History
  • No items yet
midpage
Fitch v. Howitt
32 Or. 396
Or.
1898
Check Treatment
Mr. Chief Justice Moore,

after making the foregoing statement of facts, delivered the opinion.

It is contended by Howitt’s counsel that Beach and Hogue knew that certain material furnished by them, respectively, was not used in the building, and that the claims therefor were therefore willfully false; that, *404while Nottingham & Company filed their claim within 30 days from the completion of the building, more than that period had elapsed after such material was furnished, and for these reasons no lien attached in either case to the real property sought to be incumbered in this statutory method. Counsel for Beach and Hogue jointly maintain that the material provided by their clients was furnished to be used in the erection of said building, and this fact alone entitles them to their liens for the respective amounts so demanded, notwithstanding some of this material may have been diverted from the purpose for which it was originally intended; while counsel for Nottingham & Company insist that their client, having filed their claim within 30 days from the completion of the house, complied with the requirements of the statute conferring the lien.

Considering first the rights of the latter claimants, the question is presented whether the lien was lost by the failure to file the notice thereof within 30 days from the time they ceased to furnish the material, it being admitted that it was filed within 30 days from the completion of the building. In Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97), the court, construing in pari materia sections 3673 and 3678 of Hill’s Ann. Laws, held that the claim of lien, if filed within 30 days after the completion of the structure, was a compliance with the requirements of the statute. Thayer, J., in writing the opinion, says: “Whether the claim was filed within 30 days after the work and material were furnished is unimportant, provided it was done within 30 days after the house was completed.” While *405this interpretation of the statute may be somewhat doubtful, it was approved in Curtis v. Sestanovich, 26 Or. 107 (37 Pac. 67); and, having become a settled rule, it must be held that the claim of Nottingham & Company was filed within the time prescribed by law, and hence the lien was thereby preserved.

Considering Beach’s claim next, the evidence tends to show that McHenry, at the time Howitt’s building was in process of construction, was erecting a building for himself, and also another structure, known as the “Reed House”; that Beach furnished to McHenry material of the value of $297.05 to be used in the construction of Howitt’s building, and delivered the same at the site thereof, but that McHenry, without Beach’s knowledge, removed therefrom and used in the Reed building a portion of said material, of the value of $80; that Beach made no charges for material furnished on account of the latter building, but had an account, and charged McHenry, individually, with the value of certain material which he supposed was furnished for his own dwelling; that in a settlement with McHenry, on account of the contract price for the completion of the Reed house, it was discovered that certain material used therein was manufactured by Beach, or came from his establishment, whereupon the sureties on McHenry’s bond for the faithful performance of said contract informed Beach of the discovery, who inspected the building, ascertained the value of such material, and accepted from the said sureties the sum of $80 in payment therefor, which amount he credited upon McHenry’s individual account. Thereafter Beach filed a claim against Howitt’s *406building for the full amount of the material furnished to be used, but the court, disallowing the value of the part so diverted therefrom, and used in the Reed house, gave a decree for the balance due; and this presents for consideration the extent of the authority of a contractor to bind the owner of a building for material furnished to be used in its construction. The statute upon this subject, so far as applicable to the case at bar, reads as follows: “Every * * * lumber merchant * * * furnishing material * * * to be used in the construction * * * of any building * * * shall have a lien upon the same for the * * * material furnished at the instance of the owner of the building * * * and every contractor * * * having charge of the construction * * * of any building * * * shall be held to be the agent of the owner for the purposes of this act”: Hill’s Ann. Laws, § 3669. While the legislative assembly has thus declared the effect of the relation existing between the owner of real property and one who has entered into a contract with him for the erection of a building thereon, it has not defined the measure of the authority delegated, so that it becomes necessary to consider whether the contractor, in such case, is the general or special agent of the owner. If the former, he could doubtless bind his principal by every act connected with the duty intrusted to him, and, by the purchase and appropriation of unnecessary material, entail a burden upon him, the extent of which could be measured only by his avarice. If the latter, however, his authority would be limited to the procurement of material reasonably sufficient in *407quantity for the completion of the structure in accordance with the terms of his contract,— a limitation of which persons dealing with him as such agent would be obliged to take notice.

