Flater v. GraceFlater v. Grace
Opinion
Thе defendant, Kevin M. Grace, individually and doing business as Grace Builders,
1
appeals from the trial court’s decision denying his motion to open the judgment awarding the plaintiffs, Michael Flater and Tracy Flater, $92,831 in damages for the defendant’s
failure to complete and perform satisfactorily a home improvement contract. The essence of the
The record reveals the following undisputed facts and procedural history. On September 29, 2006, the plaintiffs filed a four count complaint against the defendant alleging: breach of contract; unjust enrichment; breach of the duty of good faith and fair dealing; and a violation of the Connecticut Unfair Trаde Practices Act (CUTPA),
The plaintiffs sought compensatory damages and court costs, as well as punitive damages and attorney’s fees on the CUTPA count. The only count in their complaint that referred to specific damages was the CUTPA count, which alleged “damages, including but not limited to the expenditure of an additional [$7075] to rectify the said breaches of contract.” The statement of damages filed with the complaint sought damages “in excess of $15,000 . . . .” The defendant filed an appearance on November 16, 2006, but thereafter never filed a responsive pleading.
On January 10, 2007, the plaintiffs filed a motion for default for the defendant’s failure to plead. On January 19, 2007, the clerk’s office entered a default. On May 3, 2007, the plaintiffs filed a motion for judgment on the default and for an order of payments. See
On May 7, 2007, pursuant to
On July 7, 2007, after unsuccessfully seeking to set aside the default because judgment already had entered; see
Thereafter, the trial court,
Elgo, J.,
conducted a hearing on the motion to open, which was attended by both parties. At that hearing, thе defendant argued that he had not defended against the action because he had accepted the notion that it was fair to pay the plaintiffs the $7025 that had been estimated to complete the project, but that he had obtained counsel once
The trial court made no findings at the hearing and thereafter issued an order summarily sustaining the plaintiffs’ written objection to the motion to open the judgment. The defendant did not seek an articulation of the basis of the trial court’s decision. He did file a motion for reconsideration, alleging, inter aha, that new grounds had come to light, namely, that the plaintiffs’ counsel either intentionally or negligently had misled the defendant as to the extent of the plaintiffs’ claim. The trial court summarily denied the motion.
The defendant appealed from the trial court’s judgment to the Appellate Court, and we thereafter transferred the appeal to this court pursuant to
In response, the plaintiffs contend that the defendant has raised claims on appeal that were not raised at the hearing on the motion to open and thus he is not entitled
to a review of those claims. The plaintiffs further contend that the trial court did not abuse its discretion, and the equities do not weigh in favor of the defendant. When questionеd at oral argument before this court, the plaintiffs conceded that the damages award was incorrect with respect to the counts relating to breach of contract; see footnote 3 of this opinion; because the plaintiffs essentially were getting the completed project at no cost to themselves. The plaintiffs contended, however, that this court nonetheless should affirm the judgment because: (1) that issue goes to the merits of Judge Graham’s decision in the underlying judgment, which properly cannot be considered in this court’s review оf Judge Elgo’s denial of the defendant’s motion to open; (2) the damages award is not excessive because double damages would have been justified on the CUTPA count had they further pursued them;
4
and (3) the defendant
The principles guiding our review are well settled. Except in cases in which a judgment has been obtained by fraud, duress or mutual mistake or, under certain circumstances, where newly discovered evidence exists to challengе the judgment, the power of a court to open a judgment after a default has entered is controlled by
statute.
Chapman Lumber, Inc.
v.
Tager,
“We do not undertake a plenary review of the merits of a decision of the trial court to grant or to deny a motion to open a judgment. The only issue on appeal is whether the trial court has acted unreasonably and in clear abuse of its discretion. ... In determining whethеr the trial court abused its discretion, this court must make every reasonable presumption in favor of its action.” (Internal quotation marks omitted.)
Chapman Lumber, Inc.
v.
Tager,
supra,
“When a motion to open is filed more than twenty days after the judgment [as in the present case], the appeal from the denial of that motion can test only whether the trial court abused its discretion in failing to open the judgment and not the propriety of the merits of the underlying judgment. . . . This is so because otherwise the same issues that could have been resolved if timely raised would nevertheless be resolved, which wоuld, in effect, extend the time to appeal.” (Citation omitted; internal quotation marks
omitted.)
Tiber Holding Corp.
v.
Greenberg,
Because, as a general matter, the defendant is not entitled to appellate review of claims that were not raised in the trial court or on which there is an inadequate record;
Smith
v.
Andrews,
Turning to the defendant’s first claim, it is apparent, in light of this record, that the defendant did not raise a claim of fraud, deceit or trickery in the proceedings on the motion to open. There is no hint of an argument that the plaintiffs intended to induce the defendant not to attend the hearing in damages by submitting an intentionally understated estimate, let alone the evidentiary
support necessary to prevail on such a claim.
