FIRST STATE BANK, a corporation, Plaintiff-Respondent, v. REORGANIZED SCHOOL DISTRICT R-3, BUNKER, Missouri, and United States Fidelity and Guaranty Company, a corporation, Defendants-Appellants.
No. 9301.
Missouri Court of Appeals, Springfield District.
May 7, 1973.
Motions for Rehearing or Transfer Denied May 24, 1973 and May 25, 1973.
495 S.W.2d 471
The judgment is affirmed.
MCMILLIAN, J., dissents.
CLEMENS, J., concurs.
Weldon W. Moore, Rolla, Morton K. Lange, St. Louis, for plaintiff-respondent.
HOGAN, Judge.
This is an action to determine the priority of claims made by the surety on the performance bond of a defaulting building contractor and a bank which had advanced money on the strength of an assignment of the proceeds of the contract. The trial court has found for the plaintiff bank on stipulated facts and the surety and the school district (which is merely a stakeholder) have appealed. Our duty is to determine whether or not the trial court‘s judgment represents the proper legal conclusion on the facts stipulated. Jewel Tea Co. v. City of Carthage, 257 Mo. 383, 388, 165 S.W. 743, 744 (1914); Browning v. City of Poplar Bluff, 370 S.W.2d 179, 182 [3] (Mo.App.1963); Bartlett v. Nat‘l Fin. Corp., 228 Mo. App. 789, 799, 73 S.W.2d 451, 457 [11] (1934). In reviewing the record, we are permitted to draw reasonable inferences from the facts stated, and we should sustain the judgment if that can be done on any reasonable theory, Murphy v. Doniphan Tel. Co., 347 Mo. 372, 379, 147 S.W.2d 616, 619-620 [6], [7,8] (1941); Semo Motor Co. v. Nat‘l Mut. Ins. Co., 383 S.W.2d 158, 161 [1,2] (Mo. App.1964), but if the facts stipulated, together with the reasonable inferences to be drawn therefrom, are insufficient to sustain the result reached, the judgment must be reversed, and the case may be remanded for a new trial. City of Stanberry v. Jordan, 145 Mo. 371, 382-383, 46 S.W. 1093, 1096 [5] (1898). By express authority of Rule 83.13(c)1 the order for a new trial may be restricted to specific issues.
On November 29, 1967, the school district, specifically Reorganized School District R-3 of Bunker, Missouri, entered into a contract with R. D. Light & Son Construction, Inc., (the contractor) for the construction of an addition to the high school building at Bunker. The contract2 provides: that the work will be done for the sum of $130,069, and shall be completed by September 26, 1968; that partial or progress payments of 90% of the construction accomplished during the preceding calendar month shall be made on or about the fifth day of each month, on the basis of application for payment submitted by the contractor and certified by the architect, and that on substantial completion of the work, the owner (here the school district) shall pay a sum sufficient to increase the total payments to 90% of the total contract price. The contract further provides that this 10% “retainage“, or “retent“, as it is often called, shall be paid within 30 days of substantial completion of the work upon issuance of a certificate for payment by the architect. We have the distinct impression that the contract before us (as Exhibit L) is not the whole agreement which the parties entered into; the contract is sufficient as such, but it is written on a standard form prepared for use by the American Institute of Architects, and this form is usually integrated with a second form setting out the general conditions of the contract in detail, including the
Contemporaneously with the execution of the contract, the contractor applied to the surety (U. S. F. & G.) for a “performance” bond as required by
The surety, for a premium not disclosed, thereupon issued a labor and material payment bond (Exhibit K) as mandatorily required by
The contractor began work on the school building, apparently in December 1967, and continued working until May 16, 1968, when it entered into a loan transaction with the plaintiff bank. The nature of this transaction is not entirely clear; there are a number of instruments in the record (Exhibits A, B and C) which exemplify or prove some kind of loan agreement, and considering them as a whole, it would appear that the bank agreed to advance the contractor a line of credit up to $56,000, taking as security therefor the contractor‘s promissory note in the amount of $56,000 and an unconditional assignment of all proceeds to become due under the Bunker School District construction contract. It is stipulated that the loan was made to the contractor as working capital to complete the Bunker School job and other contracts. In any case, the bank filed the assignment, (together with a document entitled a “schedule“) for record, and Exhibit B shows that the assignment, together with the “schedule” was recorded in the Phelps County Recorder‘s Office on May 22, 1968.
