Fisher v. Abeel

66 Barb. 381 | N.Y. Sup. Ct. | 1873

By the Court,

Mullin, P. J.

It was impossible for the court to say, upon the evidence of the plaintiff Fisher, before the written order was put in evidence, that it contained the contract between the parties. The paper delivered by Stilwell was called an order. That term did not necessarily imply that it contained the contract—it was the act of one of the parties only—the contract was the act of both.

The court was right in receiving the parol evidence of the conversation between Fisher and Stilwell, and in refusing to allow the defendant to put in the written evidence, while the plaintiff was giving evidence.

Iam of opinion that the court properly refused to strike out the parol evidence as to the time within which the boat was to be loaded. The order was not intended to embrace the whole contract. It was given in performance of part of it, and contained no more of it than was necessary to enable the coal company to know how much coal to deliver, and for whom, and the amount which it should advance.

The boat was detained at Rondout eight days, before it got a cargo. Less than a day was required to load it, when its turn came. It was proved that other boats arriving after the plaintiffs’ were loaded before it. The detention was seven days, and the damages shown to be worth from $12 to $25 per day.

Demurrage, properly so called, is the, compensation provided for in the contract of affreightment for the detention of the vessel beyond the time agreed on for load*384ing or unloading, &c. (Abbott on Shipping, 304. Pars, on Mercantile Law, 362. Clendaniel v. Tuckerman, 17 Barb. 184. Cross v. Beard, 26 N. Y. 85. Morse v. Pesant, 2 Keyes, 16.) The agreement for it must be express ; it is not implied.

If an agreement for demurrage was made, it was by Stilwell as agent for the defendant, and it was by parol. To enable S. to bind the defendant by such an agreement he must have had authority from the principal to make it. Hot only is no such authority proved, but it is expressly disproved. If then the agent could make a contract for the payment of demurrage, it must result from his authority to employ vessels for the defendant.

I am not aware of any authority that recognizes any such power in such an agent. He is, of course, authorized to make such a contract as agents employed in the same business are authorized to make. Whether such agents are accustomed to contract for the payment of demurrage, we do not know, as no proof was given on the subject.

It would seem to be reasonable that such agents might agree upon the length of time the vessel should wait for a qargo, or for unloading at the port of delivery.

It is important to the owner of the vessel, as well as to the owner of the cargo, to know how long the vessel may be detained, as it may materially affect the price to be charged and paid for freight. But when, as in this case, vessels are compelled to wait their turn in being loaded, causing in one case a delay, perhaps, of one day, and in another of ten days, without fault on the part of the owner of the cargo, it might prove disastrous to him to permit his agent to bind him to load the vessel within any specified number of days.

It would seem that the plaintiffs and other boat owners were under no obligation to delay until the vessel *385can be loaded, so that after waiting a reasonable time they may depart without the coal.

When no time is fixed for loading or unloading it is to be done in reasonable time; and what constitutes a reasonable time is for the jury. In determining what constitutes a reasonable time, the custom in force at the place of receiving the cargo is to be. taken into the account; so that if vessels are required to wait their turn, the freighter is not liable for detention of the vessel while it is waiting its turn. (Cross v. Beard, 26 N. Y. 85.)

It would seem, therefore, that in the absence of proof of a custom for agents to agree with the owner of a vessel upon the lay days to be allowed the freighter, such authority cannot in a case like this be presumed, but it must be expressly proved. No such authority being proved, the defendant is not liable on the express contract.

Although there is no express agreement for demur-rage, damages in the nature of demurrage may be recovered against the owner of the cargo, when he improperly detains the vessel beyond a reasonable time for loading or unloading. (See cases cited supra.)

Detention of á vessel while waiting her turn to load or unload is not a detention for which the owner of the cargo is liable. (Cross v. Beard, supra.) So that the defendant is not liable for damages in the nature of demurrage, unless he is responsible because the vessel was not loaded in her turn by the coal company.

It is said that vessels arriving after the plaintiff’s were loaded before her, and she did not get her turn. For that wrong the defendant is not liable, but the coal company or its agents may be. The detention for which the defendant is responsible is caused by his own act, and not by the act of others, over whom he has no control.

When there is an express agreement by the freighter *386that the vessel shall be laden or unladen in a specified number of days, he is responsible for any detention beyond that, although produced by causes over which he had no manner of control. (See eases cited supra.)

[Fourth Department, General Term, at Rochester, April 1, 1873.

This doctrine has no application to the case before us.

The judgment is erroneous, and should be reversed and a new trial qrdered, costs to abide the event.

New trial granted.

Mullin, Talcolt and E. D. Smith, Justices.]

midpage