8
See
Weinstein
v.
Turning to the defendant’s miscalculation of damages claim, it does not appear that the specific claim raised on appeal is the one raised at the hearing on the motion tо open the judgment. The claim on appeal is that, in the underlying judgment, Judge Graham improperly awarded both the full amount to complete the project ($66,600) and the money paid to the defendant ($26,231), and that, even if the work performed was of no value, the proper measure of damages should have been the $26,231 plus the cost to restore the property to its original condition. The claim that the defendant made at the hearing, however, was that good cause existed to defend against the claim on the ground of mistake in the calculatiоn of damages because only $7025, the amount of the estimate to complete the proj ect, was owed, rather than that amount plus the $26,231 that had been paid to him for the work performed. The defendant never challenged the award of $66,600 in damages as it related to the cost of replacement; he never contended that cost of replacement, along with reimbursement of money paid, was an improper measure of damages. The defendant expressly claimed that he had no idea what the total damages amоunt was based on and sought the right to defend against it at a new hearing in damages.
The defendant’s claim on appeal is further compromised by his failure to obtain a written decision from the trial court. See
We are mindful that there undoubtedly was a miscalculation of damages on at least two of the four counts. For purposes of our review under the abuse of discretion standard, however, the good cause showing necessary to open the judgment cannot rely on the merits of the underlying judgment.
Tiber Holding Corp.
v.
Greenberg,
supra,
Accordingly, we turn to the defendant’s claim that, even if the trial court did not abuse its discretion, equitable considerations counsel in favor of opening the judgment. This court has invoked its common-law authority to open a judgment outside the terms of
The judgment is affirmed.
In this opinion the other justices concurred.
Notes
In this opinion we refer to Grace in both his individual and business capacity as the defendant.
There appears to be a scrivener’s error in the affidavit, which reflects an estimate of $7025, rather than the $7075 noted in the builder’s estimate.
The court awarded $92,831 in damages on each of the three counts alleging breach of contract, breach of the duty of good faith and fair dealing, and violation of CUTPA, and $26,231 on the count alleging unjust enrichment. The court noted that the damages would be added together. Although the court did not specify the basis of the $92,831 award, that amount is equal to the lesser of the two estimates for replacement, $66,600, plus the amount the plaintiffs had paid to the defendant under the contracts, $26,231.
We note that, although the plaintiffs clearly sought punitive damages for the CUTPA violation in both their complaint and the order of payment, the record does not reflect the express findings from Judge Graham necessary to supрort such damages. See
Gargano
v.
Heyman,
Among the corrective measures that the plaintiffs identify are a motion for remittitur and a motion to set aside the judgment.
The defendant refers to the fund created under the Connecticut Home Improvement Act,
The defendant’s counsel explained: “[I]n the affidavit of debt . . . [the plaintiffs] list as elements of damages both the $26,000 that [the defendant] was paid plus the $7000 that it would cost to finish the project. Well, those two don’t go together. They received $26,000, or they paid $26,000; he did some of that work. He did all but $7000 of that work. So their damage is not the $26,000 plus the [$7000], Their damages are the [$7000] plus attorney’s fees and whatever elements of damages. But—so there’s a mistake right there in the calculation in the amount of damages, and that’s defensible.”
Because this claim impugns the reputation of the plaintiffs’ counsel, we further note that the record is replete with evidence that the plaintiffs were seeking damages well in excess of $7025, such as the statement of damages filed with the complaint, the request for punitive damages and the order of payment filed with the motion for judgment on the default. Moreover, the plaintiffs consistently alleged that, in addition to the cost of completing the project, work defectively performed by the defendant might need to be replaced. Michael Mater’s affidavit of debt specifically alleged that this option might need to be pursued and put the defendant on notice that the plaintiffs were seeking additional estimates. Hаd the defendant attended the hearing in damages, he would have heard the plaintiffs’ credible explanation that those estimates had revealed an increased cost of performance due to the need to replace the defectively constructed structure in its entirety, rather than repair it.
Even if the trial court had understood the defendant’s claim more broadly to contend that the plaintiffs were not entitled to both reimbursement of the payments they had made to the defendant and the cost of completing the projeсt, whatever that cost of completion was, the court nonetheless could have concluded that the defendant lacked reasonable cause for failing to assert that defense. Specifically, the plaintiffs’ order of payment, filed with the motion for judgment, expressly had sought damages for both the money paid to the defendant and the money due on the contract to complete the project, which put the defendant on notice of that defense.
“In an action for breach of contract, the general rule is that the award of damages is designed to place the injured party, so far as can be done by money, in the sаme position as that he would have been in had the contract been performed.” (Internal quotation marks omitted.)
Schlicher v. Schwarts,