The assignment and the note were executed on May 16, 1968. On May 15, 1968, the bank had advised the school district, by letter, that the contractor had applied for a loan, and sought to pledge “their [sic] accounts receivable due from your school district as security.” The school district was asked to acknowledge a notice of assignment, prepared, it appears, to comply with the requirements of the federal Assignment of Claims Act,
The bank‘s letter of May 15, 1968, to the school district requested that progress payments be made directly to the bank, but on June 10, 1968, progress payment number six in the amount of $14,561 became due and was paid by the school district to the contractor, who endorsed the school district‘s check to the bank. On June 21, 1968, the contractor‘s president conferred with the surety‘s officers in St. Louis, and met the next day, June 22, with officers of the surety and the bank, at which time the contractor‘s president declared, in the language of the stipulation, that the contractor “did not have sufficient cash on hand to pay for materials and labor to complete his [sic] then existing contracts.”
On July 5, 1968, progress payment number seven in the amount of $12,217.50 became due and payable. On July 16, the bank, through its attorneys, made a formal written demand upon the school district for “all moneys due as progress payment“, stating that it was the bank‘s understanding that progress payment number seven (for work completed during June) was then due and payable. On July 18, the contractor addressed a letter to the surety stating that it was financially unable to complete the Bunker construction and requested the surety “to assist in the completion of the [Bunker] job [so the contractor could] fullfill [sic] its obligations under this contract.” On July 19, 1968, the school district drew its check #1607 in the amount of $12,217.50, representing progress payment number seven, in favor of the surety. The check (Exhibit M) shows that it was credited to the surety‘s account by the Mercantile Trust Company of St. Louis on August 5, 1968. A letter dated July 26, 1968, addressed to the school district‘s superintendent by Mr. Harry Zumstein, one of the surety‘s bond attorneys, states that the surety “[has] been advancing funds to assist in meeting payrolls and in the payment of bills owed on the project“, and indicates that progress payment number seven was paid by the school district to the surety at the surety‘s request, and upon the surety‘s agreement to indemnify the school district in the event of any action by the bank.
Finally, it is stipulated that from and after July 24, 1968, the surety furnished all funds to meet the payroll and discharge the materials bills, and that the surety paid “some” taxes, and on March 1, 1969, took over complete supervision of the work. There is a balance of $28,135.04 due the bank from the contractor.
The trial court made rather detailed findings of fact and conclusions of law. They have been helpful to us, but there is no need to set them forth at length. The court concluded as a matter of law that no default occurred in the performance of the construction contract prior to June 21, 1968, that the plaintiff bank was entitled to both progress payment number seven and the retainage being held by the school district, and entered judgment accordingly.
For the purpose of limiting and defining the scope of this opinion, several preliminary observations are appropriate. In ascertaining the rights of the parties, and determining the priority of their claims, we have found the federal authorities persuasive, not because we believe we are bound by such decisions, but because the federal authorities we have examined involve contracts for public work subject to bonding requirements similar to those imposed by
Two further preliminary observations should be made. As noted, the skeleton contract before us does not specifically state what shall constitute a “default” on the contractor‘s part, nor define the rights of the parties upon such default. We are therefore obliged to look to such documents as are part of the record, and to general principles of law, to determine the priority of the competing claims of the surety and the plaintiff bank. We do not, either expressly or inferentially, extend our ruling to a holding that the priority of the parties’ claims might not be modified by more specific contractual provisions defining the events of default and stating the rights of the parties thereafter.
