70 N.Y.S. 38 | N.Y. App. Div. | 1901
On June 16, 1898, the plaintiff made the following proposition in writing to the defendant :
“ Sayville, June 16, ’98.
“ I will furnish all material and labour to compleat the wind mill as we decided on
tower 60 ft high 10 ft wheal 1000 gal Sypres tank elevated in tower bottom of tank 27 ft from ground do all digging and fill up the ditch and brick up pump pit
pump 3 in brass lined force púmp laying in garden to House 11/4 galv pipe with three Hydrents the One in front yard a cast iron Hydrent laying 3/4 galv pipe in garden north of mill and in front yard with Hydrent in garden at the north and 1 facett in tower I will guarantee work and all material to be first class and will compleat the job as we talked it over for 327T6¡¡% I will do the job at once or as quick as I can get the material on the ground
“ yours Respt
“S. A. FISHER.”
At the same time and as a part of said offer the plaintiff gave to the defendant an itemized bill or statement of the amounts to be paid by her for the wheel, tower, tank, pump, pipe, valves and
The defendant accepted the proposition, and the plaintiff testified that he ordered the mill or material on June twentieth, commenced the erection of the mill on July twelfth and completed it the twenty-third. It appears that the clerk or manufacturer who shipped the mill to the -plaintiff made a mistake and sent a tower not sufficiently strong to support the tank; that the defendant-refused to accept the mill; that August twenty-third plaintiff commenced taking it down for the purpose of removing it, and on the day following the defendant served on the plaintiff the following-notice :
“ Mr. S. A. Fisher :
“ Dear Sir.— I wish you to remove everything you have put on the place and consider the contract broken and ended.
“ Respect.
“ L. A. REHDELL GOODRICH.”
The plaintiff in his complaint alleges that he furnished the pump,; tank, tower and - other material, and erected the windmill upon the-premises of the defendant, complete and in working order, and that, defendant has refused- to pay for the same.
The contract is single and entire. It is for the sale and delivery of a windmill, and if it had been performed the plaintiff would be-entitled to recover the full sum of $327.60. He was not to furnish, material and perform labor upon it for the defendant, but from his. own material and by his own labor he was to furnish and affix the-windmill to the defendant’s premises. As was said in Butler v. Butler (77 N. Y. 475), “ the defendant was to have, not these articles, as separate parts or members from which, by the. application of skill and labor a machine could be constructed, but a complete thing, placed upon his own premises, of the required capacity and ready for use.” It is not pretended that this has been done. The plaintiff testified that the parts “ were not adapted to the purpose for which they were intended. * * * I saw that if it was used, as it was intended to be used after it was put up, that it was not; safe. And I saw that it would-be necessary for it to come down.”1
It is well settled in this State that under an entire contract there is no right of action, and can be no recovery until the whole quantity contracted for is delivered. (Silberman v. Fretz, 16 Misc. Rep. 449; Nightingale v. Eiseman, 121 N. Y. 288.)
The case was submitted to the jury upon the theory that the plaintiff was entitled to recover the contract price if he was willing to make good the deficiency.
The court charged the jury that it was conceded that the contract had not been substantially performed, and also said: “ If you find that the contract was substantially performed with the exception of these matters which the plaintiff offered to make good, and that he is unreasonably prevented from making it good, he is entitled to recover.” This proposition cannot be sustained. The defect being of a material character, the defendant had the right to terminate the contract and to require the plaintiff to remove the mill, as not conforming to it, without regard to the intention of the plaintiff. (Feinberg v. Weiher, 46 N. Y. St. Repr. 389 ; Brown v. Foster, 108 N. Y. 387; Glacius v. Black, 50 id. 145 ; Smith v. Brady, 17 id. 173 ; Pullman v. Corning, 9 id. 93.)
If, however, the defendant agreed or assented to the substitution of a new tower, and the plaintiff procured one which would have been efficient and satisfactory, the act of the defendant in preventing its erection was a breach of the contract on her part which
The judgment and order should be reversed and a new-trial granted, costs to abide the event.
All concurred.
Judgment and order reversed and new trial granted, costs to abide the event.