In Andrews v. Kneeland, 6 Cow. 354, Savage, C. J., in distinguishing between these two classes of agents, and the measure of their respective powers, says: “ The difference between a general and a special agent is well understood. The principal is bound by the acts of a general agent, provided they are within the scope of his authority. But an agent constituted for a particular purpose, and under a limited and circumscribed power, cannot bind his principal by any act beyond his authority.” In Morrison v. Hancock, 40 Mo. 561, under a statute of Missouri which provides, in substance, that every person furnishing any material for a building shall have a lien upon the same, whether it was supplied at tbe request of the owner or contractor, it was held that the contractor was the agent of the owner. Fagg, J., in rendering the decision of the court, and defining the power of such agent, says: “Under the provisions of the special law authorizing this proceeding, these contractors, for certain purposes and to a certain extent, are to be treated as the agents of the company, with authority to bind it to the extent of the material necessary to complete their contract,” — in effect holding that the contractor is the special agent of the owner; for, if the agent can bind the principal to the extent only of the material necessary for the completion of the building, then it necessarily follows that he would be powerless to bind him for the payment of more *408than that quantity, and, his authority being thus limited, he is a special agent. Section 3669 of our statute confines the lien to the property benefited by the material entering into the construction of a building, and, in doing so, the statute, in effect, limits the power of the contractor; for, were he the general agent of the owner, he could undoubtedly bind the latter personally for the payment of the balance due on account of the material purchased, if the proceeds of a sale of the property subject to the lien were insufficient to satisfy the demands of the materialman: Deardorff v. Everhartt, 74 Mo. 37.

The contractor, being in the nature of a special agent of the owner, with limited power, has authority to bind the property benefited for the payment of the reasonable value of such material only as is ordinarily sufficient properly to construct the building in accordance with the plans and specifications thereof, or in pursuance of the agreement entered into between the owner and contractor: Pilz v. Killingsworth, 20 Or. at page 435 (26 Pac. 305); Gordon v. Deal, 23 Or. at page 155 (31 Pac. 287); Patterson v. Gallagher, 25 Or. 227 (42 Am. St. Rep. 794, 35 Pac. 454). It is admitted that all the material so provided by Beach was furnished, as he understood, to be used in Howitt’s building. This fact rendered such material lienable, and entitled him to a lien which could ordinarily be enforced for the reasonable value of such an amount thereof as might be found sufficient to complete the structure into which it entered. But, the house hav. ing been fully completed, certain doors, windows and locks which were furnished therefor, not having been *409used theíein, the value thereof was properly deducted from the amount claimed; for while it is hardly possible to compute with accuracy the quantity of some material necessary to complete a structure, in consequence of a waste in cutting and adjusting it to the place intended, there is little room for error in calculating the number of doors, windows, locks, etc., required, and if, after a building is fully completed, any of such material remains, the reasonable value thereof cannot become a charge against the property, because it has not entered into or become a part thereof.

All the material so provided by Beach having been lienable, he had a right to file his claim for the full amount so supplied, which it must be presumed was used in the building; for it cannot be expected that a materialman would be obliged to watch the progress of a structure, to see that every stick of timber or other material so supplied by him was used therein, and if the owner would defeat a foreclosure of the lien for- the amount demanded, the burden should be cast upon him to allege and prove that some of the material, if the accurate amount thereof was capable of computation in advance, or, if not, that an unreasonable quantity thereof, remained unused after the building was fully completed, or that, without his consent, it had been removed from the building site. The conclusion here reached is not in conflict with the opinion announced in the case of Harrisburg Lumber Company v. Washburn, 29 Or. 150 (44 Pac. 890); for in that case it was admitted that a portion of the material for which the plaintiff sought to enforce a lien against a church was furnished to be used in the construction *410of a sidewalk around the lots upon which, the building: was erected, thus showing that the purpose for which the material was supplied rendered it nonlienable as against the church. At the time Beach filed his claim,, he had no knowledge that the material used in the the Need house had been diverted from Howitt’s building, but, supposing- that some employee sent it out,, who neglected to charge it to the proper building, he accepted $80, as the value thereof, from those whose duty it was to keep down any claim that might be filed against the Reed house, and credited the amount so-received on McHenry’s individual account. Had he-knowingly accepted this money, and purposely neglected to credit the same upon the account againstHowitt’s building, thereby seeking to enforce a claim-against said property for the payment of McHenry’s debts, a different rule would prevail; but we think the-evidence clearly shows that it was an honest mistake,, in view of which the decree in his behalf should not. be disturbed.

It is admitted that Hogue furnished to McHenry,, to be used, as he understood, in the construction of Howitt’s building, material of the value of $392.87„ which was delivered to McHenry’s teamsters at Hogue’s factory, but that a part thereof, valued at. $55.50, was never taken to the said building, and that another part, of the value of $12.38, was removed therefrom, and used elsewhere. The court, however,, deducting the value of the material which never reached, and that which was diverted from, Howitt’s building, gave a decree in favor of Hogue for the *411sum of $325, the value of the material used in said building, in which award we find no error.

Beach and Hogue each complain of the allowance made by the trial court in his behalf on account of attorney’s fees, but, inasmuch as no evidence on this branch of the subject is to be found in the transcript, it must be presumed that the amounts so awarded are reasonable, and for this reason they will not be disturbed. It follows that the decree will be affirmed.

Affirmed.

Case Details

Case Name: Fitch v. Howitt
Court Name: Oregon Supreme Court
Date Published: Jan 26, 1898
Citation: 32 Or. 396
Court Abbreviation: Or.
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.