107 Cal. 55 | Cal. | 1895
Plaintiff a corporation, commenced this action July 22, 1893, to recover of defendant a sum of money alleged to be due the plaintiff under an assignment of a claim therefor to it made by the Ætna Iron and Steel Company, also a corporation, on May 16, 1893. The defendant is an irrigation district formed under the statute providing for the organization and government of such districts, approved March 7, 1887. One W. L. Ewing filed a complaint in intervention, but the findings and judgment were against him, and he has not appealed. The case comes here on the judgment-roll alone.
From the record it appears that on March 26, 1891, defendant made a contract with the Silver Gate Manufacturing Company, a corporation, whereby such company agreed to construct for defendant a line of wood pipe 6.5 miles in length, and to keep the same in repair, free from leakage, for the period of one year after the completion thereof; the price to be paid by defendant for such work was by the contract made payable thirty-five days after the completion of the pipe line. The construction of such pipe was completed by the Silver Gate "Manufacturing Company, or by said .¿Etna Iron and Steel Company, acting for and in the stead of said manufacturing company, on the ninth day of January, 1893. Previously, on September 14, 1892, said manufacturing company, the original contractor, assigned its claims due, or to become due, on account of the contract to the said .¿Etna Iron and Steel Company.
On May 2, 1893, the defendant by its board of directors allowed and approved the account of the .¿Etna Iron
The interest of the intervenor, Coronado Foundry and Machine Company, arose in this wise: Subsequently to March 26, 1891, the date of the contract, said intervenor entered into an oral agreement with the contractor, the Silver Gate Manufacturing Company, whereby said intervenor promised to furnish to the contractor all the iron couplings to be used in the construction of said pipe line, the quantity of such material so to be furnished being not otherwise specified, at the price of 4£ cents per pound, which price the contractor agreed to pay. The court found that such agreement “ also included the making by said intervenor of all patterns for said couplings and the furnishing of boxes in which to ship said couplings, said Silver Gate Manufacturing Company agreeing to pay the reasonable value of said patterns and boxes to said intervenor.” No time of payment was specified in said agreement.
The intervenor made such patterns to the value of $111 05, and boxes to the value of $99.05.. Patterns, boxes, and couplings were made and supplied by the intervenor to the contractor in divers quantities and at divers times, from April 13, 1891, to November 9°, 1891 (except a single item of patterns, amounting to $7.65, found to have been furnished February 19, 1891); the last item of couplings, $10.60 in amount, being supplied November 9, 1891. The couplings were actually used in the construction of the pipe line, but no patterns or boxes were so used; it seems that the patterns were used by the intervenor in moulding the couplings at its own works, and were necessary for that purpose; they were
Payments were made to the intervenor on account in the month of July, 1891, amounting to $300; and on October 26, 1893, after this action had been begun, said intervenor served written notice on the defendant that it, the intervenor, “ furnished materials to the Silver Gate Manufacturing Company, to be used, and which actually were used in the construction of the pipe line for the Perris Irrigation District, under the contract between the said Perris Irrigation District and the said Silver Gate Manufacturing Company; that said material was cast couplings to be used in the construction of said pipe line, and that the value of the materials so furnished was $2,439.58”; also that only $300 had been paid on account thereof, and that a balance of $2,139.58 remained due and unpaid; and required defendant to retain in its possession sufficient funds due under its contract with the Silver Gate Manufacturing Company to pay such balance. A few days later, November 4, 1893, said intervenor filed its complaint in intervention herein.
The plaintiff pleaded, among other defenses to interven or’s action, that the same is barred: 1. By the provisions of subdivision 1 of section 339 of the Code of Civil Procedure; 2. By the provisions of section 1190 of the same code.
Regarding the controversy between plaintiff and defendant the court found that default was made in performance of that term of the contract between defendant and the Silver Gate Manufacturing Company, by which the latter agreed to keep the pipe in repair for one year after the completion thereof, and that defendant necessarily expended for that purpose during such period, from January 9, 1893, to January 9, 1894, the sum of $1,223.15. The only averment in the pleadings setting up a counterclaim for this sum is contained in the de
The court gave judgment in favor of the intervenor, Coronado Foundry and Machine Company, for the amount of its demand—$2,139.58 — and in favor of plaintiff for $829.32, besides interest from February 13, 1893; the remainder of the fund in the hands of defendant, $1,223.15, being allowed to it in virtue of the counterclaim referred to. Plaintiff appeals.
