progress Energy’s liability. Specifically, the majority analysis points to three similarities between the ITT/Bernstein AOCs and the Sanford/Orlando AOCs: 1) a broad reservation of rights by the EPA, 2) non-admission of liability by the settling PRP, and 3) a conditional covenant not to sue by the EPA. Both ITT and Hobart recognized these terms as signs of an intent not to resolve liability, warranting reliance on them in this case.
1. Reservation of Rights
Analogizing the Sanford/Orlando AOCs to the ITT/Bernstein AOCs based on the EPA’s broad reservation of rights falls squarely within this Court’s analytical approach. The ITT court highlighted the ITT AOC’s broad reservation of rights in holding that the AOC did not resolve liability. ITT,
It is unclear, however, why a broad reservation of rights by the EPA impacts resolution of a PRP’s liability. The reser
Moreover, relying on a reservation of rights to find unresolved liability is in tension with the outcome in Hobart. Although not addressed in Hobart’s published opinion and thus not binding on this Court, it is noteworthy that the Hobart ASAOC
2. Non-Admission of Liability
Both ITT and Bernstein emphasized a non-admission of liability by the PRP as a reason the respective AOCs did not resolve liability. Bernstein,
It is questionable, however, that a refusal to admit liability denotes unresolved liability. Admitting liability is not the same as resolving liability. Compare Admission, Black’s Law Dictionary (10th ed.2014), available at Thomson Reuters Westlaw (“a statement in which someone admits that something is true or that he
Moreover, using a non-admission of liability to hold the Orlando AOC is not an administrative settlement cuts against the results in RSR Corp. and Hobart. Although not discussed in either published opinion, the agreements in both those eases contained a non-admission of liability, Hobart ASAOC, at 1; RSR Consent Decree, at 3, yet both agreements resolved liability. Whatever the reason for the court’s silence (possibly because the parties failed to bring the term to the court’s attention or because the court considered it immaterial), the omission demonstrates an uneven application of this factor to settlement agreements brought before this Court. This inconsistency should lead the Court to reexamine the use of this factor in determining whether agreements are administrative settlements.
3. Conditional Covenant Not to Sue
Reliance on the Sanford/Orlando AOCs’ conditional covenant not to sue to show unresolved liability accurately follows Hobart, which distinguished the ASAOC at issue in that case with the ITT AOC by noting “the covenant not to sue took effect immediately in this case,” whereas the ITT AOC “required] payment first.” Hobart,
A condition is a contractual concept that “triggers or negates a duty to render a promised performance.” Condition, Black’s Law Dictionary (10th ed.2014), available at Thomson Reuters Westlaw. A condition is precedent where an obligation does not take effect until the condition occurs. Condition, Black’s Law Dictionary (10th ed.2014), available at Thomson Reuters Westlaw. In the CERCLA settlement context, where a PRP’s obligations are a condition precedent to the EPA’s covenant not to sue, the EPA has “the right to sue up until the point when the PRP completed its obligations.” NCR Corp. v. George A. Whiting Paper,
That being said, it is doubtful whether the two types of conditions actually differ in terms of “resolving liability” under 42 U.S.C. § 9613(f)(3)(B). The permanent effectiveness of both covenants not to sue depends upon the PRP’s complete and satisfactory performance. Therefore, both covenants not to sue remain uncertain because of the contingency of complete performance.
Conclusion
I would affirm the decision of the district court because the Sanford/Orlando AOCs resemble the agreements in RSR Corp. and Hobart in demonstrating the parties’ intent to enter into an administrative settlement, thereby triggering the three-year statute of limitations for Progress Energy’s contribution action.
. Hobart dealt with an administrative settlement, whereas RSR Corp. addressed a judicially approved settlement. Both administrative settlements and judicially approved settlements must "resolve [a potentially responsible party ("PRP”)’s] liability to the United States” to entitle the PRP to a contribution action. 42 U.S.C. § 9613(f)(3)(B).
. The RSR Corp. Consent Decree is available on the Southern District of Ohio’s electronic docket. The case number is 3:89-cv-383, and the consent decree may be found at R.436. Although not on the record in this case, I would take judicial notice of the RSR Corp. Consent Decree as part of the public record of a different case. See Scotty’s Contracting & Stone, Inc. v. United States,
. Just because this argument was one of several raised by RSR does not mean the issue “was not squarely before the court” or otherwise inconsequential. Maj. Op. at 1007.
. Even if the majority is correct that RSR Corp.’s statement on resolution of liability via an exchange of promises is non-binding or otherwise inapplicable, I would still dissent at least in part. RSR Corp. held that “the statute of limitations runs from the 'entry of the settlement,' 42 U.S.C. § 9613(g)(3)(B), not from the date that each provision of the settlement takes effect.” RSR Corp., 496 at 558. In other words, even if the RSR Corp. court accepted the argument that RSR did not resolve its liability until it completed performance, it still would have ruled RSR’s contribution action time-barred because the statute of limitations runs from the date of entry regardless of when the PRP resolves liability. According to this rule, Progress Energy’s contribution action for costs arising under the Sanford AOC is time-barred. Progress Ener
. The majority expresses doubt that Bernstein in fact misinterpreted RSR Corp. In its view, Bernstein drew a reasonable distinction between RSR Corp., where the "parties 'immediately resolv[ed] liability’ based on promises of future action,” and Bernstein, where the parties entered into " ‘a conditional promise to release from liability if and when performance was completed.' ” Maj. Op. at 1008. This analysis rests on the proverbial distinction without a difference. It stretches logic to treat mutual promises of future performance as dispositive in one case (RSR Corp.) but ignore them in another (Bernstein) because of a conditional promise of released liability that was actually present in both cases.
. I maintain that both Hobart's and the majority’s treatment of the conditional covenant not to sue as a sign of unresolved liability contravenes the earlier-decided, binding RSR Corp. But even assuming the majority’s view of the conditional covenant not to sue did not misinterpret RSR Corp., I believe that this Circuit's distinction between Hobart’s immediately effective covenant not to sue versus conditional covenants not to sue is not aligned with the statutory language and has not been consistently applied.
. As with the RSR Corp. Consent Decree, I would take judicial notice of the Hobart AS-AOC as part of the public record in a different case that is not reasonably subject to dispute. See Scotty's,
. The majority excludes the Sanford AOC from this comparison because. the Sanford AOC is silent as to admission of liability by Progress Energy.
. Even this difference, however, wanes in importance under the limitation of the contractual duty of good faith and fair dealing, which a party violates by interfering with or failing to cooperate in the other party's performance. Restatement (Second) of Contracts § 205. As long as a PRP is making reasonable and good faith steps towards complete performance, the EPA bringing suit in the middle of performance would likely be a deliberate interference with the PRP’s ability to fulfill the condition precedent (i.e. its complete performance). In such a scenario, the EPA could not rely on the failed condition precedent to avoid its contractual obligation not to sue. See 7A Am.Jur.2d Contracts § 687.
. Even if the EPA’s covenant not to sue contained no condition at all, the EPA could still sue a PRP for breach of contract if the PRP failed to perform its obligations under the settlement agreement. The damages in such an action would theoretically not be significantly different from an action brought directly under CERCLA. Thus, even a unconditional covenant not to sue arguably resolves liability to the same extent as a fully conditional covenant not to sue, since both terms still allow the EPA to sue (for different causes of action) in the event of non-performance.