Finally, though the matter has not been briefed or even mentioned by either party, we have noted that many recent cases involving the priority of claims made by the surety on the performance or labor and materials bond of a defaulting contractor and the contractor‘s assignee have discussed the effect of Article 9 of the Uniform Commercial Code upon the priority of such competing claims. In our view, the surety‘s equitable lien, presently to be discussed, has not been affected by the enactment of Article 9 of the Uniform Commercial Code and Article 9 does not govern the priority of the claims here asserted.5
On the merits, the parties have briefed and argued a number of points and subpoints and in support of their arguments
The essential question presented, of course, is which of the two parties is entitled to the fund remaining in the school district‘s possession. In order to resolve this question we must, unfortunately at the expense of some repetition, consider the rights of the parties as they developed chronologically. We agree with the defendants that the obligations and rights of the contractor, the school district and the surety must be determined in the first instance from the contract itself, the application for the bond, and the bond as executed, inasmuch as the intruments relate to the same transaction, were executed contemporaneously, and the bond was specifically required by
The performance bond itself actually consists of two bonds: a) a labor and materials payment bond, as required by
Apparently performance of the work was begun as contemplated in December 1967. Inferably, several progress payments were made directly to the contractor, but by May 16, 1968, the contractor found itself in need of working capital. It applied to the plaintiff bank, which, as we read and construe the several instruments evidencing the loan transaction, agreed to advance the contractor $56,000 as working capital, taking as security the contractor‘s note and an assignment of all moneys due or to become due under the Bunker construction contract. The bank gave notice to the surety and to the school district. There is no provision in the contract forbidding assignment of the proceeds, we have no general statute forbidding the assignment of claims under public works contracts comparable to
We do not believe the bank can be heard to say that it advanced funds upon any misrepresentation by the contractor, or that there was any duty upon the surety to object at the time the assignment was made on May 16, 1968. This is not a case like Nat’l Sur. Corp. v. State Nat’l Bank of Frankfort, 454 S.W.2d 354, 357 [3] (Ky. 1970), where the surety agreed to a loan and an assignment of the contract proceeds after the contractor was in default. The contractor was in no sense in “default” on May 16. No event had occurred to effectuate the surety’s conditional assignment, and there was simply nothing to object to. Neither do we think the bank can be heard to say it was misled to its detriment because the contractor warranted and represented in its assignment to the bank that it had not previously encumbered its right to the proceeds of the Bunker construction contract. In the first place the surety does not claim the funds withheld by the school district by virtue of a prior assignment; further, even though the bank may have had no actual knowledge of the surety’s obligation, it must be charged with knowledge that
Another and determinative issue presented is whether the school district had the right to withhold progress payment No. 7 and whether or not, assuming it is entitled to the retainage, or retent by virtue of an equitable lien or equitable right of subrogation, the surety is also entitled to progress payment No. 7. The defendants maintain that the surety is entitled to the whole sum because it was required to complete the contract after the contractor‘s default; the bank argues that in any case the surety is not entitled to funds earned but unpaid before default, and that progress payment No. 7 was earned before any default occurred. The defendant‘s position is that default occurred on June 21, 1968, when the contractor advised the surety and the bank‘s officers that it did not have sufficient cash on hand to pay for materials and labor to complete its then existing contracts; the plaintiff contends that this was not an anticipatory breach or total repudiation which, it says, was necessary to compel the surety to perform.
As we have noted, one of the difficulties presented by this case is that the entire contract does not seem to be before us. The “events of default” usually set forth as part of the contract are missing. Undoubtedly, the contractor‘s admission that it did not have sufficient cash on hand to pay for the labor and materials to complete its then existing contracts was an admission of insolvency, for by definition, insolvency, whether of a corporation or a natural person, means inability to pay debts as they become due in the ordinary course of business.8 There is some authority which seems to hold that a building contractor who admits insolvency is in “default“, Bender v. Neillsville Bank of Neillsville, supra, 10 Wis.2d 282, 102 N.W.2d at 747 [4, 5], but there is respectable local authority, never to our knowledge overruled, which indicates that the surety‘s obligation to perform does not arise until there has been a failure of performance, that is, an actual breach of contract on the contractor‘s part. County of Audrain ex rel. First Nat‘l Bank of Mexico v. Walker, 236 Mo.App. 627, 635, 155 S.W.2d 251, 255 (1941). The bank maintains that the contractor‘s declaration of insolvency did not amount to a repudiation of the contract, and did not amount to a declaration that it could or would not perform. Since there was no breach of the contract, the bank says, the school district had no right to retain progress payment No. 7.