1. Was the notice served on defendant by the intervenor, October 26, 1893, in sufficient time to fix the right of the intervenor in the fund yet remaining in the hands of defendant? Such notice was given more than eight months after the completion of the contract for the construction of the pipe, more than seven months after the balance due undei said contract became payable according to its terms, more than one year after the original contractor had assigned its rights to such balance, and more than three months after plaintiff, as a subsequent assignee thereof, had commenced this action to recover the same. Appellant maintains that, these circumstances considered, the notice was too late. The decision of this question turns upon the proper construction of the statute (Code Civ. Proc., sec. 1184) as amended in 1887; what that construction should be is not discussed in the briefs filed on behalf of either the intervenor or the defendant. Said section 1184 provides that: “Any of the persons mentioned in section 1183, except the contractor, may at any time give to the reputed owner a written notice that they have performed labor or furnished materials, or both, to the contractor, or other person acting by authority of the reputed owner, or that they have agreed to do so, stating in general terms the kind of labor and materials, and the name of the person to or for whom the same was done or furnished, or both, and the amount in value, as near as may
After the expiration of thirty-five days from the time of completing the contract the .¿Etna company was, therefore, by the terms of the contract, entitled to be paid the full amount of the contract price then remaining unpaid. As has been seen, a portion of this price was paid in May following, and on the 16th of that month the claim for the residue was assigned to plaintiff. Un
V - If the contractor, previous to the giving of the notice, has transferred to another, who takes the assignment for value and without notice of the latent equities of the materialman, the amount then actually due and payable on the contract, there is then nothing either due or to become due to him, and there is no fund on which the notice can operate. It is true that the statute declares that the materialman or other person dealing with the contractor may give the notice “at any time”; but this expression must be construed in connection with the other provisions relating to the subject and the general scheme of the code chapter of which they form a part. That chapter contemplates throughout that the privileges it allows to those who furnish material or labor for the construction of buildings and other improvements shall be exercised with promptitude, and so as not to hamper either the owner or the contractor, or those who deal
We hold in this behalf: 1. That the right of the intervenor to give the notice of its demand, and thus to charge the contract price in the hands of the owner, was not affected by any assignment made by the contractor until after the time when the demand assigned became due, in this case upon the expiration of thirty-five days from the completion of the contract; 2. That the assignment made by the original contractor, the Silver Gate Manufacturing Company, to the ¿Etna Iron and Steel Company, before the completion of the work, vested the latter company, prior to the expiration of thirty-five days from the date of such completion, with no rights anywise different from or superior to those of the original contractor, nor even then if such assignment was made as part of a mere substitution of the ¿Etna company for the contractor in the original contract—a matter on which the findings are not clear;
The argument of the intervenor that it must be presumed in support of the findings and judgment that some notice other than that expressly found by the court, and prior to it in point of time, was served on the defendant, is without foundation. (North Pacific R. R. Co. v. Reynolds, 50 Cal. 90.) So of its contention that, since there is no finding that the contract of defendant with the Silver Gate Manufacturing Company was filed with the county recorder, it is therefore to be treated as void; and, as subsidiary consequences, that the defendant became personally liable to it, the intervenor, for the materials furnished (Code Civ. Proc. sec. 1183), and no notice of its claim was necessary. The court found that
2. Our conclusion on the branch of the case above considered necessitates a reversal of the judgment in favor of the intervenor; but as there maybe a new trial some other points presented should be noticed.
Appellant maintains that the intervenor should have filed notice of its claim in the office of the county recorder as in cases where a lien is claimed against a building or other structure under section 1187 of the Code of Civil Procedure. But the remedy provided by section 1184 of the same code for intercepting the contract price in the hands of the owner is not dependent upon proceedings to enforce a lien against the property affected by the contract. (Bates v. Santa Barbara County, 90 Cal. 547.) Counsel question the authority of that case, but we think it construes the statute correctly. For similar reason the intervenor’s action was not barred by the provisions of section 1190 of the Code of Civil Procedure.
The contract of the intervenor was entire; it agreed to furnish to the contractor “ all the iron couplings to be used in the construction of said pipe line” at a fixed rate per pound. (See 2 Parsons on Contracts, side page 519, and cases cited.) It could not have enforced payment in an action on the contract for any part of the couplings delivered until it had furnished all necessary for the use indicated, or had offered so to furnish the same and the contractor had refused the offer. (Civ. Code, sec. 1439.) The last delivery of couplings was on November 9, 1891, and appears to have been made in performance of the agreement of the intervenor with
The court erred in allowing to the intervenor the value of the patterns used in the manufacture of the couplings and the value of the boxes in which such couplings were cased for shipment; both the patterns and the boxes were made the subject of separate charges by the intervenor and not included in the price of the couplings; they remained the property of the contractor and were not incorporated in the structure; in these respects, and perhaps others, differing from the cartage considered lien able in West Coast Lumber Co. v. Newkirk, 80 Cal. 275, as being included in the value of the materials furnished; we regard the boxes and patterns here as too remote from the actual work of construction to permit their cost to be made a charge in this action against the contract price in the hands of the owner.
3. There is no pleading on the part of the defendant sufficient to sustain the judgment allowing a counterclaim in its favor for the expense of keeping the pipe in repair during the period of one year after completion; the averment that “it will be required to expend more than” a sum specified for that purpose, contained in the answer filed January 13, 1894—after the period of one year in question had elapsed—amounts to nothing; and we discover no other allegation by which the defect is supplied. It is found that the expenditures made by defendant for such repairs occurred between January 9, 1893, and January 9, 1894. Unless the damage thus arising from the failure of the contractor to keep the pipe in repair accrued at least as early as notice to the defendant of the assignment to plaintiff of the demand sued upon, then such damage could not be counterclaimed in this action at all—assuming that the substance of the contract between defendant and the Silver Grate Manufacturing Company is correctly set forth in the findings before us; for it appears that the agreement of the defendant to pay the contract price in thirty-five
It is not clear whether like effect would follow the assignment made by the original contractor to the .¿Etna Iron and Steel Company in 1892, and of which notice was had by defendant at least as early as May 2, 1893; for it may be surmised from some parts of the record that there was perhaps a mere novation of the .¿Etna company for the Silver Gate Manufacturing Company in the contract; and, if so, of course such assignment would not affect the right of setoff. If it becomes material, the nature of that assignment can be determined on another trial.
The judgment and order appealed from are reversed and the cause remanded for a new trial with leave to any of the parties to amend its pleadings, and it is so ordered.
Hearing in Bank denied.