114 N.W. 1085 | N.D. | 1908
Action to foreclose a lien for materials furnished for a building by the plaintiff as a subcontractor. The plaintiff re
The appellants .contend that the complaint fails to state a cause of action for the foreclosure of a mechanic’s lien. Their contention on this point is that the complaint fails to allege that the plaintiff did give notice to Ertresvaag that it had furnished to the contractor the materials for the furnishing of which a lien is claimed prior to the filing of the lien and prior to the completion of the building. The complaint alleges that the notice was given on March 15, 1904, and that the lien was filed on March 10th. There was no demurrer to the complaint, and no objection was made to the introduction of evidence under the complaint prior to the taking of testimony, nor was this objection urged during the trial by an ■objection specifically based on the fact that the complaint showed that the lien was filed before any notice was given. We are of the opinion that this objection to the sufficiency of the allegations of the complaint comes too late when raised for the first time in the Supreme Court. The uncontradicted facts are that the lien was filed on March 11th and that the notice was sent by registered letter, as required by section 6237, Rev. Codes 1905, on March 10th. If objection had been made, and the attention of the court called to the variance between the allegations of the complaint and the evidence, an amendment of the complaint would have been proper and undoubtedly allowed. Appellants claim that this testimony was objected to. Nowhere was the ground of the objection specifically pointed out. The objection was that the testimony was incompetent, irrelevant and immaterial. This objection was too general, and did not apprise the court or opposing counsel of the real ground of the objection. It is now generally held that objections in this form are not specific enough, and that error cannot be predicated upon rulings overruling them. This court has also held objections in that form not subject to assignment of error when overruled. Kolka v. Jones, 6 N. D. 461, 71 N. W. 558, 66 Am. St. Rep. 615.
Conceding, for the purposes of this appeal, that the evidence was inadmisible under the allegations of the complaint, we are satisfied that objections thereto come too late when first presented on appeal. By not objecting in time, and specifically pointing out
When the building was completed was not a matter dependent upon any action or knowledge of the owner of the building. That fact did not rest upon any fact particularly within the knowledge of the owner, and dependent in no way upon any act of his in connection with that of the contractor. The completion of the building
It is shown that the last date of the furnishing of the brick by the plaintiff was on October 17, 1903. The ninety days during which the subcontractor had to file a lien so as to protect his lien against purchasers and incumbrancers and the owner, if he made payments after the 90 days, expired on February 17, 1904. Payments made by the owner before February 17th could not be made to defeat the plaintiff’s right to a lien, providing the lien was filed within the 90 days. Payments made after February 17th and before March 11th, when the lien was filed, would have been made by the owner without regard to the plaintiff’s right to the lien. Payments made after March 11th could not have been made so as to defeat plaintiff’s lien. The administrator testifies that the sum of $9,004.19 was paid between October 17, 1903, and March 10, 1904. How much of this sum was paid before February 17th, or how much after that day and before March 11th, is not shown. It is shown, however, that about $1,800 was paid some time in February, after the 90 days had expired; and, according to the administrator’s evidence this was the last payment, and paid the contract price in full. The payment was far in excess of all sums claimed to be due the plaintiff by virtue of having furnished the materials for the building, for which the plaintiff claims a lien. The respondent’s contention that the owner could not make payments during the 90 days at the expense of the subcontractor is true, providing the lien is filed within the 90 days, but in this case the owner did not make payment in full until about one month after
Respondent also contends that the witness was not a party to the action, nor prohibited from testifying, within the meaning of said section 7253. The contention is that his testimony was admissible on the theory that he was called by the opposite party, the plain
The judgment is reversed as to defendant Hilliboe, and the action dismissed as to him only.