19 F. 731 | U.S. Circuit Court for the District of Eastern Louisiana | 1884
Under the terms of the contract sued on in this case, the defendant is to pay the plaintiffs for work done, upon certificates and estimates of the defendant’s chief engineer for the time being. “The chief engineer for the time being” is the creature of the company. Practically, then, under the terms of the contract, the obligation of the defendant to pay the plaintiffs for work done does not arise until the defendant is satisfied that the plaintiffs are entitled to compensation. The question in this case is whether the defendant, under its contract, may avail itself of the labor performed by plaintiffs, and then may “wrongfully, arbitrarily, unreasonably, and in bad faith” stand upon the literal terms of the contract and refuse to pay. The decisions are to the effect that, “in the absence of fraud, or such gross mistake as would necessarily imply bad faith, ora failure to exercise an honest judgment, Ms (the umpire’s) action in the premises is conclusive.” 97 U. S. 402; Sweeney v. U. S. 3 Sup. Ct. Rep. 344. In this case “fraud” is not specifically charged, but “bad faith” and “a failure to exercise an honest judgment” are. And it seems to me, with the relation between the umpire and the defend
The exception that plaintiffs cannot demand further payment from the company without showing that all laborers, subcontractors, and material-men have been paid, and that no liens are recorded against the company, does not seem to be well taken. The suit is for damages in a large sum, as well as for balance due under the contract. The petition alleges that what, if anything, is due to such laborers, etc., is primarily due from the company, and plaintiffs reserve their rights to sue for it, if they are compelled to pay. Any rights the defendant may have in this regard may be brought in defense.
The exception will be overruled \ and it is ordered.