It is true that the prospective inability to perform which arises upon the insolvency of one party to a contract does not necessarily excuse the other party from performance, 6 Corbin, Contracts, § 1261 (1962); 3 Williston, Contracts, § 880 (rev. ed. 1936), and see Cornett v. Best, 151 Mo.App. 546, 551-552, 132 S.W. 35, 36 [2] [3] (1910), but it may justify the solvent party in requiring security as a condition to further performance. 6 Corbin, Contracts, § 1261, p. 41; Restatement of Contracts § 287 (1932). Nevertheless, even given the school district‘s equitable obligation to see that the lawful claims of laborers and materialmen are satisfied, a matter we shall discuss further, we do not believe the record is sufficient to establish the school district‘s right to withhold progress payment No. 7. If, at the time progress payment No. 7 became due on July 5, there
Finally, we must consider the surety’s argument that in the circumstances, it is entitled to all the funds retained by the school district because of its payment of all the labor and materials bills from and after July 24, 1968, and its assumption of complete supervision of the work on March 1, 1969. The surety asserts that it has an equitable right of subrogation to or an equitable lien upon the funds now held by the school district; the bank counters with the argument that the surety stands in the shoes of the contractor, and can have no greater claim than it would have, and in any case its assignment was superior to any assignment made to the surety.
We shall not attempt to discuss the law further than is necessary to dispose of the appeal. The general rule is that a surety which executes a performance bond on a construction contract, and is thereafter required to pay unpaid labor and materials claims, or to complete the contract upon default by the contractor, has an equitable right of subrogation and an equitable lien upon funds retained by the owner or obligee; this right of subrogation or equitable lien is superior to the right of one who takes by assignment from the contractor after the execution of the bond, and relates back to the date of the surety’s bond.9 Moreover, the bank is mis-
We have neither the authority nor the inclination to say that the general principles just stated are or should be the law of this state, but upon examination of the applicable precedents cited to us, we do not find the law as declared by our courts to be very different in any material respect from the law as declared by the federal cases. The parties have cited the National Surety case, supra, 317 S.W.2d 334, many times; both the bank and the surety maintain that it supports their positions. We agree that that opinion is a most articulate and scholarly discussion of the general principles there involved, but in sum, at least as we read the case, the court merely held in the circumstances that unconditional payment of an earned sum to the contractor before default freed that sum of any equitable lien on the part of the intervening surety as against the plaintiff surety, which had a prior, valid claim against the contractor as a completing surety on another bond. Our case is not so complicated, and in any event, many of the authorities we have considered and discussed are there cited as stating the general law. As previously noted, the Camdenton School District case, supra, is easily distinguishable from the present case, because it is stipulated here that the money advanced by the bank went to furnish working capital for several construction projects, whereas in the Camdenton School District case, the funds advanced by the relator had been used to pay for labor and materials which went into the school building. The Camdenton School District case does not, perhaps, jibe with the latest federal decisions, but it has nevertheless been argued, with some merit, that when the assignee‘s loan has been made to discharge an obligation the payment bond surety would have had to bear, and has been used for that purpose, but the surety is nevertheless held subrogated to the entire retained fund, the surety is unjustly enriched. See Town of River Junction v. Maryland Cas. Co., supra, 133 F.2d at 59 [6, 7]; Royal Indemnity Co. v. United States, 93 F.Supp. 891, 899-900, 117 Ct.Cl. 736 (1950) (dissenting opinion).
