delivered the opinion of the Court.
The United States brought this suit on behalf of George S. Hallenbeck to recover upon a bond given by Fleisher Engineering & Construction Company and Joseph A. Bass, with their sureties, and providing for the payment for labor and material furnished under a contract between the principals on the bond and the -United States for the construction of a certain housing project. Part of the labor required by the contract was performed by Hal-lenbeck for a subcontractor with the approval of the contractors. The suit was brought under the Miller Act of August 24, 1935, 40 U. S. C. 270b. Plaintiff obtained a summary judgment (
The applicable provision of the Miller Act is set forth in the margin.
1
The question is whether the giving of
In construing the earlier Act, the Heard Act, for which the Miller Act is a substitute, we observed that it was intended to be highly remedial and should be construed liberally.
United States for the use of Alexander Bryant Co.
v.
New York Steam Fitting Co.,
In the instant case, we may lay on one side the fact that the notice was addressed to the project engineer. As the court below said, it was admitted that the notice, was in writing and was sent by mail and that it reached one of the two contractors who had jointly and severally agreed to perform the contract. 'And at this bar, the' actual receipt of the notice and the sufficiency of its statements have not been challenged.
'In-giving the statute a reasonable construction in order •to. effect fits remedial purpose, we think that a distinction ^should be drawn between the provision explicitly stating the condition precedent to the right to sue and the provision as tó' the manner of serving notice. The structure of the statute indicates the distinction. The proviso^.which defines the condition precedent to suit, states that tl\e material-man or laborer “shall have a
In this view we conclude that the Circuit Court of Appeals correctly disposed of the case and its judgment is
Affirmed.
Notes
Section 2 of the Act of August 24, 1935, c. 642, 49 Stat. 794, 40 U. S. C., § 270b, provides:
“(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid'in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for "the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for' the sum or sums justly due him: Pro•vided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or •implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating-with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered mail, postage, prepaid, in an envelop addressed to the contractor at any place he maintains an office or conducts his business, or his residence, or in any manner in which the United States marshal of the district in which the public improvement is situated is authorized by law to serve summons.”