11 Mo. App. 483 | Mo. Ct. App. | 1882
delivered the opinion of the court.
This action was begun before a justice of the peace for a balance claimed to be due for painting and glazing defendant’s house, under a written contract. The amount claimed was $5.30. On appeal and trial anew in the circuit court .the judgment was for plaintiff's.
1877.
Sept. 22. To painting, graining, and glazing residence,
as per contract.........$682 00
Oct. 31. Extra work, painting on wire fence ... 3 30
$685 30
Sept. 13. By cash on account.....$400 00
Sept. 28. By cash on account..... 250 00
Nov. 30. By allowance ...... 30 00 — 680 00
Balance due....... .. $5 30
Defendant filed before the justice, as a counter-claim, the following account: —
“For omitting to paint and glaze two windows in defendant’s house, which, by your contract, you were required to paint and glaze........$14 00 ”
There is a great conflict of testimony.
Plaintiffs entered into a contract to paint and glaze defendant’s house according to plans and specifications, for $682. Beinke was the architect and superintendent employed by defendant in the erection of the house. Plaintiffs received several payments on account, on the orders of Beinke. Two windows were, in building the house, omitted from the original plan. When plaintiffs, having, as they claimed, completed the work, presented their final bill to Beinke for approval, Beinke insisted that the windows omitted from the house must be deducted. There was evidence on the part of defendants that it was a custom of the trade not to charge for work omitted, during the progress of the building, from the original plan. The painting and glazing of the windows would have been $14. The bill as presented showed a balance due of $35.30. Flesh claimed that he had done extra work and, according to his
The court gave the following instructions at the instance of plaintiffs: —
“ 1. If the jury believe from the evidence that plaintiffs were at all times ready to paint and glaze the two windows mentioned in defendant’s counter-claim, but that they did not or could not paint or glaze the same, because said windows were altogether left out of the building by the defendant himself, or his .architect and builders, without any fault on part of plaintiffs, then defendant cannot recover on his counter-claim.
“ 2. If the jury believe from the evidence that plaintiffs did extra work upon the house of defendant not charged for in the account sued on, that after the completion of the work plaintiffs and the superintendent and architect of defendant agreed that plaintiffs would make no extra charge for such extra work, in consideration whereof defendant would make no deduction on account of the two windows which were not painted and glazed, then defendant' is not entitled to recover on his counter-claim.
“ 3. If the jury believe from the evidence that plaintiffs did the work embraced in the account sued on, that the balance claimed on account of the original contract still remains unpaid, and that the painting of the wire fence is*487 reasonably worth the amount charged therefor, then the jury will find for plaintiffs in the amount claimed in their account, with interest from October 4, 1878.”
For defendant the court gave the following instructions :
“1. If the jury finds and believes from the evidence that by agreement between plaintiffs and defendant the painting and glazing of two windows included in the contract as part of the work to be done by said plaintiffs on defendant’s house were omitted, and if the jury further finds that the reasonable value of said work and materials so omitted was to be deducted from the contract-price, then in arriving at a verdict the jury must give the defendant credit against plaintiffs for the value of said work and materials, and if said value exceeds the sum of $5.30, the jury should find for the defendant.
“ 2. If the jury finds from the evidence that there was a custom m relation to omitted work, as indicated in the other instructions of the court, and that two windows were omitted from the house which were included in the contract between plaintiffs and defendant, then the jury should find for the defendant on his counter-claim such sum as they may find from the evidence was the reasonable value of such two windows.
“ 3. -The court instructs the jury, that if the jury believes from the evidence that at the time of the making of the contract for the painting and glazing of defendant’s house there was a general and well-understood custom and rule among builders, architects, and painters, that the value of work included in the contract but omitted in the erection or finishing of a house is to be deducted from the contract-price of said work, then such custom and rule enters into and forms a part of the contract between the parties, with the same effect as if the same were inserted specifically therein.”
A judgment was rendered by the justice; but it was merely a judgment for costs, and not a final judgment from,.
If, as appellant contends, the statement filed by respondent was really the statement of a counter-claim, not of the nature of recoupment or set-off, and, for this reason, the justice had no jurisdiction over it, then it is immaterial that there was no special finding as to it. But it is quite immaterial what it is called. The question is, what this counter-statement really was. It is evident that it applies to the very affair from which the principal demand arose, and is in the nature of a recoupment. It cuts back on plaintiff’s claim. Plaintiff says: You owe me a balance of $2 on this contract, because I have done all the work according to contract: the contract-price was $682, and you have paid me only $680. No, says defendant; I have paid you $680 ; but I have overpaid you, because two windows, which by contract you were to paint, were omitted from the building. It was worth $14 to paint them, and, by the custom of the trade, I was entitled to retain this much from the contract-price. You really, therefore, owe me on the transaction, not I you. This is not setting up a liquidated indebtedness growing out of an independent transaction that would be a set-off. Both set-off and recoupment come under the general denomination of counter-claim, which is but a name given to the way in which the right of set-off and re
It would have been better for the litigants'and the public if the law were so that no appeal would lie from the decision of the circuit court in a case like this. It has been tried four times, and has been twice in this court. The amount in controversy is $5 ; the cost of these trials, if we include the time of all the officers of the several courts, and the delay of public business, must have been several hundred dollars. The question now becomes important to the parties in a money point of view, because the costs which must fall upon the losing party, must now be very heavy. We believe that the learned and reputable counsel who represent the litigants regret the protraction of the litigation. The case may serve at least as a warning to the litigants themselves and to others. We are asked to put an end to the matter here. But this is impossible. Believing, after careful consideration, that error prejudicial to
The judgment is reversed and the cause is remanded..