As for the other Missouri cases cited by the parties, the County of Audrain case, supra, or at least the principal opinion, simply holds, as we read it, that a completing surety‘s right of subrogation cannot arise until the contractor has defaulted. The holding in School Dist. No. 18 of Caruthersville v. McClure, 224 S.W. 831 (Mo. 1920), though somewhat obscure as to the relative priorities between the lending bank and the surety, recognizes the right of the owner to apply sums in its hands to the unsatisfied claims of laborers and materialmen. In our view it is clearly distinguishable from the case at hand a) because it was shown that the proceeds of the loan went directly to pay for labor and materials used in the construction of the school, which is not true here; and b) the surety had covenanted to repay what the obligee might expend in payment for labor and
We reiterate our conclusion that the principles developed in the federal cases involving public works contracts are applicable here. The federal cases, from the Henningsen case, decided in 1908, through the Pearlman case, decided in 1962, lay heavy emphasis upon the equitable obligation of the government or governmental unit to see that those who supply labor or materials for the construction of public buildings are paid. They also emphasize that public buildings are nonlienable, and that the Miller Act,
In light of these principles, we summarize our opinion and holding as follows:
1. The surety, upon the contractor‘s default, became subrogated to the rights of the contractor and the school district, and has an equity in the retained fund superior to that of the bank. The surety‘s rights relate back to the time of the execution of the bond.
2. It is not clear when the surety‘s right of subrogation attached; it is entitled to recover progress payment No. 7 only if the condition of its payment bond had been breached prior to the time progress payment No. 7 became due on July 5, 1968.
3. We consider it a reasonable inference that the surety would not advance all funds needed for completion of the contract without being obligated to do so by the terms of its bond; therefore, we hold the surety entitled to all sums earned
4. The surety is entitled to recover progress payment No. 7 in the amount of $12,217.50, provided: its labor and materials payment bond was breached before that estimate became due and payable on July 5, 1968, and provided the total amount expended by the surety exceeds the amount here in controversy, to-wit $18,515.04.
The judgment is therefore reversed and remanded for further proceedings not inconsistent with this opinion. The parties may stipulate further or the court may hear such evidence as will enable it to enter a final judgment in accordance with this opinion, but only on the following issues: 1) the date of the contractor‘s actual default under the labor and material payment bond, and 2) the total amount expended by the defendant surety. It is so ordered.
TITUS, C. J., and STONE, J., concur.
BILLINGS, J., not participating because not a member of the court when the cause was submitted.
ON MOTION FOR REHEARING OR TO TRANSFER
PER CURIAM:
In its alternative motion for rehearing or for transfer to the Supreme Court, the plaintiff bank asserts, among other things: 1) that it should not be charged with notice that a “completion” bond existed, because
Plaintiffs’ argument that it cannot reasonably be held to constructive notice of the existence of a “completion” bond, as distinguished from a “payment” bond draws a distinction without a difference, for the surety‘s subrogative right is essentially the same whether it performs as a “completing” surety or as a “payment” surety. Moreover, statutory provisions requiring some kind of bond from a public works contractor are usual, not exceptional, 64 Am.Jur.2d Public Works and Contracts § 99, pp. 961-962 (1972), and the rule charging the assignee of a public works contractor with constructive knowledge of such statutory provisions has been applied as a matter of state law, as well as federal law. See Standard Acc. Ins. Co. v. Federal Nat. Bank, supra, 112 F.2d 692, 695 (10th Cir. 1940) (applying Oklahoma law); Derby v. United States F. & G. Co., 87 Or. 34, 169 P. 500, 503 [3] (1917).
As for the plaintiffs’ argument that the surety should be required to notify the contractor‘s assignee of its equitable right of subrogation, we might suggest, as most courts have, that the bank was certainly under no compulsion to loan the contractor any money, and might easily have protected itself by making inquiry of the arrangements between the contractor and the surety, since it knew of the surety‘s existence. However, we wish to emphasize
The alternative motion for rehearing or for transfer is denied.
